Meltech Corporation, Inc.

CourtArmed Services Board of Contract Appeals
DecidedNovember 25, 2024
Docket63556
StatusPublished

This text of Meltech Corporation, Inc. (Meltech Corporation, Inc.) is published on Counsel Stack Legal Research, covering Armed Services Board of Contract Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Meltech Corporation, Inc., (asbca 2024).

Opinion

ARMED SERVICES BOARD OF CONTRACT APPEALS Appeal of - ) ) Meltech Corporation, Inc. ) ASBCA No. 63556 ) Under Contract No. W912DR-14-D-0021 )

APPEARANCES FOR THE APPELLANT: Leonard A. Sacks, Esq. Leonard A. Sacks & Associates, P.C. Rockville, MD

Fred A. Mendicino, Esq. Brian M. Silver, Esq. Faughnan Mendicino PLLC Dulles, VA

APPEARANCES FOR THE GOVERNMENT: Michael P. Goodman, Esq. Engineer Chief Trial Attorney Adam J. Kwiatkowski, Esq. Engineer Trial Attorney U.S. Army Engineer District, Baltimore

OPINION BY ADMINISTRATIVE JUDGE CATES-HARMAN ON APPELLANT’S MOTION FOR SUMMARY JUDGMENT ON SUPERIOR KNOWLEDGE

This appeal arises from a contract between Meltech Corporation, Inc. (“Meltech” or “appellant”), and the U.S. Army Corps of Engineers (“USACE” or “respondent”) for a Multiple Award Task Order contract (MATOC) that included both Design-Build and Design-Bid-Build construction projects within the Baltimore District Area of Responsibility, and the September 30, 2014 award by USACE of a Firm- Fixed-Price (FFP) Task Order No. 0002 to Meltech for all costs in connection with the renovation, design and construction of Building 8609, located at Ft. Meade, MD. (R4, tabs 28 at 1-2; 29 at 1-2). This appeal is related to fifteen (15) other appeals that were consolidated and heard by the Board. 1

1 ASBCA Nos. 61694, 61762, 61763, 61764, 61765, 61766, 61767, 61869, 61870, 61871, 61872, 62091, 62987. The lead appeal is ASBCA No. 61694. A decision on summary judgment was issued on ASBCA Nos. 61706 and 61768 on December 17, 2021. Before hearing the related appeals, appellant filed a motion for leave to amend the complaint to add three (3) additional counts: differing site condition, superior knowledge, and breach of the duty of good faith and fair dealing. On June 11, 2020, the Board issued an unpublished decision granting appellant’s request to amend the complaint to add differing site condition and denied the counts of superior knowledge and breach of the duty of good faith and fair dealing. The Board held that we lacked jurisdiction to hear the count of superior knowledge or breach of the duty of good faith and fair dealing. Meltech Corp., ASBCA Nos. 61694, 61706, 61762 (Slip Op’n, June 11, 2020). In the interim, on April 9, 2020, Meltech filed a certified claim with the contracting officer relating to its assertions of superior knowledge and a breach of the duty of good faith and fair dealing. The contracting officer denied the claim on July 2, 2020. Meltech did not appeal the COFD to the ASBCA within the 90-day statutory deadline. Instead, on July 1, 2021, one day shy of the one-year statutory deadline, Meltech filed a complaint in the United States Court of Federal Claims. See 41 U.S.C. § 7104(b)(3). On February 13, 2023, the Court of Federal Claims ordered the transfer of Case No. 21-1532C to the ASBCA pursuant to 41 U.S.C. § 7107(d) (Notice of Appeal dtd. March 8, 2023). The transferred case has been assigned ASBCA docket number 63556.

On May 8, 2024, appellant filed a motion seeking summary judgment on its claim based upon superior knowledge. Appellant alleges that “[i]n violation of its contractual and regulatory obligations, USACE knew and failed to disclose material and vital information to Meltech that adversely impacted its costs and time of performance.” Meltech states that the vital information withheld includes: “(1) USACE knew there were no as-built drawings of Building 8609; (2) USACE knew other TBUP Buildings required destructive testing to discover the actual strength of the existing structural concrete; and (3) USACE knew the strength of the concrete in Building 8609 was likely below the 3,000 pounds per square inch (psi) threshold presumed in the design standards incorporated into the Contract.” (App. mot. at 1) Meltech presents facts that it maintains are undisputed and entitle it to summary judgment on its claim of superior knowledge. The government challenges each material fact that appellant maintains entitles it to summary judgment as a matter of fact and law. For the reasons stated below, we find that there are material facts in dispute preventing us from entering summary judgment.

STATEMENT OF FACTS (SOF) FOR PURPOSES OF THE MOTION

1. On June 10, 2014, USACE issued a Request for Proposals (RFP) for a Multiple Award Task Order Contract (MATOC) that included both design-build and design-bid-build construction projects within the Baltimore District Area of

2 Responsibility. This was Phase 1 of a two-phase construction procurement. (Joint Stipulations of Fact (JSOF) 2 ¶ 1; R4, tab 2)

2. USACE selected a pool of eight successful offerors from Phase 1. Only those qualified offerors were permitted to submit proposals in Phase 2. Meltech was one of those offerors. (JSOF (GB) ¶ 2))

3. The MATOC included the renovation of several similar dormitory buildings at Ft. Meade, including Building 8609 (TBUP) (JSOF (GB) ¶ 3)).

4. USACE contracted with Black and Veatch (“B-V”) to prepare the RFP for Building 8609, which was the final building in the Fort Meade TBUP program. (JSOF (GB) ¶ 4)).

5. B-V’s contract provided that the “architectural programming for this building has already been developed during the design of TBUP buildings 8478/8479, 8545, and 8606” (app. supp. R4, tab 351 at 6). B-V’s contract provided that USACE would provide as-built drawings, along with other items from buildings 8606 and 8545, and the previous RFP’s for TBUP buildings 8478/8479, 8545, and 8606. However, B-V could not recall if the as-builts were provided to it by USACE. (App. supp. R4, tabs 351 at 11; 722 at 32-34; tr. 8/32-34, 195-96).

6. A value engineering report for Building 8545 includes the following excerpt:

ORIGINAL DESIGN: No structural drawings are available.

PROPOSED DESIGN: “Perform destructive testing” prior to awarding the structural design contracts.

...

JUSTIFICATION/DISCUSSION: Building[s] 8478 and 8479 both experienced critical construction delays due to a lack of available structural information. Their destructive

2 On September 7, 2022, the parties filed Joint Stipulations of Fact that included general background stipulations and stipulations related to several of the appeals pending before the Board. For purposes of this motion, the “General Background” stipulations, ¶¶ 1-18, will be cited as JSOF (GB), and the appeal- specific stipulations “Structural Concrete – ASBCA Nos. 61694, 62987” ¶¶ 1- 49, will be cited as JSOF (SC). 3 testing revealed the reinforcement conditions only after the contract was well underway. (App. supp. R4, tab 468)

7. In response to whether B-V did any testing of the building concrete to determine its psi, Mr. Randall Gowler, B-V’s design manager for the project, testified that there would be no way “short of cutting out part of the concrete” to determine the psi of the concrete in the building. (Black & Veatch depo transcript, Mr. Randall Gowler; app. supp. R4, tab 722, at 10, 36).

8. On August 14, 2014, USACE issued Amendment 0003 to RFP W912DR- 14-R0003 for two seed projects under the MATOC to provide Design Criteria for the Design-Build renovation of Building 8609 at Fort Meade and Building 4501 at Aberdeen Proving Ground. Each task order was to be awarded separately. (JSOF (GB) ¶ 7)).

9. On September 4, 2014, B-V provided responses to USACE concerning offerors’ questions with respect to Building 8609’s RFP (JSOF (GB) ¶ 9)).

10. Pre-bid question 64 requested “existing as-built drawings for ATFP evaluation.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Adickes v. S. H. Kress & Co.
398 U.S. 144 (Supreme Court, 1970)
Anderson v. Liberty Lobby, Inc.
477 U.S. 242 (Supreme Court, 1986)
Barefoot Architect, Inc. v. Bunge
632 F.3d 822 (Third Circuit, 2011)
H. N. Bailey & Associates v. The United States
449 F.2d 376 (Court of Claims, 1971)
Pure Gold, Inc. v. Syntex (u.s.a.), Inc.
739 F.2d 624 (Federal Circuit, 1984)
Mingus Constructors, Inc. v. The United States
812 F.2d 1387 (Federal Circuit, 1987)
Scott Timber Co. v. United States
692 F.3d 1365 (Federal Circuit, 2012)
Renda Marine, Inc. v. United States
66 Fed. Cl. 639 (Federal Claims, 2005)
Bannum, Inc. v. United States
80 Fed. Cl. 239 (Federal Claims, 2008)
Newsom v. United States
676 F.2d 647 (Court of Claims, 1982)

Cite This Page — Counsel Stack

Bluebook (online)
Meltech Corporation, Inc., Counsel Stack Legal Research, https://law.counselstack.com/opinion/meltech-corporation-inc-asbca-2024.