The Sithe Group, LLC, dba TSG Industries

CourtArmed Services Board of Contract Appeals
DecidedApril 3, 2024
Docket63605
StatusPublished

This text of The Sithe Group, LLC, dba TSG Industries (The Sithe Group, LLC, dba TSG Industries) is published on Counsel Stack Legal Research, covering Armed Services Board of Contract Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
The Sithe Group, LLC, dba TSG Industries, (asbca 2024).

Opinion

ARMED SERVICES BOARD OF CONTRACT APPEALS Appeal of - ) ) The Sithe Group, LLC, dba TSG Industries ) ASBCA No. 63605 ) Under Contract No. W9126G-18-P-0012 )

APPEARANCES FOR THE APPELLANT: Thomas Dunlap, Esq. Alexander Jonathan Brittin, Jr., Esq. Dunlap Bennett & Ludwig PLLC Vienna, VA

APPEARANCES FOR THE GOVERNMENT: Michael P. Goodman, Esq. Engineer Chief Trial Attorney Erin Zetterstrom, Esq. Engineer Trial Attorney U.S. Army Engineer District, Galveston

OPINION BY ADMINISTRATIVE JUDGE WILSON ON THE GOVERNMENT’S MOTION TO DISMISS

The Board, sua sponte, questioned whether it has jurisdiction over this appeal. The United States Army Corps of Engineers (USACE or government) subsequently moved to dismiss this appeal for lack of jurisdiction, contending that The Sithe Group, LLC, dba TSG Industries (TSG) failed to file a timely appeal from the contracting officer’s final decision (COFD) pursuant to the 90-day limitations period in the Contract Disputes Act, 41 U.S.C. § 7104 (CDA). For the reasons stated below, we grant USACE’s motion and dismiss the appeal.

STATEMENT OF FACTS (SOF) FOR PURPOSES OF THE MOTION

1. On November 26, 2017, USACE awarded Contract No. W9126G-18-P-0012 to TSG for site preparation, installation, and purchase or lease of modular buildings to provide classrooms, an office trailer, and a restroom for the Orangefield Elementary School in Orangefield, Texas (gov’t reply at 2, ex. 4 at 48).

2. TSG alleges that, on or about June 14, 2018, TSG substantially completed performance under the contract, (app. resp. at 1; gov’t reply at 2 and ex. 1).

3. On June 18, 2018, TSG executed an assignment of payment on the contract to SouthStar Financial, LLC (SouthStar) (gov’t reply at 2 and ex. 2). 4. On or around July 1, 2018, TSG submitted a request for equitable adjustment (REA) to USACE requesting $1,087,852.97 for unpaid contract funds, additional costs incurred, damages, and lost profits. TSG claimed that these costs were the result of USACE adding work beyond what was originally specified in the contract, providing faulty design specifications, and causing schedule delays. (Gov’t reply at 2 and ex. 3; app. resp. at 1) On July 13, 2018, citing the remaining punch list work, USACE advised TSG that it was 163 calendar days beyond the January 31, 2018 contract completion date and had incurred over $400,000 in liquidated damages (gov’t reply at ex. 1 at 2).

5. On August 23, 2018, TSG and USACE held an REA settlement conference. After several months of correspondence, TSG and USACE accepted, in principle, a USACE provided settlement offer on November 2, 2018. (Gov’t reply, ex. 4 at 48; app. resp. at 2) According to a contracting officer’s memorandum, for the next several weeks, TSG and USACE attempted to negotiate the final language to their settlement agreement, but on November 29, 2018, TSG withdrew from the settlement negotiations. After TSG’s withdrawal, USACE committed to provide a response to the REA on the merits by December 21, 2018. (Gov’t reply, ex. 4 at 48)

6. On December 20, 2018, USACE issued a “Memorandum for the File” which responded to TSG’s REA; the decision approved TSG’s request in small part and denied the remainder (gov’t reply, ex. 4; app. resp., ex. 3). The contracting officer determined that TSG was entitled to an additional nine days of contract duration due to weather delays and an increase in the contract price of $6,075 to account for additional concrete aggregate. The decision noted that these adjustments would be considered “in connection with the assessment of liquidated damages” and work TSG did not complete. The remaining items in the REA were otherwise denied. (Gov’t reply at 2 n.2 and ex. 4 at 48; app. resp. at 3-4, ex. 3)

7. On December 20, 2018, the contracting officer executed a unilateral modification to the contract (P00003) which adjusted the contract by incorporating the approved REA entitlement ($6,075 and a 9-calendar day extension), assessed liquidated damages of 157 calendar days totaling $390,705.49, and reduced the contract price by $1,600 for nonconforming supplies or services (gov’t reply at 2-3 and ex. 5 at 56; app. resp. at 3-4).

8. Around January and February of 2019, a series of email correspondence occurred between Mr. Theodore Sims, the managing partner of TSG, and USACE (app. resp., ex. 5). In an email dated February 8, 2019, Mr. Jeffrey Neill, the Galveston District Chief of Contracting, replied to TSG’s payment request and stated that the remaining balance could not be paid due to a defective invoice submitted by TSG and that TSG needed to submit an ENG 93 form (i.e., a payment estimate for contract performance form) and supporting information for the final payment to be

2 processed (app. resp. at 5-6 and ex. 5 at 39). In a second email dated February 12, 2019, Mr. Neill provided additional information about what constituted an acceptable invoice and further stated, “since this is the final payment, you will need to include a release of claims with any exclusions identified therein (e.g., you probably want to exclude the issues in your former REA).” Mr. Neill stated he attached a sample release statement for TSG’s convenience. (App. resp. at 6 and ex. 5 at 36) On August 27, 2019, Mr. Sims submitted an ENG 93 form to USACE (app. resp. at 6 and ex. 6).

9. According to a declaration submitted by Mr. Sims, he believed that “USACE would not provide a final payment for the remaining balance of the Contract until a final settlement agreement was reached and TSG executed a release of claims” (app. resp. at 7 and ex. 8 at 50).

10. On December 19, 2019, TSG submitted its first certified claim to Mr. Curtis Cole, the USACE contracting officer, for $1,780,428.76 which incorporated TSG’s denied REA claims and disputed the assessment of liquidated damages, alleging the government caused the delays (gov’t reply at 3 and ex. 7; app. resp. at 7). The certified claim also contained the statement, “the USACE stated that remaining payment under the Contract could not be made unless TSG executed a release of claims. The Contract provides no such requirement.” (Gov’t reply, ex. 7 at 70). The contracting officer sent TSG an acknowledgement of receipt of the claim by email on December 31, 2019, and indicated that a COFD would be issued by February 24, 2020 (gov’t reply at 3 and ex. 8).

11. By email dated January 6, 2020, Mr. Sims provided a copy of the certified claim to Colonel Robert Miceli, USACE Deputy Director of Contracting, and requested that he review and acknowledge receipt of the certified claim. By email and letter dated January 7, 2020, Mr. David Curry, the acting Senior Contracting Official at Dallas, responded to TSG on Colonel Miceli’s behalf by acknowledging that the contracting officer was in receipt of TSG’s claim and informed Mr. Sims that a COFD would be issued by February 24, 2020. Mr. Curry further advised Mr. Sims that Mr. Cole was the contracting officer and that if he had any further questions, he could contact Mr. Cole. (Gov’t reply at 3 and ex. 9, attach. 1)

12. Following the February 12, 2019, email and TSG’s submission of its certified claim, Mr. Neill states, by affidavit, that he had telephonic discussions with Mr. Sims in which he advised TSG that a release of claims was not required for an invoice to be paid (gov’t reply at 3-4 n.5 and ex. 12 at 98). 1

1 In his affidavit, Mr. Neill states he informed Mr. Sims that he could also include any exclusions within the release of claims so that TSG could later submit an REA or claim (gov’t reply, ex. 12 at 98).

3 13. By email and letter dated April 2, 2020, TSG sent a revised certified claim to USACE seeking $1,695,718.55 (gov’t reply at 3 and ex. 11; app. resp. at 7).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Riley & Ephriam Construction Co. v. United States
408 F.3d 1369 (Federal Circuit, 2005)
Cosmic Construction Co. v. The United States
697 F.2d 1389 (Federal Circuit, 1982)
The Borough of Alpine v. The United States
923 F.2d 170 (Federal Circuit, 1991)
Menominee Indian Tribe of Wis. v. United States
577 U.S. 250 (Supreme Court, 2016)

Cite This Page — Counsel Stack

Bluebook (online)
The Sithe Group, LLC, dba TSG Industries, Counsel Stack Legal Research, https://law.counselstack.com/opinion/the-sithe-group-llc-dba-tsg-industries-asbca-2024.