Meltech Corporation, Inc.

Armed Services Board of Contract Appeals·Decided January 16, 2026·No. 61762, 61764·Published

Opinion

ARMED SERVICES BOARD OF CONTRACT APPEALS Appeals of - ) ) Meltech Corporation, Inc. ) ASBCA Nos. 61762, 61764 ) Under Contract No. W912DR-14-D-0021 )

APPEARANCES FOR THE APPELLANT: Leonard A. Sacks, Esq. Leonard A. Sacks & Associates, P.C. Rockville, MD Fred A. Mendicino, Esq. Faughnan Mendicino PLLC Dulles, VA APPEARANCES FOR THE GOVERNMENT: Michael P. Goodman, Esq. Engineer Chief Trial Attorney Adam J. Kwiatkowski, Esq. Engineer Trial Attorney U.S. Army Engineer District, Baltimore

OPINION BY ADMINISTRATIVE JUDGE CATES-HARMAN

This appeal arises from a contract between Meltech Corporation, Inc. (“Meltech” or “appellant”), and the U.S. Army Corps of Engineers (“USACE” or “government”) for a Multiple Award Task Order contract that included both Design-Build and Design-Bid-Build construction projects within the Baltimore District Area of Responsibility, and the September 30, 2014, award by USACE of a Firm- Fixed-Price Task Order No. 0002 to Meltech for all costs in connection with the renovation, design, and construction of Building 8609, located at Ft. Meade, MD. The appeals captioned above are related to thirteen (13) other appeals that were consolidated and heard by the Board. 1 These appeals involve claims related to the hammerhead roof.

1 ASBCA Nos. 61694, 61762, 61763, 61764, 61765, 61766, 61767, 61869, 61870, 61871, 61872, 62091, 62987. The lead appeal is ASBCA No. 61694. On December 17, 2021, a decision on summary judgment was issued in ASBCA Nos. 61706 and 61768. On July 16, 2025, a decision was issued in ASBCA Nos. 61766, 61767 and 61872. On January 6, 2026, a decision was issued in ASBCA No. 61765. Familiarity with those decisions is presumed.

1 The Board has jurisdiction over these appeals under the Contract Disputes Act of 1978, 41 U.S.C. §§ 7101-7109. A nine-day hearing was held via videoconference. For the reasons stated below, we sustain the appeal.

FINDINGS OF FACT

Contract and Task Order

1. On June 10, 2014, USACE issued a Request for Proposals (RFP) for a Multiple Award Task Order Contract (MATOC) that included design-build and design-bid-build construction projects within the Baltimore District area of Responsibility. This was Phase 1 of a two-phase construction procurement. (Joint Stipulations of Fact, General Background (JSOF GB) ¶ 1; R4, tab 2))

2. The MATOC included renovating several similar dormitory buildings at Fort Meade, including Building 8609 (JSOF GB ¶ 3).

3. On August 14, 2014, USACE issued Amendment 0003 to RFP W912DR- 14-R-0003 for two seed projects under the MATOC to provide Design Criteria for the Design-Build renovation of Building 8609 at Fort Meade and Building 4501 at Aberdeen Proving Ground. Each task order was to be awarded separately. (JSOF GB ¶ 7)

4. On September 15, 2014, Meltech submitted its technical and cost proposals for the Building 8609 renovation. Meltech’s proposal included a preliminary schedule. According to this schedule, the design period would begin on November 18, 2014, and end on June 4, 2015. The construction period would begin on May 29, 2015, and end on April 26, 2016. (JSOF GB ¶¶ 11-12)

5. On September 29, 2014, USACE awarded Meltech Base Contract No. W912DR-14-D-0021. On September 30, 2014, USACE awarded Task Order Contract No. 0002 to Meltech for the renovation of Building 8609 at Fort Meade. The Task Order Contract provided Meltech with a 540-calendar day performance period beginning from the Notice to Proceed date. The Notice to Proceed was issued on November 17, 2014, and the original completion date was May 10, 2016. (JSOF GB ¶¶ 13-16)

The Existing Roof Structure

6. Prior to the renovation, the hammerhead portion of Building 8609, which housed the main entry and administrative community functions of the building, had an EPDM (Ethylene Propylene Diene Monomer) roof (Joint Stipulations of Fact, ASBCA Nos. 61762, 61764, hereinafter (JSOF) ¶ 6); R4, tab 3 at 7). The roof was flat.

2 7. In contrast, a gable roof is a roof consisting of two sections whose upper horizontal edges meet to form its ridge (JSOF ¶ 7).

Black And Veatch Expected The New Roof To Be Installed On The Existing Roof

8. USACE contracted with Black and Veatch (B-V, Designer of Record) to prepare “a partial criteria Design-Build Request for Proposal” package for the renovation of Building 8609, including a “[n]ew, sloped roof” (app. supp. R4, tab 351 at 5). The scope of B-V’s work was to “[d]evelop performance criteria for all design disciplines for the Request for Proposal [] Design-Build Package. Use tables, text, sketches, drawings and others to illustrate the performance criteria” (id. at 6). The architect-engineer services by B-V were to “provide all necessary services required for the preparation of a complete and biddable RFP Design-Build Package” (id. at 7).

9. B-V was provided a copy of a drawing FE 8257 dated April 7, 1995, titled “Roof Details BLDG 8609.” This figure provides details of component layers underneath the roof. (App. supp. R4, tab 606) These layers underneath the roof are discussed in more detail below. B-V did not include details of these hidden, underneath layers of the hammerhead roof within the Design Criteria for prospective bidders (tr. 1/119).

10. USACE’s Project Engineer posted a question to the lead Designer of Record, in the Dr. Checks System on June 26, 2014, if the existing roof will remain in place or whether it needs to be removed to install the new gable roof. The Designer of Record responded on July 22, 2014, that “It was the intent of the RFP to allow the Design Build Contractor to leave the existing roof in place as possible while providing proper connection[] of the new roof framing to the existing building. Wording to that end will be added to the RFP in paragraph 5.3.4 c) ii.” (App. supp. R4, tab 742 at 3; tr. 3/107, 109-10)

11. B-V’s estimate noted that the existing roof was to remain, “current roofing is built-up. New roof will be pitched standing seam metal. We are not intending that existing roof will be removed” (JSOF ¶ 2; app. supp. R4, tab 352 at 15).

Relevant Contract Clauses and Design Criteria Specifications

12. The contract contained the standard clauses for construction contracts, including Federal Acquisition Regulation (FAR) 52.233-1 DISPUTES (JUL 2002), FAR 52.236-2 DIFFERING SITE CONDITIONS (APR 1984), and FAR 52.236-3 SITE INVESTIGATION AND CONDITIONS AFFECTING THE WORK (APR l984) (R4, tab 2 at 41).

3 13. Section 00100 of the Proposal Submission Requirements states that “The Contractor will provide all design, management, supervision, labor, materials, tools, and equipment necessary for the performance of the work. Task orders may be either Design-Build or Design-Bid-Build” (R4, tab 2 at 5).

14. The RFP specified that a new gable roof was to be installed on the existing “hammerhead” roof portion of the building (JSOF ¶ 1; R4, tab 3 at 7).

15. Consistent with B-V’s clarification to USACE on July 22, 2014 (finding 10), the Design Criteria under section 5.3.4(c)(ii), Architecture and Interior Design, Building Exterior, provided that, at the contractor’s option, the existing roof could remain, and the contractor could perform selective demolition where the new truss assembly could attach to the new gable roof (JSOF ¶¶ 4, 20):

Roofing – Gable roof constructed of standing seam metal roof . . . . This gable roof is intended to be constructed so as to create an attic space which must be ventilated. At the contractor’s option the existing roofing may be left in place, with only selective demolition performed to allow for proper connection of the new roof framing to existing structure.

(R4, tab 3 at 41)

16.

Free access — add to your briefcase to read the full text and ask questions with AI

Meltech Corporation, Inc., (asbca 2026).

Meltech Corporation, Inc. (Meltech Corporation, Inc.) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Pacific Alaska Contractors, Inc. v. The United States
436 F.2d 461 (Court of Claims, 1971)
H.B. Mac, Inc. v. United States
153 F.3d 1338 (Federal Circuit, 1998)
Hercules Incorporated v. United States
292 F.3d 1378 (Federal Circuit, 2002)
Comtrol, Inc. v. United States
294 F.3d 1357 (Federal Circuit, 2002)
Bannum, Inc. v. United States
121 Fed. Cl. 543 (Federal Claims, 2015)
Hardwick Bros. v. United States
41 Cont. Cas. Fed. 76,972 (Federal Claims, 1996)
Hunkin Conkey Construction Co. v. United States
461 F.2d 1270 (Court of Claims, 1972)
Nova group/tutor-saliba v. United States
87 F.4th 1375 (Federal Circuit, 2023)