American Government Properties and Houma Ssa, LLC v. United States

118 Fed. Cl. 61, 2014 U.S. Claims LEXIS 868
CourtUnited States Court of Federal Claims
DecidedAugust 28, 2014
Docket1:09-cv-00153
StatusPublished
Cited by3 cases

This text of 118 Fed. Cl. 61 (American Government Properties and Houma Ssa, LLC v. United States) is published on Counsel Stack Legal Research, covering United States Court of Federal Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
American Government Properties and Houma Ssa, LLC v. United States, 118 Fed. Cl. 61, 2014 U.S. Claims LEXIS 868 (uscfc 2014).

Opinion

Contracts; Contracts Act, 41 U.S.C. § 6305, Prohibition of assignment of contracts with the federal government.

OPINION

ERIC G. BRUGGINK, Judge

This case concerns a contract to design, build, and then lease to the Social Security Administration (“SSA”) an office building in Houma, Louisiana. The General Services Administration (“GSA”) terminated the contract for default, citing lack of progress in construction. This case was filed along with three others also involving contracts to design, build, and lease office buildings in Louisiana to the SSA 1 Plaintiffs in each case were terminated for default and now allege that the termination was improper and seek damages as a result of defendant’s alleged breach of the contract. Defendant has moved to dismiss two of the cases, including this one, on the grounds of an improper assignment. In this case, the allegation is that the contract was assigned to Houma SSA, LLC (“Houma”) by American Government Properties (“AGP”), the original con-traeting party, in violation of the Contracts Act’s prohibition against assignments, 2 or, in the alternative, that one or both of the two plaintiffs lack standing. 3 Because we agree that the assignment from AGP to Houma violated the Contracts Act, we grant the motion to dismiss.

BACKGROUND

The General Services Administration (“GSA”) awarded Lease No. GS-07B-15580 to AGP on June 16, 2005. The contract called for AGP to design and build a 12,206 rentable square feet office facility in Houma, Louisiana and then lease it to SSA

On July 27, 2005, AGP executed a document entitled “Assignment of U.S. Government Real Property Lease” with Houma, a newly formed Louisiana limited liability company. AGP was the sole member of Houma. The assignment document stated that the assignor, AGP, “assign[ed] all of its contractual rights and interests under the Lease.” Def.’s App. 223. The assignee, Houma, agreed “to perform all of the obligations of Lessor under the Lease.” Id. Houma, as assignee, also agreed to “take all steps necessary to ensure that this Assignment is reflected in the records of the United States Government.” Id.

GSA provided final design drawings in late June 2006. See Def.’s App. 248-49 (emails between GSA, SSA and plaintiffs’ subcontractor regarding the design drawings). GSA issued the notice to proceed on March 1. 2007.

By September 2007, the parties were discussing possibilities for plaintiffs and their general contractor, Carotex Construction, Inc., to extricate themselves from the lease and several other related projects on which Carotex was the general contractor. Victor *64 Blackmon, a principal of plaintiffs and Caro-tex, inquired about selling and assigning the leases or mutually terminating them. See Def.’s App. 251-52 (email chain between Blackmon and GSA). On September 20, 2007, however, Mr. Blackmon proposed a construction schedule culminating in delivery of the facility to SSA for move-in on February 18, 2008. The parties proceeded down that path with AGP/Houma/Carotex building the facility.

In October 2007, the contracting officer at that time, Nancy Lopez, and Mr. Blackmon discussed by email the assignment from AGP to Houma. Ms. Lopez inquired whether Houma/AGP had sent to GSA the necessary paperwork documenting the assignment. If not, she asked for a copy of the assignment agreement between AGP and Houma. Mr. Blackmon replied that he would look through company files and send a copy of a Supplemental Lease Agreement (“SLA”) in which, he said, GSA agreed to substitute Houma for AGP. See Def.’s App. 259-60. Neither party has produced a copy of such an SLA nor is there any evidence, other than this email exchange, that one was executed.

GSA and plaintiffs did, however, execute a SLA regarding a different matter on November 8, 2007, in which the parties agreed that GSA would conduct a site visit and inspection of the concrete slab on November 12, and that plaintiff would deliver the Houma facility on February 18, 2008. Def.’s App. 261 (SLA No. 1). Less than a week later, GSA sent a cure notice to Carotex, stating that the inspection revealed that no construction progress had been made since the last site visit on August 10, 2007. Def.’s App. 274 (November 16, 2007 cure notice). The notice warned that GSA was considering terminating the contract for default and instructed Mr. Blackmon that he had ten days “to present, in writing, any facts bearing on the question” of whether the “failure to perform arose from causes beyond your control and without fault or negligence on your part.” Def.’s App. 275.

Mr. Blackmon responded to the cure notice in a November 26, 2007 email to Ms. Lopez, stating that Houma had experienced 34 days of rain delay since September 1, 2007, and that all the necessary building permits were not received until October 8, 2007. Def.’s App. 278. He asked for credit for 23 days of rain delay and a concomitant extension. Further, he promised to provide a new schedule and supporting information by November 30, 2007. He also promised to provide more information regarding the chronology of the project and the impact of the various events on the project’s time line within two weeks of his email. Id. at 279.

Plaintiffs and Carotex continued to work through problems with subcontractors and the various building permits. An internal Carotex email from project manager Jesse LeBlanc indicated that Houma had these issues largely worked out by December 21, 2007, and that the “only loose end” remaining was an electrical contractor. Def.’s App. 280. GSA conducted site visits in December 2007 and January 2008.

On February 21, 2008, GSA sent another letter to AGP, detailing the various deadlines not met, problems with the concrete slab, and failure to respond to the previous notice with the promised information. GSA once again warned of a likely termination for default and instructed AGP to provide information within 10 days regarding whether it was at fault.

Plaintiffs responded on March 4, 2008, through a Carotex employee, John Kim-brough, writing on Houma letterhead. In that letter, AGP/Houma reported that plaintiffs had hired a structural engineer to report on the concrete slab and that another nine yards remained to be poured. The next day, Mr. Kimbrough sent a revised schedule extending the completion date to June 18, 2008.

The contracting officer responded by letter dated March 12, 2008, terminating the contract for default pursuant to GSA Regulation (“GSAR”) 552.270-18, which was incorporated into the contract by reference, citing, among other things, failure to complete the project by the February 21,2008 date agreed to in SLA No. 1 and failure to submit information regarding the delays and problems noted in the November 2007 cure notice. The agency then sought bids for a replace *65 ment contractor to design, build, and lease a facility in Houma, Louisiana.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
118 Fed. Cl. 61, 2014 U.S. Claims LEXIS 868, Counsel Stack Legal Research, https://law.counselstack.com/opinion/american-government-properties-and-houma-ssa-llc-v-united-states-uscfc-2014.