WECC, Inc.

CourtArmed Services Board of Contract Appeals
DecidedOctober 19, 2021
DocketASBCA No. 60949
StatusPublished

This text of WECC, Inc. (WECC, Inc.) is published on Counsel Stack Legal Research, covering Armed Services Board of Contract Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
WECC, Inc., (asbca 2021).

Opinion

ARMED SERVICES BOARD OF CONTRACT APPEALS

Appeal of -- ) ) WECC, Inc. ) ASBCA No. 60949 ) Under Contract No. 73-0014-1522 )

APPEARANCES FOR THE APPELLANT: G. Scott Walters, Esq. Brian S. Wood, Esq. Alexander Gorelik, Esq. Jacob W. Scott, Esq. Smith, Currie & Hancock LLP Washington, DC

APPEARANCES FOR THE GOVERNMENT: Scott N. Flesch, Esq. Army Chief Trial Attorney LTC Stephen M. Hernandez, JA Harry M. Parent III, Esq. Trial Attorneys

OPINION BY ADMINISTRATIVE JUDGE MELNICK

This appeal involves a contract to renovate the exchange at Langley Air Force Base. WECC, Inc. seeks delay damages and other costs. We find that WECC is entitled to recover $546,446.11, plus interest.

FINDINGS OF FACT

I. The Contract

1. On February 13, 2014, the Army and Air Force Exchange Service (AAFES or government) awarded the contract identified above to WECC to upgrade the Langley Air Force Base Exchange (R4, tab 1). Among other things, the fixed price agreement required WECC to renovate and construct additions to the exchange store, food court, mall, garden area, and shipping areas (R4 tabs 1, 3).

2. The contract drawings identified five separate building areas. They were Administrative, Retail, Mall Shops, Mall Corridor, and Food Court. Each area was then broken into multiple phases reflecting more specific locations in an area. For instance, Phase R-1 in the Retail area was ladies wear and Phase R-8 was menswear, or Phase M-1 in the Mall Shops was the barbershop and Phase M-4 was the beauty salon. WECC was to perform the work in each area in the phased sequences shown on the drawings, which also specified the number of days that WECC was to spend in each phase. (R4, tab 2 at 4, tab 3 at 39, 111; demo. ex. 1; tr. 1/80) WECC was required to start work within 10 days of its receipt of the March 5, 2014 notice to proceed, and finish 240 days after the receipt, or by October 31, 2014 (R4, tab 1 at 1, tab 17 at 1). In the event WECC failed to complete the work on time, the contract imposed $1,500 in liquidated damages for each day of delay (R4, tab 1 at 55).

3. As required by the contract, WECC prepared a baseline schedule that followed the contract’s phase requirements. In accordance with the drawings, the schedule planned for work to proceed in multiple areas concurrently. For each area it established a logical order of specific activities within each phase. (R4, tab 3 at 127, tab 264; demo. ex. 2; tr. 1/88-90, 99-101) Because WECC worked simultaneously in different areas, there were many chains of sequential activities on the project (R4, tab 2 at 4, tab 264). However, the chain with the longest duration was the “critical path.” As the longest chain, it reflected the earliest the project could be completed (tr. 2/44). Any delay of a task on the critical path would delay completion of the overall project. As planned, the critical path started with mobilization and then ran through the Retail phases. (R4, tab 234 at 10-11, tab 264 at 1, 3-10; tr. 1/96-97, 109)

4. This contract with AAFES was not subject to the Federal Acquisition Regulation, but contained several clauses imposing comparable provisions (R4, tab 1 at 7). Thus, it contained Differing Site Conditions, Suspension of Work, Liquidated Damages, Retainage, and Changes clauses. Changes were further governed by General Provision 37 controlling price adjustments. (R4, tab 1 at 12, 19-21, 23, 26-27, 29, 55)

II. Performance, Change Orders, and the Claim

5. On March 19, 2014, shortly after receiving the notice to proceed, WECC and its subcontractor encountered unexpected conditions in the floors, which included a second layer of tile beneath the top layer, and an excessively deep mud bed (R4, tab 31 at 3, tab 78 at 11, tab 250; tr. 2/34-35). WECC also discovered that the concrete slab beneath the tile and mud bed was in such poor condition it could not be polished to the glossy surface contemplated by the contract. Instead, WECC had to remove and replace it. (R4, tab 36 at 6; tr. 1/123, 133-34) The government did not approve Change Order No. 11, in Amendment No. 2, for the replacement of concrete until June 19, 2014, and issued unilateral Change Order No. 6A for the demolition of the additional layers on August 27, (R4, tabs 36, 78). Change Order No. 11 was for $253,713. WECC’s proposal for the change excluded additional time, extended overhead, and general conditions due to delays until the actual impact could be ascertained (R4, tab 36 at 11, 14). Although the amendment contained language stating that it was “in full settlement of all entitlements...arising from the changes,” it also included documents where the parties recognized that extended overhead would be negotiated once all the work was completed (R4, tab 36 at 1-4, 14). WECC was able to perform work while it waited for the government to approve Change

2 Order No. 11 but not on the established schedule (tr. 1/153, 227). Also, the government did not release Mall Corridor Phase M-1A for concrete replacement until July 14, 2014 (tr. 1/140-41). The new concrete was poured between July 17 and 26 or 27 (R4, tab 234 at 15; demo. ex. 8; tr. 1/138, 140-41).

6. On August 11, 2014, while excavating for a footer in the M-1A phase, WECC discovered a storm drain that was not on any plans (R4, tab 85 at 3; tr. 1/141-42, 2/44-48; demo. ex. 8). This required WECC to suspend digging until the government unilaterally issued Change Order No. 52, in Contract Amendment No. 6, on September 29, 2014. WECC was then required to excavate and remove the storm drain and install a new one elsewhere. The change order for $55,940.87 was the full amount WECC had proposed. However, it failed to extend the contract performance period from August 11 until the work was completed, as requested by WECC. Accordingly, WECC reserved the right to seek an equitable adjustment for any extended overhead and general conditions costs. (R4, tab 85 at 1, 3, 20-22; tr. 1/142)

7. In six contract amendments issued during performance, the government acknowledged that the period of performance should be extended for a total of 89 days, to January 28, 2015. WECC signed two of those amendments. The first, Amendment No. 1, issued in May of 2014, approved additional direct costs associated with six change orders dealing with ventilation and plumbing, electrical panels, coil relocation, bulkheads and sprinklers, a floor drain, and light fixtures. It included $8,482 in Change Order No. 4 to relocate the coil and granted a 10-day extension. No extended overhead was included and WECC agreed that the amendment was “in full settlement of all entitlements directly or indirectly arising from the changes.” (R4, tab 29) The second, Amendment No. 3, issued in July of 2014, approved direct costs associated with 13 change orders dealing with a freezer floor, electrical panel, feeder cables, gun vault, variable frequency drive, glazing, oven power, poles, light wires, angle removal, transition strip, sills, and a fire connection. It included $18,127.99 in Change Order No. 15 to extend feeder cables and granted 10 more days of extension. Again, no extended overhead was included and WECC agreed that the amendment fully settled all entitlements arising from the changes. (R4, tab 60)

8. The other four amendments granting the remaining 69 days were unilateral orders by the government. Amendment No. 7, issued September 30, 2014, generally added 35 days through Change Order No. 42 and stated that the parties would discuss additional days at the end of the project. The amendment also included Change Order No. 54, adding 7 days for slab replacement at the main entrance for $10,941; and Change Order No. 67, adding 3 days for asbestos abatement in the barber shop for $5,231 (R4, tab 88). 1 Amendment No. 10 included Change Order No. 38A, adding

1 Amendment No.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Holland v. United States
621 F.3d 1366 (Federal Circuit, 2010)
Bell Bci Co. v. United States
570 F.3d 1337 (Federal Circuit, 2009)
Brock & Blevins Company, Inc. v. The United States
343 F.2d 951 (Court of Claims, 1965)
Blinderman Construction Co., Inc. v. The United States
695 F.2d 552 (Federal Circuit, 1982)
C.B.C. Enterprises, Inc. v. The United States
978 F.2d 669 (Federal Circuit, 1992)
M.E.S., Inc. v. McHugh
502 F. App'x 934 (Federal Circuit, 2013)
Meridian Engineering Company v. United States
885 F.3d 1351 (Federal Circuit, 2018)
King Fisher Marine Service, Inc. v. United States
35 Cont. Cas. Fed. 75,616 (Court of Claims, 1989)
P.J. Dick Inc. v. Principi
324 F.3d 1364 (Federal Circuit, 2003)

Cite This Page — Counsel Stack

Bluebook (online)
WECC, Inc., Counsel Stack Legal Research, https://law.counselstack.com/opinion/wecc-inc-asbca-2021.