Guarantee Company of North v. Ikhana, LLC

941 F.3d 1140
CourtCourt of Appeals for the Federal Circuit
DecidedOctober 29, 2019
Docket18-1394
StatusPublished

This text of 941 F.3d 1140 (Guarantee Company of North v. Ikhana, LLC) is published on Counsel Stack Legal Research, covering Court of Appeals for the Federal Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Guarantee Company of North v. Ikhana, LLC, 941 F.3d 1140 (Fed. Cir. 2019).

Opinion

United States Court of Appeals for the Federal Circuit ______________________

GUARANTEE COMPANY OF NORTH AMERICA, USA, Appellant

v.

IKHANA, LLC, Appellee ______________________

2018-1394 ______________________

Appeal from the Armed Services Board of Contract Ap- peals in Nos. 60462, 60463, 60464, 60465, 60466, 61102, Administrative Judge James R. Sweet. ______________________

Decided: October 29, 2019 ______________________

PATRICK MICHAEL PIKE, Pike & Gilliss LLC, Towson, MD, argued for appellant.

WILLIAM ATKINS SCOTT, Pederson & Scott, P.C., Charleston, SC, argued for appellee. ______________________

Before DYK, WALLACH, and HUGHES, Circuit Judges. Opinion for the court filed by Circuit Judge HUGHES. 2 GUARANTEE COMPANY OF NORTH AMERICA v. IKHANA, LLC

Concurring opinion filed by Circuit Judge WALLACH, in which Circuit Judge DYK joins. HUGHES, Circuit Judge. This case involves a government contract dispute. Af- ter a contracting officer determined that Ikhana, LLC de- faulted on a construction contract with the Army Corps of Engineers, Ikhana filed an appeal to the Armed Services Board of Contract Appeals. Guarantee Company of North America (GCNA), a surety that indemnified Ikhana, moved to intervene because the indemnity agreement authorized it to assume all contractual rights in the event of default. The Board denied GCNA’s motion, finding that GCNA lacked standing. Appeals of Ikhana, LLC, ASBCA No. 60462, 17-1 BCA ¶ 36,871 (Oct. 18, 2017). Because GCNA executed its settlement agreement with the Corps after the claims at issue arose, we affirm. I In September 2013, the United States Army Corps of Engineers awarded Ikhana a construction contract to build a secured access lane and remote screening facility at the Pentagon by October 12, 2015. The contract required Ikhana to furnish performance and payment bonds. Ikhana procured these bonds from GCNA. As a condition for issuing the bonds, GCNA required Ikhana to execute a general indemnity agreement. The in- demnity agreement included a provision that assigned GCNA all rights under the contract if Ikhana defaulted or if GCNA made payment on any bond. Construction did not go as planned. As Ikhana began working on the project, it encountered multiple problems with the work site that were not in the contract’s specifica- tion. Each time Ikhana discovered a new problem, it had to halt work until the Corps issued a unilateral change to the contract. These stoppages and contract modifications caused significant delays and cost overruns. One GUARANTEE COMPANY OF NORTH AMERICA v. IKHANA, LLC 3

modification required the Corps to schedule a power outage at the Pentagon for the project to continue, but the Corps never scheduled the outage, and by mid-October 2015, con- struction had stopped. Between October 13–27, 2015, Ikhana submitted four claims to the contracting officer seeking additional com- pensation and an extension of the project deadline. Ikhana argued that the unforeseen site conditions and unilateral changes to the contract significantly altered the scope of the contract. The Corps never issued a final decision on Ikhana’s claims. Between November 2015 and June 2016, seven of Ikhana’s sub-contractors filed claims against GCNA’s pay- ment bond. Corps terminated Ikhana for defaulting on the contract and made a claim on the performance bond. On February 25, 2016, Ikhana appealed the termination deci- sion and its four claims for additional compensation to the Armed Services Board of Contract Appeals. GCNA sent Ikhana a letter demanding collateral under the indemnity agreement. The letter stated that if Ikhana did not deliver over four million dollars in collateral, “GCNA [would] take all appropriate steps to protect its rights” under the indemnity agreement. J.A. 292. Ikhana responded that the demand for collateral was premature and unreasonably high. GCNA and the Corps began to negotiate for GCNA to tender a completion contractor. During the negotiations, Ikhana informed GCNA that it would “not [forgo] its claim against the Corps under any circumstances.” J.A. 444. GCNA invoked its powers under the indemnity agreement and entered into a settlement agreement with the Corps on September 30, 2016. As part of the settlement agreement, GCNA agreed to “cause the dismissal, with prejudice, of the current pending appeals before the [Board].” J.A. 365. 4 GUARANTEE COMPANY OF NORTH AMERICA v. IKHANA, LLC

GCNA sued Ikhana for declaratory judgment in the United States District Court for the Eastern District of Vir- ginia. GCNA sought a declaration that the indemnity agreement authorized it to “settle [Ikhana’s] dispute with the [Corps] and dismiss the [Board] appeal.” Guarantee Co. of N. Am. USA v. Ikhana, LLC, No. 1:16-CV-1484, 2017 WL 1821106, at *2 (E.D. Va. May 4, 2017). The district court stayed GCNA’s action pending resolution of Ikhana’s Board appeal. Id. at *4. GCNA moved to intervene and withdraw Ikhana’s ap- peal before the Board on the grounds that Ikhana had as- signed all contractual claims to GCNA. Ikhana opposed the motion. The Board denied the motion because GCNA lacked standing. GCNA now appeals from the order denying interven- tion. We have jurisdiction over the Board’s final decision under 28 U.S.C. § 1295(a)(10) and 41 U.S.C. § 7107(a)(1). II We review the Board’s conclusions of law de novo. Win- ter v. Bath Iron Works Corp., 503 F.3d 1346, 1350 (Fed Cir. 2007). The Board’s jurisdictional determinations are con- clusions of law. England v. Swanson Grp., Inc., 353 F.3d 1375, 1378 (Fed. Cir. 2004). “The Board’s jurisdiction is defined by the Contract Disputes Act [(CDA)]. Parties can- not, by agreement, confer upon a tribunal jurisdiction that it otherwise would not have.” United Pac. Ins. Co. v. Roche, 380 F.3d 1352, 1356 (Fed. Cir. 2004). The issue here is whether the Board correctly denied GCNA’s attempt to intervene and replace Ikhana as the appellant. The Board’s rules of procedure do not include instructions for third-party practice. See In Re S. Powell Constr. Co., AGBCA No. 2004-122-1, 04-2 BCA ¶ 32,725 (Aug. 26, 2004). The limited Board decisions on the subject do not provide any clear guidance over what standards the Board uses for determining the propriety of intervention or GUARANTEE COMPANY OF NORTH AMERICA v. IKHANA, LLC 5

whether intervention is even permitted. See id. (collecting cases and discussing intervention under the CDA). But while the scope of third-party practice rules is murky, the outer bounds are limited by the Federal Rules of Civil Pro- cedure, which the Board may adopt at its discretion. Id. A party seeking to supplant the plaintiff must be able to show that it could have initiated the complaint on its own. Cf. United States v. 936.71 Acres of Land, More or Less, in Bre- vard Cty., State of Fla., 418 F.2d 551, 556 (5th Cir. 1969) (noting that the real-party-in-interest requirement applies equally to intervenors as it does to plaintiffs). Thus, GCNA cannot commandeer Ikhana’s appeal if it could not directly appeal the contracting officer’s decisions to the Board un- der the CDA. As explained below, we find that GCNA fails to meet this threshold requirement.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
941 F.3d 1140, Counsel Stack Legal Research, https://law.counselstack.com/opinion/guarantee-company-of-north-v-ikhana-llc-cafc-2019.