City of Gettysburg v. United States

64 Fed. Cl. 429, 2005 U.S. Claims LEXIS 68, 2005 WL 627792
CourtUnited States Court of Federal Claims
DecidedMarch 16, 2005
DocketNo. 00-773 L
StatusPublished
Cited by9 cases

This text of 64 Fed. Cl. 429 (City of Gettysburg v. United States) is published on Counsel Stack Legal Research, covering United States Court of Federal Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
City of Gettysburg v. United States, 64 Fed. Cl. 429, 2005 U.S. Claims LEXIS 68, 2005 WL 627792 (uscfc 2005).

Opinion

OPINION

BUSH, Judge.

This takings ease is currently before the court on defendant’s Motion To Dismiss Complaint For Failure To State A Claim Or In The Alternative For Summary Judgment And Memorandum In Support Thereof. For the reasons set forth herein, defendant’s Motion For Summary Judgment is hereby granted.

BACKGROUND

I. Factual Background

Plaintiff, the City of Gettysburg, South Dakota, is an incorporated municipality located in Potter County (City). The City is approximately sixteen miles east of the Oahe Reservoir located on the Missouri River (Reservoir). In the 1960’s, the City obtained its water from two wells located within the City. However, in the mid-1960’s, the City began to look for alternative water sources because of the poor quality of the wells and the high costs of maintaining them. Consequently, in the early 1970’s, the City explored the possibility of constructing a system to transport water from the Reservoir to the City. The Reservoir was formed by the creation of the Oahe Dam, as authorized by the Flood Control Act of 1944, Pub.L. No. 534, 58 Stat. 887 (1944) (codified as amended in scattered sections of 33 U.S.C. §§ 701-1, et seq.), to serve the purpose of flood control and [433]*433navigation.1 According to plaintiff, the United States Army Corps of Engineers (Corps) owns or controls the Reservoir up to the Corps’ property line located at an elevation of approximately 1680 feet up the Reservoir slope.

Thus, in October 1972, an engineering firm recommended that the City construct a water transmission system from the Reservoir to the City and that the City begin with the project as soon as possible because of problems being experienced with the existing water system. The proposed project included an intake structure exiting the Reservoir to a pumphouse on the east bank of the Reservoir, an underground transmission pipeline running east approximately two miles from the pumphouse to a water treatment facility, and an underground transmission pipeline running approximately fourteen miles from the treatment facility to the City. The intake structure, the pumphouse, and the first portion of the underground pipeline were to be located on property owned or under the control of the Corps.

In December 1972, the City wrote to the Corps to apply for an easement which would give the City a right-of-way from the government to build and maintain the water transport system. The easement was necessary because the water transport system would be located, in part, on land owned or under the control of the Corps. The Corps responded by detailing the information it needed in order to consider an application for an easement, and the City complied by furnishing the data requested.

In an internal memorandum dated May 11, 1973, the Corps recommended that the City be granted the requested right-of-entry on the designated Corps property, pending final consideration of the City’s request for an easement. Subsequently, on July 25, 1973, the Corps forwarded to the City proposed easement No. DACW45-2-74-6007 granting the City, for a fifty-year term, a right-of-access across the Corps’ land for the withdrawal of water from the Reservoir.

The Corps also provided the City with a list of requirements for obtaining a permit under Section 10 of the Rivers and Harbors Appropriation Act of 1899, 33 U.S.C. § 403. As of August 28, 1973, the City had requested a Section 10 permit, which it received on November 12, 1973 (Permit). The Permit was officially signed by the Corps on November 12, 1973 and by Mayor Klein, on behalf of the City, on November 14, 1973. Distinct from the requested easement, the Permit allowed the City to maintain the water intake structure, lay an intake line, and construct a pumphouse in the Reservoir. The Permit specifically did “not convey any property rights either in real estate or material” and [434]*434contained a release from liability clause stating that “the United States shall in no way be liable for any damage to any structure or work authorized herein which may be caused by or result from future operations undertaken by the Government in the public interest.” Def.’s Ex. 10. at 35-36.

Accordingly, in 1973, the City proceeded with construction of the water transmission system. The water supply system was constructed in or around 1973 through 1974 and completed in mid-1975. The water supply system included a water intake structure located on the floor of the Reservoir which carried water to the pumphouse on the east bank of the Reservoir in an inlet called Whit-lock’s Bay. An underground transmission line then ran from the pumphouse 2.5 miles east to a water treatment plant. Following that, an underground transmission pumpline ran 13.5 miles from the water treatment plant to the City. According to the complaint, the water supply system was the City’s sole source of water. As stated previously, the intake structure, the pumphouse, and the first portion of the underground pipeline were located on property owned or controlled by the Corps. The total cost for the project was $864,000.

On September 25, 1975, after construction of the project had been completed, the City advised the Corps that the easement requested in 1972 had not yet been issued. On that date, the City wrote to the Corps requesting that a permanent easement be issued. On November 18, 1975, the Corps responded with a statement that the City’s request for a permanent easement was still being processed and had not yet been approved. A year and a half later, on June 2, 1977, the Corps sent the City another proposed easement with purportedly different terms than the previous one. On October 18, 1977, the Corps sent the City yet another proposed easement to replace the one sent in June of that year.

A fourth proposed easement was then sent to the City on January 24, 1978. Finally, on March 7, 1978, the Corps formally issued Easement No. DACW45-2-78-6002 (Easement) granting the City a right-of-way to construct, operate and maintain the pipeline and pumping station. Defendant acknowledges that the drafting of the easement was in progress for several years. Defendant states that it does not know why the Easement was not finalized until 1978.

Paragraph 7 of the Easement contains the following clause:

The United States shall not be responsible for damages to property or injuries to persons which may arise from or be incident to the use and occupation of the said premises, nor for damages to the property of the grantee, nor for damages to the property or injuries to the person of the grantee’s officers, agents, servants, or employees, or others who may be on said premises at their invitation or the invitation of any one of them, arising from or incident to government activities, and the grantee shall hold the United States harmless from any and all such claims.

Def.’s Ex. 26 at 64.

On March 7, 1978 the Corps also issued License No. DACW45-3-78-6001 (License), which gave the City right-of-use of a nearby strip of land for a period of two years as a temporary work site to construct the water intake structure and pumping station. The License was scheduled to expire on March 6, 1980. The granting of the License was the natural corollary to the Easement and the Permit.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Urban v. United States
Federal Claims, 2025
United States v. Bolton
District of Columbia, 2020
Baha v. United States
Federal Claims, 2019
Abou-El-Seoud v. United States
Federal Claims, 2018
North v. United States
123 Fed. Cl. 457 (Federal Claims, 2015)
Santiago v. United States
107 Fed. Cl. 154 (Federal Claims, 2012)
Sikorsky Aircraft Corp. v. United States
102 Fed. Cl. 38 (Federal Claims, 2011)
Nwogu v. United States
94 Fed. Cl. 637 (Federal Claims, 2010)
Colon v. United States
71 Fed. Cl. 473 (Federal Claims, 2006)

Cite This Page — Counsel Stack

Bluebook (online)
64 Fed. Cl. 429, 2005 U.S. Claims LEXIS 68, 2005 WL 627792, Counsel Stack Legal Research, https://law.counselstack.com/opinion/city-of-gettysburg-v-united-states-uscfc-2005.