ETSI Pipeline Project v. Missouri

484 U.S. 495, 108 S. Ct. 805, 98 L. Ed. 2d 898, 1988 U.S. LEXIS 938
CourtSupreme Court of the United States
DecidedFebruary 23, 1988
Docket86-939
StatusPublished
Cited by70 cases

This text of 484 U.S. 495 (ETSI Pipeline Project v. Missouri) is published on Counsel Stack Legal Research, covering Supreme Court of the United States primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
ETSI Pipeline Project v. Missouri, 484 U.S. 495, 108 S. Ct. 805, 98 L. Ed. 2d 898, 1988 U.S. LEXIS 938 (1988).

Opinion

Justice White

delivered the opinion of the Court.

We must decide whether in the circumstances of this case the Secretary of the Interior has exceeded the authority Congress delegated to him by the Flood Control Act of 1944.

I

The dispute centers on Lake Oahe, an enormous reservoir located on the Missouri River in South Dakota, with a capacity of more than 23 million acre-feet of water. In 1982, ETSI *498 Pipeline Project entered into a contract with the Secretary of the Interior to withdraw up to 20,000 acre-feet of water from Lake Oahe per year for 40 years. 1 South Dakota already had granted ETSI a state permit to use this water in a coal slurry pipeline that would transport coal from Wyoming to the southeastern United States. Soon after the contract was signed, the States of Missouri, Iowa, and Nebraska brought suit in District Court to enjoin performance of the contract, alleging that the manner in which the contract was approved violated several federal statutes. In particular, the plaintiffs contended that the Interior Secretary lacks statutory authority under the Flood Control Act of 1944 (Act), 58 Stat. 887, to execute a contract to provide water from Lake Oahe for industrial uses without obtaining the approval of the Secretary of the Army. 2

The District Court ruled for the plaintiffs. Missouri v. Andrews, 586 F. Supp. 1268 (Neb. 1984). It concluded that the Oahe Dam was not a reclamation or power development that was undertaken by the Interior Secretary, pursuant to clear statutory authority. Instead, the dam was built by the Corps of Engineers, now part of the Department of the Army (formerly the Department of War, but renamed by Act of July 26,1947, 61 Stat. 495), which has always maintained and operated the reservoir. No block of water in Lake Oahe has been specifically set aside for use by the Interior Department, and the Interior Secretary has not constructed any works at Lake Oahe. On these facts, the District Court held *499 that the Act does not empower the Interior Secretary to furnish water from Lake Oahe for industrial use.

The Court of Appeals affirmed, with one judge dissenting. Missouri v. Andrews, 787 F. 2d 270 (CA8 1986). It upheld the District Court’s conclusion that Lake Oahe is not a reclamation development undertaken by the Interior Secretary, primarily because the Army built the reservoir and controls its operation. Accordingly, the Interior Secretary cannot contract on his own to withdraw water from the reservoir for industrial use. Neither the language nor the legislative history of the Act was thought to support the claim that the Interior Secretary was ceded broad authority over water in this reservoir, even water that it claims has been designated as available for future irrigation purposes. Indeed, the language of the Act and its legislative history were found to be convincing enough on this point that the Court of Appeals refused to defer to the Interior Secretary’s contrary interpretation.

The Court of Appeals denied a petition for rehearing en banc by an equally divided vote of the judges. We granted certiorari, 480 U. S. 905 (1987), and we now affirm.

II

A

The Missouri River Basin is a watershed that covers a vast area in the midwestern United States. The topography of this area, however, reveals two distinct regions that experience very different water problems. The upper part of the Basin, which includes large sections of Montana, Wyoming, North Dakota, and South Dakota, is mostly arid or semiarid; there, the Missouri River and its tributaries are important because they represent a major resource for developing the agricultural and industrial potential of the area. The lower part of the Basin, which includes territory in Nebraska, Kansas, Iowa, and Missouri, is more humid, and there the rivers are used chiefly for navigation, though the critical problem in *500 this region is to control flooding. See generally M. Ridge-way, The Missouri Basin’s Pick-Sloan Plan 47-55 (1955). In the early 1940’s, Congress focused its attention on the water problems of the Missouri River Basin, prompted especially by severe floods that had devastated the lower Basin in 1943 and 1944.

At the behest of Congress, the Army Corps of Engineers prepared a report that described a comprehensive plan to develop the entire Basin, known as the Pick Plan for its author, a colonel in the Corps. The Pick Plan proposed the construction of 12 multiple-purpose reservoirs and related works, including 5 reservoirs on the main stem of the Missouri River, at an approximate initial cost of $480 million, though it was estimated that to carry out the entire proposal might cost close to $1 billion. The Pick Plan stressed flood control as its primary objective, but noted that its comprehensive list of projects “would also provide for the most efficient utilization of the waters of the Missouri River Basin for all purposes, including irrigation, navigation, power, domestic and sanitary purposes, wildlife, and recreation,” as well as other intangible benefits. H. R. Doc. No. 475, 78th Cong., 2d Sess., 29 (1944) (H. R. Doc.). The report estimated the gross storage capacity of the Oahe Reservoir at about 6 million acre-feet of water.

At almost the same time, the Interior Department’s Bureau of Reclamation independently completed its own plan to develop the Basin, which it had begun earlier, known as the Sloan Plan after the Montana engineer who prepared much of its analysis. The Sloan Plan proposed a total of 90 reservoirs, many of them on the smaller tributary streams, and included 3 reservoirs on the main stem of the Missouri River, at a projected cost of $1.2 billion, with much of that figure to be repayable. The Sloan Plan was also a comprehensive proposal, though it emphasized use of the water for irrigating land, especially in the upper part of the Basin. It estimated that the Oahe Reservoir would hold 19,600,000 acre-feet of *501 water. The Sloan Plan also contained a section comparing its provisions to those in the Pick Plan and suggesting modifications to the Pick Plan “which appear necessary to satisfy water-use requirements throughout the Missouri River Basin.” S. Doc. No. 191, 78th Cong., 2d Sess., 120 (1944) (S. Doc.). This section concluded that though “the capacity of individual reservoirs, as well as aggregate capacities, remain to be determined in greater detail,” the “Army and Reclamation plans on storage needs for all purposes can be composed.” Id., at 122-123.

The Pick and Sloan Plans differed with one another not only in their primary objectives, but also in several other important respects, such as the amount of expenditures and the number of projects. The engineering features of the two plans also were dissimilar. On the main stem of the Missouri River, the two plans called for different numbers of reservoirs of divergent sizes, and thus for inconsistent amounts of total water storage.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Bohlman v. United States
W.D. Virginia, 2024
EEE Minerals, LLC v. State of North Dakota
81 F.4th 809 (Eighth Circuit, 2023)
Ideker Farms, Inc. v. United States
71 F.4th 964 (Federal Circuit, 2023)
NRDC v. Michael Regan
67 F.4th 397 (D.C. Circuit, 2023)
Arreaga-Velasquez v. Cissna
D. South Carolina, 2020
Goncalves Pontes v. Barr
938 F.3d 1 (First Circuit, 2019)
Sierra Club v. Pruitt
293 F. Supp. 3d 1050 (N.D. California, 2018)
New Mexico v. Department of the Interior
854 F.3d 1207 (Tenth Circuit, 2017)
Virgin Islands Taxi Ass'n v. West Indian Co.
66 V.I. 473 (Supreme Court of The Virgin Islands, 2017)
Wyoming v. United States Department of the Interior
136 F. Supp. 3d 1317 (D. Wyoming, 2015)
Texas v. United States
95 F. Supp. 3d 965 (N.D. Texas, 2015)
E.P.A. v. EME Homer City Generation, L.P.
134 S. Ct. 1584 (Supreme Court, 2014)
Lozano v. State
2013 OK CR 17 (Court of Criminal Appeals of Oklahoma, 2013)
Comite De Apoyo A Los Trabajadores Agricolas v. Solis
933 F. Supp. 2d 700 (E.D. Pennsylvania, 2013)

Cite This Page — Counsel Stack

Bluebook (online)
484 U.S. 495, 108 S. Ct. 805, 98 L. Ed. 2d 898, 1988 U.S. LEXIS 938, Counsel Stack Legal Research, https://law.counselstack.com/opinion/etsi-pipeline-project-v-missouri-scotus-1988.