Meltech Corporation, Inc.

CourtArmed Services Board of Contract Appeals
DecidedJanuary 6, 2026
Docket61765
StatusPublished

This text of Meltech Corporation, Inc. (Meltech Corporation, Inc.) is published on Counsel Stack Legal Research, covering Armed Services Board of Contract Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Meltech Corporation, Inc., (asbca 2026).

Opinion

ARMED SERVICES BOARD OF CONTRACT APPEALS Appeal of - ) ) Meltech Corporation, Inc. ) ASBCA No. 61765 ) Under Contract No. W912DR-14-D-0021 )

APPEARANCES FOR THE APPELLANT: Leonard A. Sacks, Esq. Leonard A. Sacks & Associates, P.C. Rockville, MD Fred A. Mendicino, Esq. Faughnan Mendicino PLLC Dulles, VA APPEARANCES FOR THE GOVERNMENT: Michael P. Goodman, Esq. Engineer Chief Trial Attorney Adam J. Kwiatkowski, Esq. Engineer Trial Attorneys U.S. Army Engineer District, Baltimore

OPINION BY ADMINISTRATIVE JUDGE CATES-HARMAN

This appeal arises from a contract between Meltech Corporation, Inc. (“Meltech” or “appellant”), and the U.S. Army Corps of Engineers (“USACE” or “government”) for a Multiple Award Task Order contract that included both Design-Build and Design-Bid-Build construction projects within the Baltimore District Area of Responsibility, and the September 30, 2014 award by USACE of a Firm- Fixed-Price Task Order No. 0002 to Meltech for all costs in connection with the renovation, design and construction of Building 8609, located at Ft. Meade, MD. This appeal is related to fifteen (15) other appeals that were consolidated and heard by the Board. ∗

In this appeal, Meltech claims that the government interfered with its work by changing its base access policy, making it much harder and causing delay to get access to the base for Meltech’s workers and drivers. On November 1, 2017, Meltech filed its request for equitable adjustment seeking, in part, 87 days of delay caused by unforeseen/changed conditions associated with badging and base access during the time

∗ ASBCA Nos. 61694, 61762, 61763, 61764, 61765, 61766, 61767, 61869, 61870, 61871, 61872, 62091, 62987. The lead appeal is ASBCA No. 61694. A decision on summary judgment was issued on ASBCA Nos. 61706 and 61768 on December 17, 2021. A decision on the merits was issued on July 16, 2025, in ASBCA Nos. 61766, 61767, 61872. Familiarity with those decisions is presumed. period of December 2016 to April 2017. Specifically, Meltech claims that after the change in the security policy, it was required to provide sponsorship, escort duties, and delivery impacts for getting workers base access and clearance. On April 30, 2018, Meltech converted its request for equitable adjustment to a claim. The contracting officer did not issue a final decision. Meltech timely appealed to the Board on a deemed denial basis on August 23, 2018, and the Board has jurisdiction over these appeals under the Contract Disputes Act of 1978, 41 U.S.C. §§ 7101-7109. A nine-day hearing was held via videoconference for the fifteen (15) Appeals. For the reasons stated below, we deny Appeal No. 61765.

FINDINGS OF FACT

Background

1. On June 10, 2014, USACE issued a Request for Proposals (RFP) for a Multiple Award Task Order Contract (MATOC) that included design-build and design-bid-build construction projects within the Baltimore District [A]rea of Responsibility. This was Phase 1 of a two-phase construction procurement. (Joint Stipulations of Fact (JSOF) ¶ 1; R4, tab 2))

2. The MATOC included renovating several similar dormitory buildings at Fort Meade, including Building 8609 (JSOF ¶ 3).

3. On August 14, 2014, USACE issued Amendment 0003 to RFP W912DR-14-R-0003 for two seed projects under the MATOC to provide Design Criteria for the Design-Build renovation of Building 8609 at Fort Meade and Building 4501 at Aberdeen Proving Ground. Each task order was to be awarded separately (JSOF ¶ 7).

4. On September 15, 2014, Meltech submitted its technical and cost proposals for the Building 8609 renovation. Meltech’s proposal included a preliminary schedule. According to this schedule, the design period would begin on November 18, 2014, and end on June 4, 2015. The construction period would begin on May 29, 2015, and end on April 26, 2016. (JSOF ¶¶ 11-12)

5. On September 29, 2014, USACE awarded Meltech Base Contract No. W912DR-14-D-0021. On September 30, 2014, USACE awarded Task Order Contract No. 0002 to Meltech for the renovation of Building 8609 at Fort Meade. The Task Order Contract provided Meltech with a 540-calendar day performance period beginning from the Notice to Proceed date. The Notice to Proceed was issued on November 17, 2014, and the original completion date was May 10, 2016. (JSOF ¶¶ 13- 16)

2 BASE ACCESS, CONSTRUCTION PHASE DELAYS – ASBCA No. 61765

Fort Meade heightened security

6. When the project began in 2014, Fort Meade was an “open base,” and anyone with valid identification could enter the base (R4, tab 199 at 1-3; tr. 4/30, 212).

7. On March 11, 2016, Fort Meade Director, Directorate, Plans, Training, Mobilization and Security, sent an email addressing “New Installation Access Procedures,” with an effective date of April 4, 2016. The new procedures aligned “with U.S. Army standards across military posts world-wide.” (App. supp. R4, tab 555 at 6-9) These were base- wide security changes initiated by Fort Meade for general security reasons (tr. 4/32-33, 212-13). Once the new base access policies were implemented, visitors were required to get a permit or pass to enter the property (tr. 4/212). The change in policy was made by Fort Meade Security (tr. 4/31).

8. Attached to the March 11, 2016 email was a pamphlet titled “The New Installation Access Procedures,” which explained that “[i]ndividuals without DoD-issued ID cards must obtain a Fort Meade Access pass from the Visitor Control Center . . . [and] [f]requent visitors are encouraged to pre-register for a long-term . . . pass.” The installation access procedures included a telephone number for questions surrounding Fort Meade access. (App. supp. R4, tab 555 at 6-9)

9. Attached to the New Installation Access Procedures pamphlet were common questions and answers, including, “how can I enter Fort Meade if I don’t have a military ID card? . . . A valid reason to visit the installation. . . . A Fort Meade Access pass.” The pamphlet provided two options to obtain a Fort Meade access pass: a one-day pass and multi-day access passes. The one-day pass required an enhanced driver’s license or a U.S. Passport and submission to an NCIC III background check through the Fort Meade Visitor Control Center (FMVCC). The multi-day pass required a completed FGGM 192 form and appropriate identification (three options). Option 1 included the driver’s license, birth certificate, and social security card; option 2, U.S. Passport and social security card; option 3, for visitors who did not have an enhanced driver’s license, the process required a U.S. Passport, social security card, and driver’s license. Submission procedures for new badging required a requestor to provide scanned documents in color (app. supp. R4, tabs 555 at 2, 10-11; 603; R4, tab 199 at 2).

10. In response to Meltech’s questions, USACE Project Engineer Melvin Damoudt, by email dated April 21, 2016, described the application process, which included subcontractors providing their documentation to Meltech, who forwarded it to the USACE sponsor, who would evaluate each application, and if they approved, forward it to the FMVCC for review and background checks. The Project Engineer cautioned Meltech that the background checks alone would likely take around 10 days. (App. supp.

3 R4, tab 555 at 12) FMVCC notified the USACE sponsor of the final disposition of each application through email, and USACE informed Meltech whether the applicant was cleared or rejected and the deadline to pick up the new access badge from FMVCC. The Project Engineer informed Meltech that badges not timely picked up from FMVCC would be destroyed and the applicant would need to resubmit the access application package. (App. supp.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

CONNER BROS. CONST. CO., INC. v. Geren
550 F.3d 1368 (Federal Circuit, 2008)
M.E.S., Inc. v. McHugh
502 F. App'x 934 (Federal Circuit, 2013)
Casitas Municipal Water District v. United States
543 F.3d 1276 (Federal Circuit, 2008)
Garco Construction, Inc. v. Secretary of the Army
856 F.3d 938 (Federal Circuit, 2017)
Delhur Industries, Inc. v. United States
95 Fed. Cl. 446 (Federal Claims, 2010)

Cite This Page — Counsel Stack

Bluebook (online)
Meltech Corporation, Inc., Counsel Stack Legal Research, https://law.counselstack.com/opinion/meltech-corporation-inc-asbca-2026.