Roxco, Ltd. v. United States

77 Fed. Cl. 138, 2007 U.S. Claims LEXIS 195, 2007 WL 1805167
CourtUnited States Court of Federal Claims
DecidedJune 20, 2007
DocketNo. 02-176C
StatusPublished
Cited by8 cases

This text of 77 Fed. Cl. 138 (Roxco, Ltd. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Federal Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Roxco, Ltd. v. United States, 77 Fed. Cl. 138, 2007 U.S. Claims LEXIS 195, 2007 WL 1805167 (uscfc 2007).

Opinion

OPINION AND ORDER

SWEENEY, Judge.

Before the court is defendant’s Motion for Partial Dismissal pursuant to Rule 12(b)(1) of the Rules of the United States Court of Federal Claims. Plaintiff contractor filed suit in this court appealing the contracting officer’s rejection of its claim for an equitable adjustment on its construction contract with the United States Department of the Air Force. Plaintiff later amended its Complaint, seeking, inter alia, the contract balance. Defendant seeks dismissal of that [139]*139portion of plaintiffs Amended Complaint1 requesting the outstanding contract balance. For the reasons stated below, defendant’s Motion for Partial Dismissal is denied.

I. BACKGROUND2

The facts pertinent to defendant’s Motion for Partial Dismissal are set forth in an earlier decision, Roxco, 60 Fed.Cl. at 40-42, and for the sake of clarity and context, are repeated here. On March 17, 1995, the United States Department of the Air Force (“Air Force”) awarded Contract No. F16602-95-C-0013 (“Contract”) to Roxco, Ltd. (“Roxco” or “plaintiff’). Roxco, 60 Fed.Cl. at 40. The Contract, as amended, provided for the construction of 172 new housing units at Barks-dale Air Force Base in Shreveport, Louisiana, for a contract price of approximately $18.9 million. Id. Roxco was expected to complete construction by August 5,1996. Id.

Disputes arose between Roxco and the Air Force over allegations of differing site conditions, constructive changes, government-caused delays, and breaches of contract. Id. From April 1995 to August 1998, Roxco’s Vice President corresponded with Ms. Kathleen Lee, the contracting officer (“CO”), about these disputes. Id. at 40-41. The letters from Roxco reflect that Roxco sought additional payments and extensions of time while reserving its right to an equitable adjustment under the Contract. Id. at 41. The record before this court reflects that the CO did not respond to most of Roxco’s concerns. Id. The completion date passed without Roxco having completed the project. Id. On February 14, 1998, the Air Force unilaterally modified the Contract and set February 18, 1998, as the new date for completion on the project. This date also passed without the Contract being completed. Id.

By letter dated October 16, 1998,3 Roxco advised the Air Force that:

[Roxco] is financially unable to perform or complete the performance of the work or comply with its contractual obligations on the above project, and accordingly, is in default under the above [C]ontract for the project. Roxco, Ltd. hereby irrevocably and voluntarily abandons and terminates the above construction Contract effective immediately.

Def.’s App. 1; see also Tr. 7 (noting that Roxco “performed this work from the time the [C]ontract was entered into in 1995 until it basically ran out of funds”).

In a November 4, 1998 letter, the surety informed the Air Force that it would be taking over the Contract. Def.’s App. 2-3. The CO sent Roxco a show cause letter on November 23, 1998, stating that the Air Force was considering terminating the Contract for default and offered Roxco forty-eight hours to explain its failure to perform. Roxco, 60 Fed.Cl. at 41. Roxco did not respond. Id. Thus, the CO issued a Notice of Default Termination (“Notice”) on December 21, 1998, but no specific sum was assessed against Roxco. Id. In the Notice, the CO stated that the government “terminates the subject contract” and “Construction of the Wherry Housing may be purchased against your account, and you will be held liable for any excess costs.” Id.; Def.’s App. 4-5. The Notice provided that it was the final decision of the CO, and Roxco could appeal to the agency board of contract appeals within ninety days from the date it received the decision or to the United States Court of Federal Claims (“Court of Federal Claims”) within twelve months of the date it received the decision. Roxco, 60 Fed.Cl. at 41. In the months that followed, Roxco’s surety and the Air Force attempted to negotiate a takeover agreement, but these negotiations broke down, in part, due to the surety’s insistence that the agreement explicitly [140]*140reserve Roxco’s claims. Id. The Air Force rejected all attempts by the surety to preserve any claims Roxco might have had against the government. Id. Although a takeover agreement was never executed due to the Air Force’s and Roxco’s surety’s inability to agree to language regarding the preservation of Roxco’s claim against the Air Force, on August 20, 1999, the surety completed the project. Id. at 4H2. The surety utilized Roxco’s resources to complete the work. Tr. 7.

On March 30, 2001, Roxco submitted its request for equitable adjustment (“REA”) to the CO pursuant to the Contract Disputes Act of 1978 (“CDA”), Pub.L. No. 95-563, 92 Stat. 2383 (codified as amended at 41 U.S.C. §§ 601-613 (2000)), in the amount of $7,840,497.40, for breach of contract. Roxco, 60 Fed.Cl. at 42; see also Am. Compl. U17. The REA requested that the Contract be modified to take into account such alleged government actions as defective documents, differing site conditions, abusive government conduct, and active interference by the government. Roxco, 60 Fed.Cl. at 42. On November 9, 2001, the CO notified Roxco that she had received the REA. The CO noted that Roxco had failed to respond to the show cause letter issued on November 23,1998; as a result, the notice of default termination was issued on December 21, 1998. Id. Thus, the CO concluded, the Air Force was returning Roxco’s REA without action because Roxco failed to appeal the default termination within the time provided by the CDA. Id.

Plaintiff appealed the CO’s decision by filing its Complaint in the Court of Federal Claims on March 7, 2002. The Complaint sought: (1) equitable adjustment in the amount of $7,840,497.40; (2) breach of contract in the amount of $7,840,497.40; and (3) interest and litigation costs.

On” June 10, 2002, defendant filed its Answer and Counterclaim, seeking liquidated damages in the amount of $909,791.00. On August 27, 2002, defendant filed a Motion to Dismiss the counterclaim without prejudice pursuant to Rule 41(a)(2) of the Rules of the United States Court of Federal Claims (“RCFC”) because defendant wanted a final decision from the CO on the liquidated damages issue before proceeding in the Court of Federal Claims. On May 5, 2003, the court granted defendant’s Motion to Dismiss the counterclaim without prejudice.

On May 15, 2003, the CO issued a final decision (“Final Decision”) assessing liquidated damages against Roxco in the amount of $909,791.00. Id. The Final Decision notified Roxco that it could either appeal the decision to the agency board of contract appeals or to the Court of Federal Claims. Def.’s App. 8-9. Copies of the decision were sent to Roxco’s attorney Mr. E. Stephen Williams (“Mr.Williams”), Roxco’s surety, and Southeast Bonding & Insurance, Inc. Id. Also on May 15, 2003, the CO sent a demand letter (“Demand Letter”) to Roxco seeking payment of the liquidated damages. Id. at 19-20.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Bruhn Newtech, Inc. v. United States
129 Fed. Cl. 656 (Federal Claims, 2016)
Hanover Insurance Company (The) v. United States
116 Fed. Cl. 303 (Federal Claims, 2014)
K-Con Building Systems, Inc. v. United States
115 Fed. Cl. 558 (Federal Claims, 2014)
Sikorsky Aircraft Corp. v. United States
102 Fed. Cl. 38 (Federal Claims, 2011)
Northrop Grumman Computing Systems, Inc. v. United States
101 Fed. Cl. 362 (Federal Claims, 2011)
M. Maropakis Carpentry, Inc. v. United States
84 Fed. Cl. 182 (Federal Claims, 2008)
Ramah Navajo School Board, Inc. v. United States
83 Fed. Cl. 786 (Federal Claims, 2008)

Cite This Page — Counsel Stack

Bluebook (online)
77 Fed. Cl. 138, 2007 U.S. Claims LEXIS 195, 2007 WL 1805167, Counsel Stack Legal Research, https://law.counselstack.com/opinion/roxco-ltd-v-united-states-uscfc-2007.