Winter v. FloorPro, Inc.

570 F.3d 1367, 2009 U.S. App. LEXIS 13824, 2009 WL 1812782
CourtCourt of Appeals for the Federal Circuit
DecidedJune 26, 2009
Docket2008-1407
StatusPublished
Cited by54 cases

This text of 570 F.3d 1367 (Winter v. FloorPro, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals for the Federal Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Winter v. FloorPro, Inc., 570 F.3d 1367, 2009 U.S. App. LEXIS 13824, 2009 WL 1812782 (Fed. Cir. 2009).

Opinion

PROST, Circuit Judge.

In this case, we are presented with the question of whether the Contract Disputes Act of 1978 (“CDA”) gives the Armed Services Board of Contract Appeals (“Board”) jurisdiction over a claim against the government brought by a subcontractor that is a third-party beneficiary of a contract between the government and the prime contractor. For the reasons stated below, we hold that it does not.

I. BACKGROUND

On February 6, 2002, the Navy awarded a contract for the installation of floor coating at warehouse bays on a military base to G.M. & W. Construction Corp. (“GM & W”), a minority-owned business qualifying under section 8(a) of the Small Business Act. The Navy agreed to pay GM & W $42,000 for the completion of the work. FloorPro, Inc., which is not a section 8(a) contractor, entered into a subcontract agreement with GM & W on February 11, 2002. Under the terms of the subcontract, FloorPro agreed to perform the work specified by the Navy’s contract with GM & W for $37,500.

FloorPro completed all of the work under the contract by February 27, 2002, and submitted its invoice to GM & W on March 6, 2002. On March 8, 2002, the government’s contracting officer notified GM & W that the work had been completed satisfactorily. The government received GM & W’s request for payment on April 16, 2002. The next day, FloorPro informed the government that GM & W had not paid its invoice on the subcontract. On April 22, 2002, the government’s contracting officer called GM & W to inquire about GM & W’s failure to pay FloorPro. GM & W informed the contracting officer that there were various pending claims against it and that it did not know whether it would be able to use funds deposited into its account to pay FloorPro. Accordingly, the government and GM & W agreed to modify the original contract, which provided for payment to be made directly to GM & W, to specify that the government would issue a two-party check made payable to both FloorPro and GM & W. This agreement was executed by GM & W and the government as Modification No. P00001 on April 22, 2002.

Notwithstanding the modification, the government paid GM & W directly. On July 18, 2002, the contracting officer notified FloorPro that the payment had not been made by two-party check. Several weeks later, the contracting officer confirmed to FloorPro that GM & W had been *1369 paid in full. Thereafter, FloorPro’s attorney sent a letter to the contracting officer that purported to be a claim for payment based on the government’s alleged violation of the contract modification. The government declined to issue a decision on FloorPro’s claim because it did not have a contract with FloorPro.

On March 27, 2003, FloorPro filed an appeal against the government with the Board. . The underlying claim was hot sponsored by GM & W. 1 The government filed a motion to dismiss in which it alleged that the Board lacked jurisdiction over FloorPro’s appeal. Specifically, the government argued that the CDA only authorizes appeals to the Board taken by “contractors,” and thus claims brought by FloorPro, a subcontractor, are outside the Board’s jurisdiction. The Board denied the government’s motion, concluding that FloorPro was an intended third-party beneficiary of the contract modification and, therefore, could file a claim even in the absence of contractual privity. In re FloorPro, Inc., ASBCA No. 54143, 2004 WL 691691, 04-1BCA ¶ 32571, 2004 ASBCA LEXIS 23 (Mar. 30, 2004) (“Floor-Pro I”). The Board subsequently determined that there were no genuine issues of material fact with respect to whether the government was liable to FloorPro for breaching the payment provision. In re FloorPro, Inc., ASBCA No. 54143, 2007 WL 1978045, 07-2 BCA ¶ 33615, 2007 ASBCA LEXIS 38 (June 27, 2007) (“Floor-Pro II”). Accordingly, it granted summary judgment in favor of FloorPro and awarded $37,500 plus interest. Id. Following the Board’s decision in FloorPro II, the government moved for reconsideration of the Board’s conclusions with respect to jurisdiction and FloorPro’s status as a third-party beneficiary of the contract modification. The Board reaffirmed its prior decisions on both grounds. In re FloorPro, Inc., ASBCA No. 54143, 2008 WL. 436927, 08-1 BCA ¶33793, 2008 ASBCA LEXIS 12 (Feb. 8, 2008) {“Floor-Pro III”).

The government timely appealed. We have jurisdiction' under 28 U.S.C. § 1295(a)(10).

II. DISCUSSION

“The determination of jurisdiction under the CDA is a question of law. It is therefore subject to de novo review.” England v. Swanson Group, Inc., 353 F.3d 1375, 1378 (Fed.Cir.2004).

The CDA was enacted to “provide! ] a fair, balanced, and comprehensive statutory system of legal and administrative remedies in resolving government contract claims.” Contract Disputes Act of 1978, S.Rep. No. 95-1118, at 1 (1978), as reprinted in 1978 U.S.C.C.A.N 5235, 5235. Under the CDA, a contractor has two possible avenues of appeal after an adverse decision from a contracting officer. Id. at 2. First, the contractor may file an appeal with an agency board of contract appeals. 41 U.S.C. § 606. In the alternative, the contractor may file a claim against the government in the United States Court of Federal Claims. Id. § 609(a). Importantly, these provisions apply only to those who are “contractors” within the meaning of the CDA, which defines the term to mean “a party to a Government contract other than the Government.” Id. § 601(4); see also Admiralty Constr., Inc. v. Dalton, 156 F.3d 1217, 1220 (Fed.Cir.1998) (“[T]he *1370 Act emphasizes that only a ‘contractor’ may appeal the decision of a contracting officer.”). Moreover, the CDA only applies to “express or implied eontract[s] ... entered into by an executive agency.” 41 U.S.C. § 602(a); see also Admiralty Constr., 156 F.3d at 1221 (surety could not appeal a contracting officer’s decision under the CDA because “it cannot show that it ‘entered into’ a contract with ‘an executive agency’ ”).

In this case, the Board determined that FloorPro was not in contractual privity with the government. FloorPro III, 2008 WL 436927, 2008 ASBCA LEXIS 12, at *3-4 (‘We agree[] that Modification No.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Racer Machinery International
Armed Services Board of Contract Appeals, 2026
Frontline Support Solutions, LLC
Armed Services Board of Contract Appeals, 2025
Crawford v. Clay (MAG+)
M.D. Alabama, 2024
percipient.ai, Inc. v. United States
104 F.4th 839 (Federal Circuit, 2024)
GLJ, Inc.
Armed Services Board of Contract Appeals, 2024
United Aeronautical Corp. v. Usaf
80 F.4th 1017 (Ninth Circuit, 2023)
Contrack Watts-Uejo Kogyo JV
Armed Services Board of Contract Appeals, 2022
Trinity Source Logistics LLC
Armed Services Board of Contract Appeals, 2022
Davis v. US Marshals Srv
Fifth Circuit, 2021

Cite This Page — Counsel Stack

Bluebook (online)
570 F.3d 1367, 2009 U.S. App. LEXIS 13824, 2009 WL 1812782, Counsel Stack Legal Research, https://law.counselstack.com/opinion/winter-v-floorpro-inc-cafc-2009.