Riley & Ephriam Construction Co. v. United States

408 F.3d 1369, 2005 U.S. App. LEXIS 8817, 2005 WL 1163017
CourtCourt of Appeals for the Federal Circuit
DecidedMay 18, 2005
Docket2004-5152
StatusPublished
Cited by76 cases

This text of 408 F.3d 1369 (Riley & Ephriam Construction Co. v. United States) is published on Counsel Stack Legal Research, covering Court of Appeals for the Federal Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Riley & Ephriam Construction Co. v. United States, 408 F.3d 1369, 2005 U.S. App. LEXIS 8817, 2005 WL 1163017 (Fed. Cir. 2005).

Opinion

CLEVENGER, Circuit Judge.

Riley & Ephriam Construction Company, Inc. (“R & E”) appeals the grant of summary judgment in favor of the United States (“government”) by the Court of Federal Claims.based on the determination'that R & E’s, claims were untimely filed under the Contract Disputes Act (“CDA”). Riley & Ephriam Constr. Co. v. United States, 61 Fed.Cl. 405 (2004). Because the Court of Federal Claims erred in determining when the contracting officer’s final decision had been received by the contractor, it incorrectly determined that the statute of limitations barred R & E’s claim. We reverse the grant of summary judgment in favor of the government and hold that R & E’s claims were timely filed.

*1371 I

R & E entered into a contract with the government that could not be completed as originally agreed due to unforeseen conditions at the jobsite. R & E listed a Post Office box (“P.O.box”) in Stone Mountain, Georgia, as its contact address for matters relating to this contract. On March 8, 2000, after the parties could not agree to an adjustment of the contract, R & E applied for an equitable adjustment in the amount of $294,097. While the contracting officer was reviewing this request, R & E closed its corporate offices and ran the business from a home. R & E continued to maintain the Stone Mountain P.O. box.

The equitable adjustment was finally denied on November 27, 2001. On this date, the contracting officer mailed the final decision in the equitable adjustment claim via certified letter addressed to R & E’s P.O. box and faxed a copy of the final decision to the fax number on file for R & E’s attorney. R & E’s attorney claims to have never received this fax and the government is unable to produce a fax transmittal sheet. The certified letter arrived at the Post Office on November 30, 2001, at which time a postal employee placed a notice in R & E’s box that the letter could be picked up at the counter. The Post Office placed a second notice in the P.O. box on December 19, 2001. R & E did not pick up the letter and on December 29, 2001, the Post Office returned the certified letter unsigned to the contracting officer. Upon receipt of the unclaimed certified letter and the unexecuted return receipt form, the government was on notice that no authorized person had received the certified mail.

In January of 2002, the contracting officer called the attorney to notify him that the letter was returned and asked if the attorney would accept another copy of the final decision on behalf of R & E. On January 30, 2002, the contracting officer faxed the attorney a message that the letter had been resent to the firm’s address. Less than one year later, on January 24, 2003, R & E filed suit in the Court of Federal Claims for $306,039.33 in damages resulting from the additional work performed on the contract.

Before the Court of Federal Claims, the government moved for summary judgment based on the statute of limitations time bar in the CDA that requires suit to be filed within twelve months of the contractor’s actual receipt of the contracting officer’s final decision. 41 U.S.C. § 609(a)(3) (2000). The Court of Federal Claims found that R & E had received the final decision because both the fax sent on November 27, 2001, and the certified letter sent on the same date were deemed actually received by the contractor. Riley & Ephriam, 61 Fed.Cl. at 411. Because R & E filed suit on January 24, 2003, the Court of Federal Claims found that the twelvemonth statute of limitations barred the claim and granted the government’s motion for summary judgment. Id. R & E now appeals the decision of the Court of Federal Claims. We have jurisdiction over an appeal from a final decision of the Court of Federal Claims pursuant to 28 U.S.C. § 1295 (2000).

II

This court reviews the grant of summary judgment de novo. Insituform Techs., Inc. v. CAT Contracting, Inc., 385 F.3d 1360, 1377 (Fed.Cir.2004). Summary judgment is appropriate when the moving party is entitled to judgment as a matter of law and no disputes over material facts remain. Fed. Cl. R. 56(c). The moving party bears the burden of demonstrating the absence of a genuine issue of material fact. Celotex Corp. v. Catrett, 477 U.S. 317, 322-25, 106 S.Ct. 2548, 91 L.Ed.2d 265 (1986). All justifiable inferences should be *1372 drawn in favor of the nonmovant. Anderson v. Liberty Lobby, Inc., 477 U.S. 242, 255, 106 S.Ct. 2505, 91 L.Ed.2d 202 (1986).

Ill

The burden is. on the government to prove the earlier date of receipt. See, e.g., Pub. Serv. Cellular, Inc., ASBCA No. 52489, 00-1 BCA ¶ 30,832 (Mar. 2, 2000). The CDA states that:

a contractor may bring an action directly on the claim in the United States Court of Federal Claims .... [This] action ... shall be filed within twelve months from the date of the receipt by the contractor of the decision of the contracting officer concerning the claim, and shall proceed de novo in accordance with the rules of the appropriate court.

41 U.S.C. § 609(a)(1), (3) (2000). The CDA requires that “[t]he contracting officer shall issue his decisions in writing, and shall mail or otherwise furnish a copy of the decision to the contractor.” § 605(a). The implementing regulations further require that the decision is to be provided to the contractor via “certified mail, return receipt requested, or by any other method that provides evidence of receipt.” 48 C.F.R. § 33.211(b) (2004) (emphasis added).

The Federal Circuit has interpreted receipt by the contractor to mean “actual physical receipt of that decision by the contractor [or his representative].” Borough of Alpine v. United States, 923 F.2d 170, 172 (Fed.Cir.1991) (quoting Pathman Constr. v. United States, 817 F.2d 1573, 1577 (Fed.Cir.1987)). “[Objective indicia of receipt by the contractor” must be shown to establish the date of proper delivery of the decision by the contracting officer. See Borough of Alpine, 923 F.2d at 172. This court has found that “[b]y linking the limitations period to receipt by the contractor, the CDA eliminates disputes about the time of actual notice, fault and misaddressing a letter, or the internal mail procedures of various contractors.” Id. at 172.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

The Sithe Group, LLC, dba TSG Industries
Armed Services Board of Contract Appeals, 2024
MVP Network Consulting, LLC
Armed Services Board of Contract Appeals, 2023
MECTS Services Joint Venture
Armed Services Board of Contract Appeals, 2023
Cheung v. United States
Federal Claims, 2019
Rohulhameed Construction Company
Armed Services Board of Contract Appeals, 2019
Phoenix Hawk Construction Company
Armed Services Board of Contract Appeals, 2019
Menendez v. United States
Federal Claims, 2018
Lucier v. United States
Federal Claims, 2018
Name Redacted
Armed Services Board of Contract Appeals, 2017
Black Bear Construction Company
Armed Services Board of Contract Appeals, 2017
Baley v. United States
134 Fed. Cl. 619 (Federal Claims, 2017)
Horton Construction Co., Inc.
Armed Services Board of Contract Appeals, 2017
Gazpromneft-Aero Kyrgyzstan LLC v. United States
132 Fed. Cl. 202 (Federal Claims, 2017)
James v. United States
130 Fed. Cl. 707 (Federal Claims, 2017)
Phipps v. United States
126 Fed. Cl. 674 (Federal Claims, 2016)

Cite This Page — Counsel Stack

Bluebook (online)
408 F.3d 1369, 2005 U.S. App. LEXIS 8817, 2005 WL 1163017, Counsel Stack Legal Research, https://law.counselstack.com/opinion/riley-ephriam-construction-co-v-united-states-cafc-2005.