Fireman's Fund Insurance Company v. Gordon R. England, Secretary of the Navy

313 F.3d 1344, 2002 U.S. App. LEXIS 24238, 2002 WL 31662778
CourtCourt of Appeals for the Federal Circuit
DecidedNovember 27, 2002
Docket00-1420
StatusPublished
Cited by47 cases

This text of 313 F.3d 1344 (Fireman's Fund Insurance Company v. Gordon R. England, Secretary of the Navy) is published on Counsel Stack Legal Research, covering Court of Appeals for the Federal Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Fireman's Fund Insurance Company v. Gordon R. England, Secretary of the Navy, 313 F.3d 1344, 2002 U.S. App. LEXIS 24238, 2002 WL 31662778 (Fed. Cir. 2002).

Opinion

FRIEDMAN, Senior Circuit Judge.

After a contractor defaulted on a government construction contract, the surety entered into a takeover agreement and completed the work. The government assessed liquidated damages against the surety for delays in doing its work. The contracting officer rejected the surety’s challenges to the liquidated damages, and the surety appealed that action to the Board of Contract Appeals (“Board”). The Board dismissed the portion of the claims relating to delays before the takeover agreement, and in this appeal the surety challenges that ruling. We (1) hold that the Board’s action was a final decision that we have jurisdiction to review, and (2) affirm the Board’s dismissal of the pre-takeover claims.

I

The United States Navy and Summit General Contracting Corp. (“Summit”) entered into a contract in 1988 for Summit to construct a government building. Fireman’s Fund Insurance Company (“Fireman’s Fund”) was the surety and provided performance and payment bonds. Summit and Fireman’s Fund executed a “General Indemnity Agreement” under which, in case of a breach of the construction contract, Summit assigned to Fireman’s Fund “all of their rights under the contracts ... including their right, title and interest in and to ... all actions, causes of actions, claims and demands whatsoever which the Principal may have in anyway arising out of or relating to such Bond, or contract covered by such Bond.”

The government terminated the contract for default on January 16, 1990, after Summit failed to complete the contract by the scheduled date. The government and Fireman’s Fund entered into a takeover agreement on April 17, 1990, under which Fireman’s Fund agreed to complete the contract. Summit was not a party to that contract, which did not mention the Gener *1347 al Indemnity Agreement or its assignment of claims to Fireman’s Fund.

Fireman’s Fund submitted a claim to the contracting officer seeking an “equitable adjustment and/or rescission of assessed liquidated damages.” Its claims all related to delays in performance that the government allegedly caused, both before and after the takeover agreement. The contracting officer denied all the claims, and Fireman’s Fund appealed to the Board.

On the government’s motion, the Board dismissed the claims that arose before the takeover agreement. The Board held that Fireman’s Fund was not a “contractor” under the Contract Disputes Act who could invoke that Act to assert those claims, and that the Board thus lacked jurisdiction over those claims. The Board also ruled that Summit’s assignment of-its claims to Fireman’s Fund under the General Indemnity Agreement was barred by the Anti-Assignment Act. Finally, the Board rejected Fireman’s Fund’s claim of equitable subrogation, determining the doctrine was inapplicable.

After the Board denied Fireman’s Fund’s motion for reconsideration on May 2, 2000, Fireman’s Fund appealed to this court. Thereafter, on March 5, 2001-, the Board dismissed the remaining appeal (which involved delays after the takeover agreement) without prejudice, but provided that the dismissal would be with prejudice, unless within three years either party sought to reinstate the appeal or the court itself did so.

II

In reviewing decisions of trial tribunals, federal appellate courts treat as “final decisions” reviewable under 28 U.S.C. § 1291 only those decisions that fully dispose of all the claims in the case. Teller Envtl. Sys., Inc. v. United States, 802 F.2d 1385, 1388 (Fed.Cir.1986). A trial court decision that “adjudicates fewer than all the claims or the rights and liabilities of fewer than all the parties” is not final unless the trial court certifies it as such. Fed.R.Civ.P. 54(b). As the standard frequently is stated: “[flinality classically has required that the appealed order end the litigation on the merits and leave nothing for the court to do but execute judgment.” Kinetic Builder’s Inc. v. Peters, 226 F.3d 1307, 1312 (Fed.Cir.2000) (citations omitted). Under this standard, the Board’s decision on appeal in this case would not be final because it did not dispose of all the claims pending before the tribunal.

“Although this classical finality requirement is strictly imposed on district court decisions, it is not imposed with exact congruence on Board decisions.” Id. at 1313 (citations omitted). In determining the “finality” of Board decisions that completely dispose of less than all the claims, we have focused not on whether the decision disposed of the entire “case,” but on its impact on the particular claims and their relationship to the Board’s administrative proceeding. “[F]inality of a Board decision can be found ‘where the process of the Board decisionmaking has reached a stage where judicial review will not disrupt the orderly process of adjudication and where rights or obligations have been determined or legal consequences will flow from the agency action.’” Id. (quoting Dewey Elecs. Corp. v. United States, 803 F.2d 650, 654 (Fed.Cir.1986)).

Consistent with this analysis, we have held that a Board decision adjudicating the merits of nine claims but remanding five of them (upon which the contractor prevailed) to the contracting officer to determine damages was final with respect to the four claims that the Board decided against the contractor. Dewey Elecs., 803 F.2d at 653. *1348 We “h[e]ld that the Board made a final decision on the four claims that are the subject of this appeal and that appeal should not be deferred pending resolution of quantum for the five claims remanded.” Id. This court refused to make “the finality concept of district court litigation, requiring both liability and damages to be resolved before an appeal ... applicable to agency board proceedings.” Id. at 654. It stated that:

the Board here, in disposing of all of the entitlement questions, fully addressed all of the decisions (constructively made) of the contracting officer then on appeal to the Board. In the words of the Supreme Court, “there was no possible disruption of the administrative process; there was nothing else for the [Board] to do.”

Id. at 658 (quoting Marine Terminal Ass’n v. Rederiaktiebolaget Transatlantic, 400 U.S. 62, 71, 91 S.Ct. 203, 27 L.Ed.2d 203 (1970)).

Our decisions have treated as final (and hence appealable) Board decisions in various situations that have decided less than all the issues before the Board. See, e.g., Kinetic Builder’s,

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Miller v. United States
Federal Claims, 2025
Trinity Source Logistics LLC
Armed Services Board of Contract Appeals, 2022
Guarantee Company of North v. Ikhana, LLC
941 F.3d 1140 (Federal Circuit, 2019)
Cooper/Ports America, LLC
Armed Services Board of Contract Appeals, 2018
Team Systems International, LL v. Jeff Haozous
656 F. App'x 907 (Tenth Circuit, 2016)
Anchor Savings Bank, FSB v. United States
121 Fed. Cl. 296 (Federal Claims, 2015)
Textainer Equipment Management Limited v. United States
115 Fed. Cl. 708 (Federal Claims, 2014)
Council for Tribal Employment Rights v. United States
112 Fed. Cl. 231 (Federal Claims, 2013)
Red Hawk Construction, Inc. v. United States
108 Fed. Cl. 779 (Federal Claims, 2013)
Insurance Co. of the West v. United States
100 Fed. Cl. 58 (Federal Claims, 2011)

Cite This Page — Counsel Stack

Bluebook (online)
313 F.3d 1344, 2002 U.S. App. LEXIS 24238, 2002 WL 31662778, Counsel Stack Legal Research, https://law.counselstack.com/opinion/firemans-fund-insurance-company-v-gordon-r-england-secretary-of-the-cafc-2002.