Hanover Insurance Company (The) v. United States

116 Fed. Cl. 303, 2014 U.S. Claims LEXIS 430
CourtUnited States Court of Federal Claims
DecidedMay 27, 2014
Docket1:13-cv-00500
StatusPublished
Cited by3 cases

This text of 116 Fed. Cl. 303 (Hanover Insurance Company (The) v. United States) is published on Counsel Stack Legal Research, covering United States Court of Federal Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Hanover Insurance Company (The) v. United States, 116 Fed. Cl. 303, 2014 U.S. Claims LEXIS 430 (uscfc 2014).

Opinion

OPINION AND ORDER

SWEENEY, Judge

These three consolidated cases concern a construction contract between the United States Army Corps of Engineers (“Corps”) and Lodge Construction, Inc. (“Lodge”). In the complaint filed in the lead ease, Lodge’s surety, The Hanover Insurance Company (“Hanover”), contends that the Corps improperly terminated its contract with Lodge for default. Lodge makes this same contention in its first complaint (“Lodge I”), and then contends in its second complaint (“Lodge II”) that the Corps should not have denied three of its requests for contract adjustments. Defendant moves to dismiss, for lack of jurisdiction, the claims for monetary damages asserted by Hanover and Lodge in their complaints challenging the default termination. According to defendant, plaintiffs failed to submit a valid claim for money damages to the contracting officer prior to filing suit in this court. For the reasons set forth below, the court grants defendant’s motion.

I. BACKGROUND

A. Factual History

On August 24, 2010, Lodge entered into a contract with the Corps to perform certain work as part of the Everglades upgrade project. Lodge’s obligations under the contract were backed by payment and performance bonds issued by Hanover. Lodge and Hanover had previously executed an Indemnity Agreement in which Lodge assigned to Hanover the right to take possession of any contract work it had been performing, and agreed to indemnify Hanover for any expenditures incurred by Hanover under the bonds.

The work that Lodge was to perform under its contract with the Corps included the design and implementation of a plan to dewater a construction area. Under the dewatering plan it developed, Lodge would relocate surface water from the construction area to onsite retention areas, where it would dissipate through percolation or evaporation. In addition, Lodge’s plan called for the construction of a temporary cofferdam wall using metal sheet piling. In developing its dewatering plan, Lodge relied on geotechnical information included in the solicitation. Lodge submitted its dewatering plan to the Corps on November 29, 2010, and the Corps subsequently approved it. Several months later, Lodge provided the Corps with its design for the sheet pile wall, which the Corps ultimately approved on July 1, 2011.

Lodge began implementing its dewatering plan in July 2011. It soon became evident that the water was not dissipating from the retention areas at a rate sufficient to allow Lodge’s work to be completed within the contractually mandated 720 days. Accordingly, on June 26, 2012, Lodge submitted a certified claim to the contracting officer seeking a $3,282,123.02 price increase for the additional effort required for dewatering and an additional ninety-one days for contract performance.

In the meantime, during construction of the sheet pile wall, breaches occurred in two small areas. Two weeks later, on March 29, 2012, the Corps retroactively disapproved Lodge’s design for the sheet pile wall. The *305 Corps then issued a cure notice on June 11, 2012. Ten days later, Lodge responded to the cure notice and submitted another certified claim. In this claim, Lodge sought an additional $679,279.58 and sixty-three days related to the Corps’ retroactive disapproval of its design for the sheet pile wall.

The Corps then issued a show cause notice to Lodge on June 29, 2012. On July 6, 2012, three days before it responded to that notice, Lodge submitted a third certified claim, seeking $1,805,760.33 and an indeterminate number of days for being required to remove and reinstall the sheet pile wall in the area of the breaches.

The Corps did not find Lodge’s response to its show cause notice to be satisfactory. Consequently, on July 23, 2012, it terminated its contract with Lodge for default, asserting that Lodge did not diligently pursue the work to ensure its completion within the contractually mandated 720-day time frame, and that Lodge did not submit an acceptable design for the sheet pile wall. That same day, the Corps made a demand on Hanover under the performance bond to either complete the work itself or tender a new contractor to complete the work. While negotiating the completion of the work with Hanover, the contracting officer denied Lodge’s wall breach claim on October 15, 2012, denied Lodge’s design claim on October 29, 2012, and denied Lodge’s dewatering claim on December 28, 2012.

Hanover eventually tendered a new contractor, and on December 31, 2012, Hanover and the Corps executed a Tender and Release Agreement. The agreement obligated Hanover to pay the Corps $23,995,183.86, an amount that represented the difference between the sum to be paid to the new contractor to complete the work ($47,778,910.00) and the unpaid balance of the Corps’ contract with Lodge ($23,783,726.14). In return, the Corps agreed to release Hanover from claims under the performance bond. In other provisions of the agreement, the parties stipulated that Hanover retained all of its rights under the bonds and the Indemnity Agreement, that Hanover did not waive Lodge’s right to challenge the default termination or pursue any other claims, and that Hanover reserved the right to pursue as its own any of Lodge’s claims against the Corps. The contracting officer executed the agreement on the Corps’ behalf.

B. Procedural History

Lodge and Hanover each filed a complaint in this court on July 22, 2013. Lodge sets forth two counts in its complaint. In its first count, Lodge alleges that the Corps wrongfully terminated its contract for default, arguing that it was entitled to substantial time extensions, as described in its three certified claims. In its second count, Lodge avers that it is entitled to reimbursement for the funds that it is required to pay Hanover under their Indemnity Agreement. This amount includes the $23,995,183.86 that Hanover paid the Corps pursuant to the Tender and Release Agreement and other bond-related costs incurred by Hanover. Lodge concludes its complaint with the following prayer for relief:

[Lodge] requests that the Court find that the Corps’ termination of the contract for default was wrongful, that the Court order the termination for default be converted to a termination for the convenience of the government that will effectively result in the reimbursement to Lodge of all of the costs it incurred in the performance of the project, including, but not limited to, all sums owed to Hanover on account of Hanover having issued the Bonds and having entered into the Tender and Release Agreement with the Corps, all of which have been demanded by Hanover, overhead and profit, and further requests that the Court enter judgment against the Corps awarding Lodge damages, interest, costs, and attorneys’ fees allowed by law, and such other relief as the Court deems appropriate.

Lodge I Compl. 10.

In its complaint, Hanover sets forth three counts. In its first count, Hanover avers that the Corps’ termination of its contract with Lodge for default was wrongful, seeks the conversion of the default termination into a termination for the government’s convenience, and estimates Lodge’s damages as $23,995,183.86. In its second count, Hanover asserts an equitable subrogation claim, and

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
116 Fed. Cl. 303, 2014 U.S. Claims LEXIS 430, Counsel Stack Legal Research, https://law.counselstack.com/opinion/hanover-insurance-company-the-v-united-states-uscfc-2014.