Casitas Municipal Water District v. United States

543 F.3d 1276, 38 Envtl. L. Rep. (Envtl. Law Inst.) 20251, 67 ERC (BNA) 1769, 2008 U.S. App. LEXIS 20297, 2008 WL 4349234
CourtCourt of Appeals for the Federal Circuit
DecidedSeptember 25, 2008
Docket2007-5153
StatusPublished
Cited by110 cases

This text of 543 F.3d 1276 (Casitas Municipal Water District v. United States) is published on Counsel Stack Legal Research, covering Court of Appeals for the Federal Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Casitas Municipal Water District v. United States, 543 F.3d 1276, 38 Envtl. L. Rep. (Envtl. Law Inst.) 20251, 67 ERC (BNA) 1769, 2008 U.S. App. LEXIS 20297, 2008 WL 4349234 (Fed. Cir. 2008).

Opinions

MOORE, Circuit Judge.

Casitas Municipal Water District (Casi-tas) appeals the judgment of the United States Court of Federal Claims granting summary judgment in favor of the government holding that there was no governmental breach of contract and no compen-[1280]*1280sable taking under the Fifth Amendment. We affirm-in-part, reverse-in-part, and remand.

BACKGROUND

Congress authorized the construction of the Ventura River Project (Project) on March 1, 1956. Pub.L. No. 423, 70 Stat. 32 (1956). The Project provides the water supply for farmland irrigation and municipal, domestic, and industrial uses in Ventu-ra County, California. The Project comprises, among other things, the Casitas Dam, Casitas Reservoir, Robles Diversion Dam, and the Robles-Casitas Canal. More specifically, the Project combines water of Coyote Creek and Ventura River in its principal feature, the Casitas Reservoir, generally called Lake Casitas. Lake Casitas itself is located on Coyote Creek and is formed by Casitas Dam. Approximately sixty percent of the Project’s water comes from Coyote Creek. The remaining forty percent of the Project’s water comes from the nearby Ventura River. Ventura River water is diverted via the Robles Diversion Dam into a four and a half mile long canal (the Robles-Casitas Canal), which carries the water to Lake Casitas. Water from Lake Casitas is distributed for use via a conveyance system comprising thirty-four miles of pipeline, five pumping stations, and six balancing reservoirs. The project is shown in Figure 1.

Figure 1: Ventura River Project

[1281]*1281[[Image here]]

On March 7,1956, the United States and Casitas entered into a contract providing for the construction of the Project by the United States in exchange for a commitment by Casitas to repay the construction costs over a forty-year period,1 as well as all operation and maintenance costs.2 Ad[1282]*1282ditionally, the contract provided in Article 4 that Casitas “shall have the perpetual right to use all water that becomes available through the construction and operation of the Project.” The contract also required Casitas to apply to the State of California to appropriate the water for the Project. State water permits were issued to Casitas on May 10, 1956, and the Project was completed and transferred to Ca-sitas for operation in 1959.

In August, 1997, almost forty years after the construction of the project, the National Marine Fisheries Service (NMFS) listed the West Coast steelhead trout as an endangered species in the Project watershed. Section 9 of the Endangered Species Act (ESA) makes it illegal to “take” any species listed as endangered under the Act.3 16 U.S.C. § 1538. To avoid ESA section 9 liability, the Bureau of Reclamation (BOR) sought a biological opinion by the NMFS (BiOp) pursuant to section 7 of the ESA. Id. § 1536(a)(2). For the purposes of this appeal, the government concedes that the BOR’s May 2, 2003 directive advising Casi-tas that it was obligated to comply with the requirement of the BiOp compelled Casitas to: (1) construct a fish ladder facility, which is located at the intersection of the Ventura River, Robles Diversion Dam, and the Robles-Casitas Canal; and (2) divert water from the Project to the fish ladder, resulting in a permanent loss to Casitas of a certain amount of water per year.4 Under protest Casitas complied, but on January 26, 2005, Casitas filed suit against the government alleging that these actions constituted a breach of contract and a compensable Fifth Amendment taking of its water.

After filing its answer, the government filed a motion for summary judgment seeking to resolve the breach of contract claim, and a motion for partial summary judgment regarding the takings claim. In this latter motion, the government requested the trial court to determine the appropriate takings standard to be applied to Casitas’ claim that the government’s appropriation of water to operate the fish ladder constituted a compensable taking.

With respect to the breach of contract claim, Casitas contended that the United States breached the 1956 repayment contract by ordering Casitas to pay the costs of installing the fish ladder, which allegedly brought the total reimbursable project construction costs to more than the contract’s $30.9 million limit. Casitas also argued that the BiOp’s provision for changes to the Project’s operating criteria breached Article 4 of the contract.

On October 2, 2006, the trial court granted summary judgment on the con[1283]*1283tract claims in favor of the United States. See Casitas Mun. Water Dist. v. United States, 72 Fed.Cl. 746 (2006) (Casitas I). Relying principally upon the Supreme Court’s decision in Nampa & Meridian Irrigation District v. Bond, 268 U.S. 50, 45 S.Ct. 383, 69 L.Ed. 843 (1925), the trial court ruled that the costs associated with the construction of the fish ladder facility, more than forty years after the Project’s initiation, were in the nature of operation and maintenance costs and, thus, not reimbursable under the repayment contract. Casitas I, 72 Fed.Cl. at 751. The trial court held that even if Article 4 of the contract was breached by the government, the sovereign acts doctrine applied, shielding the government from liability. Id. at 755.

On March 29, 2007, the trial court granted the government’s partial summary judgment motion and held that the regulatory takings standard applied to Casitas’ claim rather than the physical takings standard. Casitas Mun. Water Dist. v. United States, 76 Fed.Cl. 100, 105-06 (2007) (Casitas II). While the court recognized that a prior trial court decision— Tulare Lake Basin Water Storage District v. United States, 49 Fed.Cl. 313 (2001), rendered by Judge Wiese who also presided in this case—held that a deprivation of water amounts to a physical taking under somewhat similar circumstances, the court concluded that the Supreme Court’s intervening decision Tahoe-Sierra Preservation Council, Inc. v. Tahoe Regional Planning Agency, 535 U.S. 302, 122 S.Ct. 1465, 152 L.Ed.2d 517 (2002), clarified takings law so as to require a different result. Casitas II, 76 Fed.Cl. at 106. On August 2, 2007, in response to Casitas’ concession that it could not prevail under the regulatory takings framework laid out in Penn Central Transportation Co. v. New York City, 438 U.S. 104, 98 S.Ct. 2646, 57 L.Ed.2d 631 (1978), the trial court dismissed the complaint and entered final judgment for the United States. Casitas appealed.

DISCUSSION

This court reviews a grant of summary judgment de novo. Anderson v. United States, 344 F.3d 1343, 1349 (Fed. Cir.2003). Summary judgment is only appropriate if the record shows that there is no genuine issue as to any material fact and that the moving party is entitled to a judgment as a matter of law. Ct. Fed. Cl. R. 56(c); see also Fed.R.Civ.P.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
543 F.3d 1276, 38 Envtl. L. Rep. (Envtl. Law Inst.) 20251, 67 ERC (BNA) 1769, 2008 U.S. App. LEXIS 20297, 2008 WL 4349234, Counsel Stack Legal Research, https://law.counselstack.com/opinion/casitas-municipal-water-district-v-united-states-cafc-2008.