HECO Pacific Manufacturing, Inc.

CourtArmed Services Board of Contract Appeals
DecidedSeptember 4, 2025
Docket63217
StatusPublished

This text of HECO Pacific Manufacturing, Inc. (HECO Pacific Manufacturing, Inc.) is published on Counsel Stack Legal Research, covering Armed Services Board of Contract Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
HECO Pacific Manufacturing, Inc., (asbca 2025).

Opinion

ARMED SERVICES BOARD OF CONTRACT APPEALS Appeal of - ) ) HECO Pacific Manufacturing, Inc. ) ASBCA No. 63217 ) Under Contract No. N62470-13-D-4018 )

APPEARANCE FOR THE APPELLANT: Casey J. McKinnon, Esq. Cohen Seglias Pallas Greenhall & Furman PC Washington, DC

APPEARANCES FOR THE GOVERNMENT: Allison M. McDade, Esq. Navy Chief Trial Attorney David M. Ruddy, Esq. Ryan C. Kujawski, Esq. Trial Attorneys

OPINION BY ADMINISTRATIVE JUDGE MELNICK DENYING THE GOVERNMENT’S MOTION FOR SUMMARY JUDGMENT

HECO Pacific Manufacturing, Inc. (HECO) contracted with the government to provide new cranes. It alleges that government delays pushed its performance into the period of the COVID-19 pandemic, subjecting HECO to COVID mitigation requirements that caused it to incur extra costs. The government moves for summary judgment. For the reasons given below we deny the motion.

STATEMENT OF FACTS (SOF) FOR PURPOSES OF THE MOTION

1. In 2016, the government issued a fixed price delivery order under an existing contract to HECO for three new cranes at Naval Base Kitsap, Bangor, Washington (R4, tab 1 at 10, tab 7 at 47, tab 12). On March 21, 2019, about a month prior to the April 19 extended delivery date, the government expressed concerns by letter respecting the painting of the cranes. Work was then suspended. (Gov’t. mot., ex. C at 1-2; government statement of undisputed material facts (gov’t statement) ¶¶ 16, 21; statement of genuine issues (app. statement) ¶ 9) 1 About eight months later, on November 17, 2019, HECO submitted a Request for Equitable Adjustment (REA) seeking $506,997.75 for delays and impacts resulting from the dispute about painting and the government’s prevention of completion. It recited a plan of action for completion once a modification

1 The government concedes HECO’s statement for purposes of the motion (gov’t reply at 2).

1 was issued. (Gov’t mot., ex. D at 1-4) HECO responded to government questions and revised the REA on December 23, 2019 (gov’t mot., ex. E at 1-5).

2. On March 13, 2020, COVID-19 was declared a national emergency (gov’t. mot., ex. F). The record does not reveal anything more happening until six months later when on September 3, 2020, HECO sent another REA to the government complaining about continuing delays arising from the paint issue, proposing the same plan of action as before, and seeking $559,589.35. This new REA clearly stated that “[t]he costing does not include any Covid related costs.” (R4, tab 26 at 240) Two weeks later, on September 17, the parties completed Modification No. 07 to the delivery order, settling the November 17, 2019, REA and “revised REA dated 27 December 2019.” 2 The modification “incorporate[d] the scope of work and corrective actions” of HECO’s September 3, 2020, REA, increased the contract price by the amount sought in that letter, $559,589.35, and extended the period of performance to April 30, 2021. It stated that “[a]cceptance of this modification by the contractor constitutes an accord and satisfaction and represents payment in full for both time and money and for any and all costs, impact effect and for any delays and disruptions arising out of, or incidental to, the work as herein revised.” (R4, tab 22 at 192-96)

3. Three months after Modification No. 07 was executed, on December 16, 2020, the government project manager forwarded to HECO “COVID related restrictions and requirements necessary for . . . [the] project.” They had been provided to the project manager by the “Crane Mechanical Engineer, SPB 243, Strategic Weapons Facility Pacific.” Generally, they entailed movement restrictions, trip questionnaires, COVID checklists, face covering and social distancing, and that HECO personnel were required to obtain permission to access the base. (R4, tab 26 at 274-76)

4. Around nine months later, on September 13, 2021, HECO submitted another REA for $322,886 for the impacts of the COVID rules that were imposed on it. It addressed the burdens and delays generated by complying with the trip questionnaires as well as the government’s delays responding to them and their frequent rejections. HECO also complained about completing forms, time spent hand washing, as well as addressing mask requirements. It added costs associated with losing the labor of ill employees, and increased shipping expenses it said were associated with COVID lockdowns. (R4, tab 24 at 205) After the government denied the REA on October 21, saying it was not liable for COVID costs, HECO sought reconsideration on November 1 (R4, tabs 25; 26 at 238). Among other things, it argued that government delays had pushed the work into the pandemic period, subjecting HECO to changed site conditions. It added that conditions required additional employee breaks. HECO included the claim certification required by 41 U.S.C. § 7103(b). (R4, tab 26 at 239) The government treated the November 1 submission as a claim and denied it on December 9, 2021 (R4, tab 27).

2 We suspect that it intended to refer to the December 23 revision (gov’t mot., ex. E).

2 5. HECO has appealed. After generally alleging facts, the complaint maintains government delays prevented HECO from completing the work prior to the onset of COVID, subjecting it to COVID related costs.

DECISION

The government moves for summary judgment. It argues (1) the appeal is barred by the doctrines of release or accord and satisfaction, (2) that HECO cannot recover for the impact of COVID restrictions because COVID was not foreseeable when the government first delayed performance, and (3) recovery is barred by the sovereign acts doctrine. We reject the first two theories and rule the government has not established the third.

I. Release/Accord & Satisfaction

The effect of a modification is often analyzed under both the doctrines of accord and satisfaction and release. See Haskell Co., ASBCA No. 63291, 24-1 BCA ¶ 38,537 at 187,332. “A release is a contractual defense where a party abandons a claim or relinquishes a right that could be asserted against another.” Id. It is interpreted like any other contract. We review its plain language. If clear and unambiguous it is given its plain and ordinary meaning. Bell BCI Co. v. United States, 570 F.3d 1337, 1341 (Fed. Cir. 2009). An accord and satisfaction occurs “when some performance different from that which was claimed as due . . . is accepted by the claimant as full satisfaction of his claim.” Id. at 1340-1341 (quoting Cmty. Heating & Plumbing Co. v. Kelso, 987 F.2d 1575, 1581 (Fed. Cir. 1993)). Among the elements of an accord and satisfaction is a meeting of the minds of the parties. Id. at 1341. That inquiry is fact specific and can entail review of a wide range of evidence. See Meridian Eng’g Co. v. United States, 885 F.3d 1351, 1365 (Fed. Cir. 2018).

The government says Modification No. 07 bars HECO’s claim for the costs it incurred complying with COVID related requirements. Modification No. 07 says it settles HECO’s November 17, 2019 REA, as revised in December, and incorporates the scope of work and corrective actions contained in HECO’s September 3, 2020, REA (SOF ¶ 2). The plain language therefore designates the contents of those documents for the description of what claims are being settled. The November 17, 2019, REA concerns government delays in 2019 associated with painting issues (SOF ¶ 1). It entirely predates COVID and cannot pertain to its effects or requirements imposed because of it.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Horowitz v. United States
267 U.S. 458 (Supreme Court, 1925)
Stockton East Water District v. United States
583 F.3d 1344 (Federal Circuit, 2009)
Bell Bci Co. v. United States
570 F.3d 1337 (Federal Circuit, 2009)
CONNER BROS. CONST. CO., INC. v. Geren
550 F.3d 1368 (Federal Circuit, 2008)
Dairyland Power Cooperative v. United States
16 F.3d 1197 (Federal Circuit, 1994)
Casitas Municipal Water District v. United States
543 F.3d 1276 (Federal Circuit, 2008)
Meridian Engineering Company v. United States
885 F.3d 1351 (Federal Circuit, 2018)

Cite This Page — Counsel Stack

Bluebook (online)
HECO Pacific Manufacturing, Inc., Counsel Stack Legal Research, https://law.counselstack.com/opinion/heco-pacific-manufacturing-inc-asbca-2025.