H. Lawrence Garrett, Iii, Secretary of the Navy v. General Electric Company

987 F.2d 747, 38 Cont. Cas. Fed. 76,486, 1993 U.S. App. LEXIS 3049, 1993 WL 46874
CourtCourt of Appeals for the Federal Circuit
DecidedFebruary 24, 1993
Docket92-1119
StatusPublished
Cited by57 cases

This text of 987 F.2d 747 (H. Lawrence Garrett, Iii, Secretary of the Navy v. General Electric Company) is published on Counsel Stack Legal Research, covering Court of Appeals for the Federal Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
H. Lawrence Garrett, Iii, Secretary of the Navy v. General Electric Company, 987 F.2d 747, 38 Cont. Cas. Fed. 76,486, 1993 U.S. App. LEXIS 3049, 1993 WL 46874 (Fed. Cir. 1993).

Opinions

RADER, Circuit Judge.

The Department of the Navy appeals a decision of the Armed Services Board of Contract Appeals (Board). The Board held that it had jurisdiction over General Electric Company’s (GE) appeal from a nonmon-etary Navy order for work corrections. General Elec. Co., ASBCA No. 36005, 91-2 BCA 1123,958, 1991 WL 81497 (1991). Because the Contract Disputes Act of 1978 (CDA or Act), Pub.L. No. 95-563, 92 Stat. 2383 (codified as amended at 41 U.S.C. §§ 601-613 (1988 & Supp. I 1989)), permits appeal of the contracting officer’s final decision on a claim, this court affirms.

BACKGROUND

The Navy awarded GE a series of eighteen production contracts from November 1977 through March 1987. Under the contracts, GE manufactured approximately 1200 jet engines for the F/A-18A aircraft. After accepting a number of new engines, the Navy experienced several incidents of buckling in an engine component known as the after-burner liner. These failures damaged the engine and the aircraft.

Each contract contained an inspection clause from the Federal Acquisition Regulations (FAR) or from an earlier version, the Defense Acquisition Regulations (DAR). These clauses made acceptance of the engines final except for latent defects, fraud, or gross mistakes amounting to fraud. See, e.g., 48 C.F.R. § 52.246-2(k) (1991). In the event of latent defects, the contracts provided remedies such as: (1) a requirement that the contractor correct or replace the item at no increase in contract price; (2) a reduction in contract price for delays; or (3) repayment of an equitable portion of the contract price. See, e.g., id. § 52.246-2(1). Each contract also included a FAR or DAR disputes clause. The disputes clauses require the parties to resolve disputes under the Contract Disputes Act.

The Navy paid GE $1.25 million under a separate component improvement program (CIP) to investigate the cause of and suggest a solution for the engine failures. On the basis of the study, the Navy concluded that latent defects — undiscoverable at the time of acceptance — caused the engine liner failures. The Navy directed GE to replace the defective parts in those engines at no additional cost. GE refused and sub[749]*749mitted a proposal to replace the parts at a substantial additional cost to the Navy.

After further meetings and correspondence, the contracting officer (CO) issued a final decision requiring GE to correct the problem at no additional cost to the Navy. The decision vitiated the prior acceptances under the inspection clause. The decision also required GE to return the $1.25 million in CIP funds to the Navy.

GE appealed the CO’s decision to the Board. The Board took jurisdiction based on the Navy’s assertion of post-acceptance contract rights. The Board reasoned that the Navy’s actions constituted a claim by the Government under the CDA.

DISCUSSION

This court reviews whether the Board properly asserted jurisdiction over GE’s appeal of the CO’s decision. On appeal, the Board’s legal conclusion on jurisdiction is not final or conclusive. 41 U.S.C. § 609(b) (1988).

The CDA grants the Board jurisdiction over cases arising from Government contracts for the procurement of equipment and services. 41 U.S.C. § 602(a). In particular, the Act authorizes the Board to exercise jurisdiction over appeals from a CO’s final decision on Government or contractor “claims.” Id. §§ 605(a), 607(d). GE submitted no claims to the CO on the engine defects at the time of the decision. The Act, however, provides that a contractor may appeal a Government claim to the appropriate board without submitting a claim of its own to the CO. See id. Thus, only jurisdiction over the Navy’s claims under the contract are at issue in this appeal. The Board’s jurisdiction depends on whether the Navy’s directives under the contract’s inspection clause are appealable CDA claims.

The CDA does not specifically define the term “claim.” Therefore, this court assesses whether an action amounts to a claim on the basis of “regulations implementing [the CDA], the language of the contract in dispute, and the facts of the ease.” Dawco Constr., Inc. v. United States, 930 F.2d 872, 877 (Fed.Cir.1991). The FAR, the applicable regulation, defines a claim as a “written demand ... by one of the contracting parties seeking, as a matter of right, [1] the payment of money in a sum certain, [2] the adjustment or interpretation of contract terms, or [3] other relief arising under or relating to the contract.” 48 C.F.R. § 33.201 (1991). The GE contracts contained this definition. Therefore, these regulations and the terms of GE’s contracts agree on the standard for determining the meaning of “claim” for Board jurisdiction. This court must also assess the facts of this case in assessing the sufficiency of the Navy’s claim.

The Navy directed GE to correct or replace the defective engines. Under the contract, the Navy had three options. It could have reduced the contract price or demanded repayment of an equitable portion .of the contract price. Rather than seek these monetary remedies, the Navy chose “other relief arising under ... the contract.” The Navy’s alternative to a monetary remedy — the directive to correct or replace defective engines — constitutes “other relief” within the FAR’s third category of “claims.” Thus, the regulations, GE’s contract, and the facts of this case suggest that the Navy’s choice of relief — a substitute for monetary remedies — fit within the CDA concept of “claim.” Accordingly, the Board correctly determined its jurisdiction to adjudicate this Government claim.

This court also assesses whether the Board’s decision to take jurisdiction over the Navy’s claim is in harmony with the purpose and structure of the CDA. One primary purpose of the CDA, invoked by both parties in this appeal, is to achieve parity between the jurisdiction of the United States Court of Federal Claims and the boards. The CDA has as one of its purposes the elimination of differences in the jurisdictions of the forums which decide Government contract disputes. See, e.g., S.Rep. No. 1118, 95th Cong., 2d Sess. 12 (1978) 1978 U.S.Code Cong. & Admin.News pp. 5235, 5246 (“The considerable disharmony between the administrative and judicial [750]*750systems that oversee the resolution of disputes was a matter of considerable concern to the Procurement Commission.... [The CDA provides a] pragmatic answer.”). Thus, the CDA provides for appeals from a CO’s decision alternatively to either the Board or directly to the Court of Federal Claims. See 41 U.S.C. §§ 607, 609 (1988). The Act further states that the Board “is authorized to grant any relief that would be available to a litigant asserting a contract claim in the United States [Court of Federal Claims].” Id. § 607(d). Thus, the CDA creates parity between these two lines of appeal.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

The Sithe Group, LLC, dba TSG Industries
Armed Services Board of Contract Appeals, 2024
J&J Maintenance, Inc., d/b/a J&J Worldwide Services
Armed Services Board of Contract Appeals, 2023
Lockheed Martin Aeronautics Company
Armed Services Board of Contract Appeals, 2021
JAAAT Technical Services, LLC
Armed Services Board of Contract Appeals, 2021
Parsons Government Services, Inc.
Armed Services Board of Contract Appeals, 2020
Harper Constr. Co. v. Nat'l Union Fire Ins. Co. of Pittsburgh
377 F. Supp. 3d 1134 (S.D. California, 2019)
Greenland Contractors I/S
Armed Services Board of Contract Appeals, 2019
Hensel Phelps Construction Co.
Armed Services Board of Contract Appeals, 2018
Securiforce International America, LLC v. United States
879 F.3d 1354 (Federal Circuit, 2018)
Magnus Pacific Corporation v. United States
133 Fed. Cl. 640 (Federal Claims, 2017)
DynPort Vaccine Company LLC
Armed Services Board of Contract Appeals, 2015
Sikorsky Aircraft Corporation v. United States
773 F.3d 1315 (Federal Circuit, 2014)
Bay County, Florida v. United States
117 Fed. Cl. 131 (Federal Claims, 2014)
K-Con Building Systems, Inc. v. United States
107 Fed. Cl. 571 (Federal Claims, 2012)
M.E.S., Inc. v. United States
104 Fed. Cl. 620 (Federal Claims, 2012)
Pacific Gas & Electric Co. v. United States
105 Fed. Cl. 420 (Federal Claims, 2012)

Cite This Page — Counsel Stack

Bluebook (online)
987 F.2d 747, 38 Cont. Cas. Fed. 76,486, 1993 U.S. App. LEXIS 3049, 1993 WL 46874, Counsel Stack Legal Research, https://law.counselstack.com/opinion/h-lawrence-garrett-iii-secretary-of-the-navy-v-general-electric-company-cafc-1993.