Riley & Ephriam Construction Co. v. United States

61 Fed. Cl. 405, 2004 U.S. Claims LEXIS 181, 2004 WL 1708960
CourtUnited States Court of Federal Claims
DecidedJuly 29, 2004
DocketNo. 03-177C
StatusPublished
Cited by1 cases

This text of 61 Fed. Cl. 405 (Riley & Ephriam Construction Co. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Federal Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Riley & Ephriam Construction Co. v. United States, 61 Fed. Cl. 405, 2004 U.S. Claims LEXIS 181, 2004 WL 1708960 (uscfc 2004).

Opinion

OPINION

BASKIR, Judge.

We hereby GRANT Defendant’s Motion for Summary Judgment and dismiss Plaintiffs Complaint. We find that Plaintiff received the contracting officer’s (CO) final decision via fax on November 27, 2001, and via certified letter to its Post Office (PO) box on November 30, 2001. Plaintiffs instant action, filed in January of 2003, is thus time-barred by the Contract Dispute Act’s (CDA) 12-month statute of limitations.

BACKGROUND

As demonstrated by the parties’ briefs and confirmed by counsel during oral argument, the facts giving rise to this jurisdictional issue are undisputed. On November 17, 1998, Plaintiff Riley & Ephriam Construction Company (R & E) entered into a contract with the Government to “ ‘demolish and dispose of an existing nominal six inch thick concrete slab and replace with new eon[407]*407erete.” Pl. Opp. 2. During the demolition, Plaintiff discovered that the concrete slab in question did not contain the steel bars necessary to complete the project, as had been anticipated. As a result of the change in the work required, and the parties’ failure to agree on a price for these modifications, Plaintiff applied for an equitable adjustment to the contract on March 8, 2000, seeking $294,097.

During the fall of 2001, Plaintiff closed its corporate offices and began to handle operations from a home located in Stone Mountain, Georgia 30083. Plaintiff claims this move was “due in large part to the extreme financial hardship imposed by the government’s failure to resolve [its] claim.” Pl. Opp. 3. Although as a result of this move Plaintiff started to receive business-related mail at the Springleaf Court home address, it maintained its business address at a PO box in Stone Mountain, Georgia 30083.

On November 27, 2001, the CO issued a final decision denying Plaintiffs equitable adjustment. He sent this decision via certified mail to the address Plaintiff had provided as its business address when it submitted its claim-the PO box address. The decision arrived at the United States Post Office where the box was located on November 30, 2001. The letter was accepted, and pursuant to Post Office policy regarding the receipt of certified mail in corporate PO boxes, a notice stating that the letter had arrived was placed in Plaintiffs PO box. Alexander Aff. 1. At this point, the Post Office considered the letter “received by the boxholder [and] available for pickup.” Id.

On December 19, 2001, the Post Office placed a second notice in Plaintiffs box informing it of the letter’s availability for pick up. Although Plaintiff was able to pick up the CO’s final decision at any time during a 29-day period, it failed to do so, and consequently, the Post Office returned the package to the CO on December 29,2001.

In addition to the certified letter, the CO faxed a copy of this decision to Plaintiffs legal representative on November 27, 2001. The fax was sent to the attention of Steven Smith, the attorney “through whom communications to R & E had previously gone,” and it contained a cover letter indicating, “[t]he original document was forwarded to Riley & Ephriam via certified mail on 27 November 2001. ” Def. Mot. Summ. J. 6, Attach. A.

We asked counsel for the Plaintiff to provide information explaining the internal procedures for receiving official correspondence via fax at his firm. According to him, “all incoming faxes arrive at a central fax machine and are supposed to be delivered to the intended recipient.” Pl. Op. Ex. B. However, the Federal Circuit has held that “[b]y linking the limitations period to receipt by the contractor, the CDA eliminates disputes about ... the internal mail procedures of various contractors.” Borough of Alpine v. United States, 923 F.2d 170, 172 (Fed.Cir.1991). This holding applies to the internal mail procedures of a contractor’s representatives as well. As a result, although we will take into consideration the policies regarding fax delivery at counsel’s firm, insofar as these policies are relevant, we will focus our inquiry on the date of receipt, and not on mail handling procedures.

Although there is no fax confirmation sheet, we are satisfied with the CO’s undisputed declarations that he sent the fax and that the fax machine indicated a successful transmission, as well as with the copy of the fax cover sheet submitted to the Court. By the same token, Plaintiffs attorney states he never personally received the fax. For purposes of this motion, we will credit counsel’s assertion that he had no knowledge of the fax and that he did not personally receive it.

Ultimately, after the fax failed to come to the attention of Plaintiffs counsel and Plaintiff failed to pick up the certified letter sent to its PO box, the CO once more sent his decision via certified mail on January 30, 2002. The letter was sent to counsel, who accepted it and signed the return receipt.

On January 24, 2003, Plaintiff brought suit seeking $306,039.33 in damages, within 12 months of the January 30, 2002, delivery to counsel, but more than 12 months after the earlier apparent deliveries of November 2001.

[408]*408 DISCUSSION

To resolve this matter, we must determine what constitutes “receipt” under the CDA, and whether either the November 27, 2001, fax or the November 30, 2001, certified letter delivery constitutes legal receipt. Because we conclude that both the fax and the letter resulted in receipt pursuant to the CDA, we find Plaintiffs instant suit, filed in January of 2003, to be time-barred.

A. Standard for Resolving a Factual Challenge to Jurisdiction on Summary Judgment

Our inquiry into the facts surrounding the timeliness of Plaintiffs claim is necessary to determine whether Plaintiff is entitled to have this Court exercise its jurisdiction over contract disputes. See 41 U.S.C. § 609(a)(1); See also Borough of Alpine, 923 F.2d at 171 n. 1 (“[F]ailure to file a timely appeal [means a Plaintiff is] not entitled to have the Claims Court exercise its subject matter jurisdiction”). Technically speaking, we understand this to mean that the Court is the correct forum to consider this subject matter, but that a Plaintiff who fails to meet the CDA’s timeliness requirements has not stated a claim upon which relief can be granted pursuant to RCFC 12(b)(6).

As a formal matter, the Plaintiff has the burden of establishing the Court’s jurisdiction. Cedars-Sinai Med. Ctr. v. Watkins, 11 F.3d 1573, 1583 (Fed.Cir.1993). But in this case, the Government is alleging an earlier date of receipt and thus “[t]he Government must bear the burden of proving when the contractor actually received the final decision.” John Cibinic, Jr. & Ralph C. Nash, Jr., Administration of Government Contracts 1308 (3rd ed.1995).

Finally, this Court will grant a motion for summary judgment where there are no genuine issues of material fact in dispute and the moving party is entitled to judgment as a matter of law. RCFC 56(c).

B. Applicable Law

The CDA states, in part:

“[A] contractor may bring an action directly on the claim in the United States Claims Court [United States Court of Federal Claims].... [This] action ...

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Riley & Ephriam Construction Co. v. United States
408 F.3d 1369 (Federal Circuit, 2005)

Cite This Page — Counsel Stack

Bluebook (online)
61 Fed. Cl. 405, 2004 U.S. Claims LEXIS 181, 2004 WL 1708960, Counsel Stack Legal Research, https://law.counselstack.com/opinion/riley-ephriam-construction-co-v-united-states-uscfc-2004.