Allied Signal, Inc. v. The United States

941 F.2d 1194, 37 Cont. Cas. Fed. 76,141, 1991 U.S. App. LEXIS 16693, 1991 WL 138502
CourtCourt of Appeals for the Federal Circuit
DecidedJuly 29, 1991
Docket90-1324
StatusPublished
Cited by2 cases

This text of 941 F.2d 1194 (Allied Signal, Inc. v. The United States) is published on Counsel Stack Legal Research, covering Court of Appeals for the Federal Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Allied Signal, Inc. v. The United States, 941 F.2d 1194, 37 Cont. Cas. Fed. 76,141, 1991 U.S. App. LEXIS 16693, 1991 WL 138502 (Fed. Cir. 1991).

Opinion

PLAGER, Circuit Judge.

Allied Signal, Inc. (Allied) appeals from the November 1, 1989 decision of the Armed Services Board of Contract Appeals (ASBCA or Board) which granted the government’s motion for partial summary judgment. Allied had disputed the government’s right to withhold progress payments due under its contract with the government. The government withheld the payments after concluding, in light of a separate dispute with Allied regarding the terms of the contract, that Allied was already overpaid on the underlying contract. We affirm the decision of the ASBCA.

I. BACKGROUND

In 1982, Allied was awarded a multi-year fixed price contract for development and production of a trainer aircraft engine. The contract included an Economic Price Adjustment (EPA) clause. The EPA clause allowed for adjustment of the target cost and ceiling values, within specified parameters, for fiscal years 1984 through 1988. The contract also included a Defense Acquisition Regulation (DAR) Progress Payment clause.

On August 27 and 28,1987, the Air Force contracting officer (CO) issued modifications to the contract, reducing the contract price pursuant to the government’s inter *1195 pretation of the EPA clause. Allied disputed the amount of the price adjustments on September 11, 1987.

Soon after, in a letter dated September 23, 1987, the Administrative Contracting Officer (ACO) refused to pay two of Allied’s requests for progress payments. The ACO also notified Allied that, as a result of the reduction in contract price, Allied had been overpaid by progress payments already made by the government, and that Allied owed the overpaid amount, plus applicable interest, to the government. On January 28, 1988, Allied submitted a certified claim to the ACO, disputing the refusal to make progress payments. The ACO denied the claim on May 6, 1988. Allied appealed to the ASBCA on July 12, 1988.

In the meantime, on May 2, 1988, Allied submitted to the CO a certified claim disputing the amount of the price adjustment and the government’s interpretation of the EPA clause. The CO denied this claim on January 19, 1989. Allied appealed this denial to the ASBCA on April 13, 1989.

In the first appeal before the ASBCA, regarding the withheld progress payments, both parties filed cross-motions for partial summary judgment. The motions dealt with the applicability of the procedural requirements in the Debt Collection Act of 1982, 31 U.S.C. § 3701 et seq. (DCA), and DAR Appendix E. These provisions relate to a situation in which the government seeks to collect on a contractual indebtedness by withholding or offsetting amounts otherwise payable under a contract. By decision dated November 1, 1989, the ASBCA granted the government’s motion and held that the procedural requirements of neither the DCA nor DAR Appendix E applied. The ASBCA, citing Fairchild Republic Company, ASBCA No. 29385, 85-2 BCA (CCH) ¶ 18,047,1985 WL 16623 {Fair-child I), clarified on reconsideration, 86-1 BCA (CCH) ¶[ 18,608, 1985 WL 17233 (ASBCA 1985) {Fairchild II), appeal dismissed, 810 F.2d 1123 (Fed.Cir.1987) {Fairchild III), reasoned that the withholding of progress payments was an act of contract administration rather than collection of a debt as contemplated by the DCA and DAR provisions. On advice from both parties, the ASBCA later issued an Order of Dismissal dated February 2, 1990, dismissing the remaining issues in this first appeal as “moot” in light of the November 1 decision. Allied appealed to this court.

II. ALLIED’S APPEAL

Allied appeals the ASBCA’s holding that the DCA and DAR provisions do not apply to the withheld progress payments. Allied’s second appeal before the ASBCA, regarding the underlying interpretation of the EPA clause and the concomitant price adjustment, was not yet decided at the time Allied filed the present appeal before this court. The issues in that second appeal to the ASBCA are not now before us.

A. Is the Decision of the ASBCA a Final Decision For Jurisdiction Purposes?

The government argues that we should not reach the merits of this case, citing Fairchild Republic Company v. U.S., 810 F.2d 1123 (Fed.Cir.1987) {Fairchild III). In Fairchild III, contractor Fairchild appealed to this court from a decision of the ASBCA upholding the government’s right to withhold progress payments, and consequently denying Fair-child’s motion for summary judgment. The ASBCA held there, as it did here, that the DCA and DAR Appendix E were inapplicable. There, however, the ASBCA had not yet considered a second issue which was before it in the same action&emdash;whether the government had properly determined that there was defective pricing by the contractor.

On review, because this court may only review “final decisions”, see United States v. W.H. Moseley Co., 730 F.2d 1472, 1474 (Fed.Cir.1984), the court dismissed Fair-child’s appeal, without prejudice, on the grounds that the ASBCA decision was not a final decision on all the issues before the Board in that action. 810 F.2d at 1125. Further, in response to an argument that this situation comes under the Cohen exception to the usual rule on finality, see *1196 Cohen v. Beneficial Indus. Loan Corp., 337 U.S. 541, 546, 69 S.Ct. 1221, 1225, 93 L.Ed. 1528 (1949), the court noted that

Fairchild’s claim that the government improperly withheld the amount of the defective pricing is not completely separate from the merits of the claim of defective pricing [ — also before the Board in the same proceeding]. Both issues arose out of interrelated conduct and the same or closely connected facts_ Furthermore, Fairchild has failed to indicate any reason why the board’s decision on withholding cannot be reviewed at the time a final decision on the defective pricing issue is entered. Whether or not Fair-child prevails on the defective pricing claim, it may then appeal the [then final] ASBCA decision regarding withholding and seek as a remedy interest from the date of withholding for loss of use of its money.

810 F.2d at 1126 (citations omitted). The court also concluded that “a considerable savings in judicial resources can be achieved by waiting to consider both of Fairchild’s ‘claims’ [involved in a single action before the ASBCA] in one appeal [of that action].” 810 F.2d at 1126.

Unlike the setting in Fairchild, Allied’s claim here regarding withholding has been pursued in a completely separate action from Allied’s claim regarding interpretation and application of the EPA clause.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
941 F.2d 1194, 37 Cont. Cas. Fed. 76,141, 1991 U.S. App. LEXIS 16693, 1991 WL 138502, Counsel Stack Legal Research, https://law.counselstack.com/opinion/allied-signal-inc-v-the-united-states-cafc-1991.