Greenland Contractors I/S

CourtArmed Services Board of Contract Appeals
DecidedJanuary 29, 2019
DocketASBCA No. 61113, 61248
StatusPublished

This text of Greenland Contractors I/S (Greenland Contractors I/S) is published on Counsel Stack Legal Research, covering Armed Services Board of Contract Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Greenland Contractors I/S, (asbca 2019).

Opinion

ARMED SERVICES BOARD OF CONTRACT APPEALS

Appeals of -- ) ) Greenland Contractors I/S ) ASBCA Nos. 61113, 61248 ) Under Contract No. FA2523-15-C-0002 )

APPEARA.tl\JCES FOR THE APPELLANT: James J. McCullough, Esq. Michael J. Anstett Esq. Anayansi Rodriguez, Esq. Fried, Frank Harris, Shriver & Jacobson LLP Washington, DC

APPEARANCES FOR THE GOVERNMENT: Jeffrey P. Hildebrant, Esq. Air Force Deputy Chief Trial Attorney Kyle E. Gilbertson, Esq. Trial Attorney

OPINION BY ADMINISTRATIVE JUDGE D'ALESSANDRIS ON THE GOVERN:r-v1ENT'S SECOND MOTION TO DISMISS

Pending before the Board is the four-page motion to dismiss filed by respondent, the Department of the Air Force (Air Force or government). As the procedural posture of these appeals is complex, it is explained in detail below.

Greenland Contractors I/S (Greenland) filed its first appeal, ASBCA No. 61113, in April 2017, from what Greenland contended was a government claim for contract interpretation regarding maintenance of electrical generation equipment, referred to as engines #1 through #5, at Thule Air Force Base in Greenland. The Air Force filed its first motion to dismiss before a complaint was filed. While that motion to dismiss was pending, Greenland filed its second appeal, ASBCA No. 61248, from what it contends is a government claim in the nature of a unilateral deductive modification in the amount of $3.2 million, pursuant to the inspection clause, for work purportedly required by the contract, but not perf01med by Greenland.

On December 8, 2017, the Board denied the Air Force's first motion to dismiss. Greenland Contractors IS, ASBCA Nos. 61113, 61248, 18-1 BCA ,r 36,942. Based upon the limited record before us at that time, we held that the Air Force had asserted a non-monetary government claim for other relief. Subsequent to that opinion, the Board denied Greenland's motions to require the government to file the complaint in the then consolidated appeals (ASBCA Nos. 61113 and 61248). Greenland filed its complaint on February 12, 2018. Relevant to the pending motion, Greenland included in its prayer for relief a request that the Board "[d]etermine that the Air Force's unilateral contract modification was factually and legally in error, entitling Greenland Contractors to return of the Air Force's claimed $3.2 million in withheld amounts" (compl. at 24).

The government then filed the instant motion to dismiss asserting two jurisdictional challenges: first, because Greenland had not presented its purported monetary claims to the contracting officer; and second, because ASBCA No. 61113 was not timely filed. Greenland opposed the government's motion. Although not addressed by the Air Force in its motion to dismiss, Greenland's complaint also indicated that it had "pe1formed the directed repairs [to engine #1] by September 30, 2017 at a cost of$422,086" (compl. at 21, ,r 100).

The Board raised the issue of Greenland's performance of purportedly additional work with the parties in a telephonic status conference on May 30, 2018. Greenland subsequently indicated that it would present a claim for its additional costs of performance which it did. An Air Force contracting officer denied Greenland's claim on October 2, 2018 (R4, tab 17). Greenland appealed this denial to the Board and the appeal was docketed as ASBCA No. 61834, 1 and consolidated with ASBCA Nos. 61113 and 61248. Greenland filed its consolidated complaint on November 13, 2018 (consol. comp1. ). By order dated October 17, 2018, the Board invited the government to file a supplemental brief addressing any new information relevant to its pending motion. On December 13, 2018, the government provided notice that it would not file a supplemental brief.

Not addressed by the government, but relevant to our dete1mination of jurisdiction, Greenland asserts in its consolidated complaint three instances where it was directed to pe1form work on engines #1 and #3 that Greenland contends was beyond the scope of its contract or was additional work caused by the Air Force's failure to perform work that Greenland contends the Air Force was required to perf01m under the contract (R4, tab 16 at 3). Specifically, Greenland asserts that its subcontractor repaired the master and articulating rod on engine # l at a cost of $237,941.02 (consol. compl. at 20, ,r,r 90-91). This work was invoiced on February 28, 2017, and Greenland paid the invoice on Aptil 12, 2017 (R4, tab 16 at 22-25). Greenland asserts that its subcontractor repaired the left camshaft on engine #3 at a cost of $257,803.64 (consol. compl. at 28, ,r,r 135-36). This work was invoiced on May 31, 2017, and paid on August 30, 2017 (R4, tab 16 at 48-54). In addition, Greenland contends that its subcontractor performed additional repairs to engine # 1 at

1 The government's motion to dismiss only pertains to ASBCA Nos. 61113 and 61248 which are consolidated with ASBCA No. 61834.

2 a cost of $422,085.99 (consol. compI. at 29, ,r,r 142-43 ). These costs were invoiced on September 12, 2017, and paid on November 3, 2017 (R4, tab 16 at 34-41).

The government's pending motion to dismiss asserts that ASBCA Nos. 61113 and 61248 must be dismissed because Greenland seeks ·'return of the Air Force's claimed $3.2 million in withheld amounts'' (gov't mot. at 1 (quoting compl. at 24)). According to the Air Force, the quoted language means that Greenland is asserting a money claim that was not certified and was not presented to the contracting officer, and thus that we are without jmisdiction to entertain the claim. The Air Force relies on the Court of Appeals for the Federal Circuit's holding in Securtforce International America, LLC v. United States, 879 F.3d 1354, 1360 (Fed. Cir. 2018), for the proposition that Greenland's claim is, in essence, a monetary claim, and thus, Greenland was required to present the claim to the contracting officer for a final decision (gov't mot. at 1-2). In opposition, Greenland asserts that its future entitlement to repayment of funds withheld by the Air Force does not convert its nonmonetary claims into prematm·e claims for money damages, and points out that certification is not required for a gove1nment claim (app. opp'n at 9-13). In its reply brief, the Air Force doubles-down on its argument asserting that Greenland was required to present a claim requesting a sum certain to the contracting officer asserting that Securiforce makes no distinction between government and contractor claims, and that the "only practical result" of granting Greenland's requested relief would be money damages against the government (gov't reply at 1-6). The Air Force additionally cites to the Civilian Board of Contract Appeals' decision in Duke University v. Dept. ofHealth and Human Services, CBCA No. 5992, 18-1 BCA ,r 37,023. 2 The Air Force "disputes" that its contract modification, deleting $3.2 million from the contract for work it contends was required by the contract but not performed, was a government claim (gov't reply at 5).

In our opinion denying the government's first motion to dismiss, we held that ASBCA No. 61113 was a government claim. Greenland, 18-1 BCA ,r 36,942 at 179,972-73. It is beyond dispute that a contractor is not required to certify a government claim. See, e.g., Placeway Construction Corp. v. United States, 920 F.2d 903,906 (Fed. Cir. 1990)~ 41 U.S.C. § 7103(a).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
Greenland Contractors I/S, Counsel Stack Legal Research, https://law.counselstack.com/opinion/greenland-contractors-is-asbca-2019.