Meltech Corporation, Inc.

Armed Services Board of Contract Appeals·Decided February 6, 2026·No. 61871·Published

Opinion

ARMED SERVICES BOARD OF CONTRACT APPEALS Appeal of - ) ) Meltech Corporation, Inc. ) ASBCA No. 61871 ) Under Contract No. W912DR-14-D-0021 )

APPEARANCES FOR THE APPELLANT: Leonard A. Sacks, Esq. Leonard A. Sacks & Associates, P.C. Rockville, MD Fred A. Mendicino, Esq. Faughnan Mendicino PLLC Dulles, VA APPEARANCES FOR THE GOVERNMENT: Michael P. Goodman, Esq. Engineer Chief Trial Attorney Adam J. Kwiatkowski, Esq. Engineer Trial Attorney U.S. Army Engineer District, Baltimore

OPINION BY ADMINISTRATIVE JUDGE CATES-HARMAN

This appeal arises from a contract between Meltech Corporation, Inc. (“Meltech” or “appellant”), and the U.S. Army Corps of Engineers (“USACE” or “government”), specifically a Multiple Award Task Order contract that included both Design-Build and Design-Bid-Build construction projects within the Baltimore District Area of Responsibility, and the September 30, 2014, award by USACE of a Firm- Fixed-Price Task Order No. 0002 to Meltech for all costs in connection with the renovation, design, and construction of Building 8609, located at Ft. Meade, MD. This appeal is related to fifteen total appeals that were consolidated. 1 This appeal involves Meltech’s challenge to the government credit taken on the 24-gauge panels for the metal roof.

1 ASBCA Nos. 61694, 61706, 61762, 61763, 61764, 61765, 61766, 61767, 61768, 61869, 61870, 61871, 61872, 62091, 62987. The lead appeal is ASBCA No. 61694. Thirteen appeals were heard by the Board, and two appeals were resolved on summary judgment. On December 17, 2021, a decision on summary judgment was issued in ASBCA Nos. 61706 and 61768. On July 16, 2025, a decision was issued in ASBCA Nos. 61766, 61767 and 61872. On January 6, 2026, a decision was issued in ASBCA No. 61765. On January 16, 2026, a decision was issued in ASBCA Nos. 61762 and 61764. Familiarity with those decisions is presumed. The Board has jurisdiction over these appeals under the Contract Disputes Act of 1978, 41 U.S.C. §§ 7101-7109. A nine-day hearing was held via videoconference. For the reasons stated below, we deny the appeal.

FINDINGS OF FACT

Contract and Task Order

1. On June 10, 2014, USACE issued a Request for Proposals (RFP) for a Multiple Award Task Order Contract (MATOC) that included design-build and design-bid-build construction projects within the Baltimore District area of Responsibility. This was Phase 1 of a two-phase construction procurement. (Joint Stipulations of Fact, General Background (JSOF GB) ¶ 1; R4, tab 2)

2. The MATOC included renovating several similar dormitory buildings at Fort Meade, including Building 8609 (JSOF GB ¶ 3).

3. On August 14, 2014, USACE issued Amendment 0003 to RFP W912DR- 14-R-0003 for two seed projects under the MATOC to provide Design Criteria for the Design-Build renovation of Building 8609 at Fort Meade and Building 4501 at Aberdeen Proving Ground. Each task order was to be awarded separately. (JSOF GB ¶ 7)

4. On September 15, 2014, Meltech submitted its technical and cost proposals for Building 8609’s renovation. Meltech’s proposal included a preliminary schedule. According to this schedule, the design period would begin on November 18, 2014, and end on June 4, 2015. The construction period would begin on May 29, 2015, and end on April 26, 2016. (JSOF GB ¶¶ 11, 12)

5. On September 29, 2014, USACE awarded Meltech Base Contract No. W912DR-14-D-0021. On September 30, 2014, USACE awarded Task Order Contract No. 0002 to Meltech for the renovation of Building 8609 at Fort Meade. The Task Order Contract provided Meltech with a 540-calendar day performance period beginning from the Notice to Proceed date. The Notice to Proceed was issued on November 17, 2014, and the original completion date was May 10, 2016. (JSOF GB ¶¶ 13-16)

Design Criteria

6. The Design Criteria, under Applicable Criteria, Section 4.0, lists nearly 300 “starting criteria for the RFP,” and that “these publications reference other codes, standards or manuals that may be of assistance to the designers and where applicable

2 should be assumed to be all inclusive in the development of the design” (R4, tab 3 at 30). Included in the standards were National Roofing Contractors Association (Roofing and Waterproofing Manual), Installation Design Guides (Fort Meade Installation Design Guide; Army Installation Design Standards), and Minimum Design Loads for Buildings and Other Structures (American Society of Civil Engineers) (R4, tab 3 at 31, 33, 35).

7. The Design Criteria provided that the building’s roof design shall take into consideration live loads and wind loads (Unified Facilities Criteria (UFC), Structural Engineering 3-301-01, Table D-1; Table E-1) (R4, tab 3 at 55, 104). The structural design of the roof stated “[c]alculations, including computer analyses, shall be furnished for all principal roof” and that “[s]ufficient documentation shall be provided to interpret input and output” (R4, tab 3 at 104).

8. The Design Criteria, under General Technical Requirements, Building Exterior, 5.3.4, required roof panels for the new gabled roof but did not specify the gauge (thickness) 2 of the panel (Joint Stipulations of Fact, ASBCA No. 61871, hereinafter (JSOF) ¶ 1; R4, tab 3 at 41).

The Processes for Providing Design Submittals and Deviating from the Accepted Design

9. The Design Criteria required four distinct design submittals: 30% (Concept Submittal), 50% (Preliminary Design Review Submittal), 95% (Final), and 100% (Design Complete) (R4, tab 3 at 99, 109, 110, 116-17). The 100% Design Complete Submittal describes that “[a]fter the Final Design Review, the Contractor shall revise the Contract Documents by incorporating any comments generated during the Final Design Review and shall prepare final hard copy Contract Specifications” (R4, tab 3 at 116-17). The Design Criteria states that USACE’s “review will be for conformance with the contract [Design Criteria]” (R4, tab 3 at 94).

10. The Design Criteria, under Section 01 12 00, Design After Award, subsection 1.3, Deviating from the Accepted Design, states that changes from the approved design will require government concurrence and modification (R4, tab 3 at 92).

2 The “gauge” of steel refers to its thickness, with smaller numbers being thicker and larger numbers being thinner (JSOF ¶ 2). 3 Meltech’s Roof Submittals

11. Meltech’s price estimate for its proposal assumed that the metal panels that would be used to construct the gable roofs would be made of 22-gauge steel (JSOF ¶ 3; R4, tab 287 at 15).

12. Meltech’s Design Complete (100%) Submittal Specifications dated February 24, 2016, under the Description of Metal Roof System, Section 1.2, lists the performance standards which the roof “panels and accessory components must conform to,” including standards for carbon steel sheets and coatings (R4, tab 311 at 947). In addition, the description of the metal roof system included requirements for Hydrostatic Head Resistance (ASTM E2140), Wind Loads (FM 4471), and Wind Uplift Resistance (ASTM E1592 and UL 580) (R4, tab 311 at 947). Section 1.2.1.2 addressed wind uplift resistance and recognizes that “[u]plift force due to wind action governs the design for panels,” and that Meltech will “[s]ubmit wind uplift test report prior to commencing installation” (R4, tab 311 at 947).

13. Section 2.1, Roof Panels, stated that Meltech would install metal roof panels with a thickness of 22-gauge and adhered to certain ASTM standards, including abrasion, flame spread, flexibility, hardness, and impact (JSOF ¶ 4; R4, tabs 21 at 1; 311 at 955-56). Included in the submittal were calculations for roof wind loads and uplift resistance of roof assemblies (R4, tab 311 at 79-89).

14.

Free access — add to your briefcase to read the full text and ask questions with AI

Meltech Corporation, Inc., (asbca 2026).

Meltech Corporation, Inc. (Meltech Corporation, Inc.) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related