M.E.S., Inc. v. McHugh

502 F. App'x 934
CourtCourt of Appeals for the Federal Circuit
DecidedJanuary 15, 2013
Docket2012-1457, 2012-1466
StatusUnpublished
Cited by3 cases

This text of 502 F. App'x 934 (M.E.S., Inc. v. McHugh) is published on Counsel Stack Legal Research, covering Court of Appeals for the Federal Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
M.E.S., Inc. v. McHugh, 502 F. App'x 934 (Fed. Cir. 2013).

Opinion

PER CURIAM.

M.E.S., Inc. appeals a decision by the Armed Services Board of Contract Appeals (“Board”) denying M.E.S.’s claims for equitable adjustments under a construction contract. The Board found that M.E.S. had failed to present sufficient evidence to support the two claims at issue in this appeal. We affirm.

BACKGROUND

On September 29, 2001, the U.S. Army Corps of Engineers (“Corps”) awarded M.E.S. a $10.3 million firm-fixed-price contract to design and build a fitness center at McGuire Air Force Base in New Jersey. The scheduled duration of the contract was 720 days, with a planned completion date of November 4, 2003. The project was repeatedly delayed, for reasons ranging from unusually severe weather to the discovery of unexpected quantities of asbestos in the existing structure. The Corps *936 agreed to postpone the contract completion date twelve times, extending its duration by 345 days and awarding M.E.S. $626,469 in additional compensation. Three of the modifications were issued unilaterally by the Corps, and most of the remaining, bilateral modifications included a clause reserving MJE.S.’s right “to request additional compensation for the delay and impact costs, as well as any adjustment to the Overhead charged.” J.A. 3. Though M.E.S. disputes it, at least one modification appears to have included an allowance for additional home office overhead accrued by M.E.S. as a result of the delay. The work was substantially completed on October 14, 2004.

M.E.S. submitted five claims for equitable adjustments to the Corps’ contracting officer, totaling $1,250,597.33 (later amended to $1,593,949). The contracting officer denied each of the claims, and M.E.S. appealed to the Board. The Board sustained two of the appeals, awarding M.E.S. $105,286.03 (consisting of $97,908.70 for 155 days of additional field office overhead and $7377.33 for rental and installation of temporary bleachers, including profit and fourteen percent overhead), and denied three others. M.E.S. has appealed two of those denials.

In the first of the appealed claims (the “cost overrun claim”), M.E.S. sought $575,113 in cost overruns related to thirteen work activities, plus profit and overhead. M.E.S. sought compensation on two theories: first, that government-caused delays had created inefficiencies and increased M.E.S.’s material and labor costs, and second, that the government had constructively accelerated the project by denying M.E.S. additional time extensions. M.E.S. sought to recover the entire difference between the actual cost of each activity, including seven percent profit and fourteen percent overhead, and the projected value of the activity as included in its contract bid. The Board rejected this claim, finding that M.E.S. “ha[d] failed to prove that the claimed increased [cost] over and above the ‘as-bid’ amounts ... was caused by government-directed acceleration or ... government delays.” J.A. 11; see also J.A. 14 (noting that M.E.S. had “failed to establish a causative connection between the delays and the alleged increased costs claimed”).

In the second claim (the “overhead claim”), M.E.S. sought $459,845 in “additional Home Office Overhead Costs” for the added duration of the contract. J.A. 12 (quotation marks omitted). M.E.S. arrived at this figure by multiplying 210 days of allegedly government-caused delay 1 by a daily allocable home office overhead rate of $2189.74. 2 The Board rejected this claim, too, finding that:

None of these alleged dollar amounts [relied on by M.E.S. to calculate its daily rate] are supported in the evidentiary record by a [government] audit report, or in the absence of such report, by testimony or affidavit of the accountant preparing the claim or copies of the pertinent financial statements ... prepared contemporaneously in the regular course of business, or other persuasive substantiating accounting documents. *937 Moreover, nowhere in the [M.E.S.] calculation is there any allowance for home office expense paid in the price adjustments previously granted in the modifications for compensable government delays.

J.A. 13. The Board also found “no persuasive evidence that [M.E.S.] was required to remain on standby and/or was unable to shift its resources to other un-impacted work.” J.A. 12.

M.E.S. timely appealed the Board’s disposition of these two claims, and we have jurisdiction under 28 U.S.C. § 1295(a)(10).

DisoussioN

This court may set aside the Board’s determination on a question of fact only if it is “fraudulent, arbitrary, or capricious; ... so grossly erroneous as to necessarily imply bad faith; or ... not supported by substantial evidence.” 41 U.S.C. § 7107(b)(2). A determination is adequately supported if it is based on “such relevant evidence as a reasonable mind might accept as adequate to support a conclusion.” E.L. Hamm & Assocs. v. England, 379 F.3d 1334, 1338 (Fed.Cir.2004).

I. The Cost Overrun Claim

A. The delay theory

A contractor who seeks compensation for costs allegedly caused by government-imposed delays “has the burden of proving the fundamental facts of liability and damages.” Wilner v. United States, 24 F.3d 1397, 1401 (Fed.Cir.1994). Here, the Board found “no persuasive and particularized evidence ... establishing the nature and extent of specific interferences or inefficiencies and how they materially increased [M.E.S.’s] cost,” and concluded that “[M.E.S.] ha[d] failed to prove that the [cost overruns] w[ere] caused by ... compensable government delays.” J.A. 8, 11.

On appeal, M.E.S. points to testimony by its president and owner, George Makhoul, recounting the delays it experienced and tying them to a few specific cost escalators such as material and labor cost inflation and difficulty working in cold weather. M.E.S. has not attempted to quantify the specific additional costs directly attributable to any particular item, and instead has asserted that all its overruns on the thirteen activities, measured relative to the cost estimates developed for its bid, were caused by the delays. Substantial evidence therefore supports the Board’s conclusion.

B. The acceleration theory

Constructive acceleration occurs “when the government requires the contractor to adhere to the original performance deadline set forth in the contract even though ... excusable delay[s] ... entitle the contractor to a longer performance period.” Fraser Constr. Co. v. United States, 384 F.3d 1354, 1361 (Fed.Cir.2004).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Meltech Corporation, Inc.
Armed Services Board of Contract Appeals, 2026
WECC, Inc.
Armed Services Board of Contract Appeals, 2021
Garco Construction, Inc.
Armed Services Board of Contract Appeals, 2014

Cite This Page — Counsel Stack

Bluebook (online)
502 F. App'x 934, Counsel Stack Legal Research, https://law.counselstack.com/opinion/mes-inc-v-mchugh-cafc-2013.