Rohulhameed Construction Company

CourtArmed Services Board of Contract Appeals
DecidedApril 4, 2019
DocketASBCA No. 61359
StatusPublished

This text of Rohulhameed Construction Company (Rohulhameed Construction Company) is published on Counsel Stack Legal Research, covering Armed Services Board of Contract Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Rohulhameed Construction Company, (asbca 2019).

Opinion

ARMED SERVICES BOARD OF CONTRACT APPEALS

Appeal of -- ) ) Rohulhameed Construction Company ) ASBCA No. 61359 ) Under Contract No. W91B4M-09-C-7104 )

APPEARANCE FOR THE APPELLANT: Mr. Rohul A. Afzaly President

APPEARANCES FOR THE GOVERNMENT: Raymond M. Saunders, Esq. Army Chief Trial Attorney CPT Jeremy D. Burkhart, JA Trial Attorney

OPINION BY ADMINISTRATIVE JUDGE HARTMAN ON THE GOVERNMENT'S MOTION TO DISMISS

The government moves to dismiss this appeal for lack of jurisdiction upon the ground it is untimely because it was filed more than 90 days after the contracting officer (CO) emailed her final decision to an attorney who had been assisting appellant, a construction company located in Afghanistan. Appellant opposes the government's motion.

STATEMENT OF FACTS FOR PURPOSES OF THE MOTION

On March 23, 2009, the Department of the Army awarded to appellant, Rohulhameed Construction Company (RCC), a contract, No. W91B4M-09-C-7104, in the sum of $414,160.00 for the construction of earth berms and guntruck ramps in Helmand, Zabul, and Kandahar provinces in Afghanistan, contract line item numbers (CLINs) 1, 2, and 3, respectively, each in the amount of $135,720 (R4, tab 1). CLIN 4 was workers compensation insurance or security as required by the Defense Base Act, 42 U.S.C. §§ 1651-54 (DBA), with estimated funding of$7,000.

The contract stated the delivery date in each province was "21 d[ a]ys after date ofNTP" and the contractor shall "complete the entire work ready for use not later than 63 calendar days after the date the Contractor receives the notice to proceed" (NTP) (R4, tab 1 at 8-9). The contract incorporated by reference Federal Acquisition Regulation (FAR) 52.233-1, DISPUTES (JUL 2002); and FAR 52.249-2, TERMINATION FOR THE CONVENIENCE OF THE GOVERNMENT (FIXED-PRICE) (MAY 2004) - ALTERNATE I (SEP 1996) (id. at 19). On April 29, 2009, RCC received from the Army CO its NTP with contract work ""effective 30 Apr 2009" stating that it was to complete the entire contract work in 63 calendar days or by "2 Jul 2009" (R4, tab 5). RCC furnished the Army on June 24, 2009, an invoice dated June 8, 2009, in the amount of $135,720 for work it had performed in Helmand province (Tarin Kowt ANA Base) and received payment from the Army (R4, tabs 5, 7-8, 10). RCC furnished the Army on November 9, 2009, a second invoice dated October 11, 2009, in the amount of $135,720 for work it had performed in Zabul province, which was sent to the Army's finance office for payment on November 12, 2009, and paid by the Army (R4, tabs 11-13, 19).

According to RCC, prior to April 15, 2010, it completed all work with respect to CLIN 3. By memorandum dated April 15, 2010, the Army CO stated that ··[e]ffective 15 April 2010 you are notified that contract number W9 l B4M-09-C-7104 ... is terminated in its entirety for the government's convenience under clause 52.249-2 ALT l ." The CO added ''[t]he Contractor is hereby informed that this termination is a no-cost settlement and that the Contractor waives any and all charges against the Government because of the termination of this contract and releases it from all obligations under this contract or due to its termination." (R4, tab 14)

In a final decision dated four days later, April 19, 2010, the CO stated:

In the matter of the Termination for the Convenience of the Government of contract number W9 l B4M-09-C-7104, it is the final decision of the Contracting Officer to terminate this contract unilaterally and deobligate all remaining funds from the contract except for the DBA insurance amount. This action is taken as a result of the contractor's failure to sign or acknowledge the Notice of Termination effective on 15 April 2010.

The CO noted RCC could appeal his final decision to the Joint Contracting Command- Iraq/Afghanistan's Deputy Principal Assistant Responsible for Contracting- Afghanistan/Competition Advocate at Bagram Air Base, Afghanistan or to the Armed Services Board of Contract Appeals (ASBCA). The CO added "[i]nstead of appealing to the agency board of contract appeals, [RCC] may bring an action directly in the United States Court of Federal Appeals within 12 months of the date you receive this decision." (R4, tab 15) On the same date, April 19, 2010, the CO issued a "unilateral" contract modification, No. P00002, purporting "to reflect a no-cost settlement agreement with respect to the Notice of Termination dated 15 April 2010," which stated as follows:

The Contractor unconditionally waives any charges against the Government because of the termination of the contract and releases it from all obligations under the contract or

I due to its termination. The Government agrees that all obligations under the contract are concluded WITH THE EXCEPTION OF THE OUTSTANDING DBA INSURANCE CHARGE.

(R4,tabl6)

The Army has not presented any evidence in this appeal of the means by which it transmitted the CO's final decision to RCC or, more importantly, the date on which RCC received the CO's final decision terminating the contract.

Nearly four years later, by email dated March 12, 2014, an Army contract specialist based at Rock Island, Illinois, sent an email to three different addresses at Gmail, Yahoo and Hotmail advising that he was "closing out" RCC's contract and he needed confirmation there were no outstanding claims, disputes or other contractual issues (R4, tab 17). By email dated June 9, 2014, RCC notified the contract specialist it had received payments for CLINs 1 and 2, but CLIN 3 "[ c ]onstr1:1ction at Kandahar Province $135,720.00 is yet to be paid." The contract specialist responded by email stating he could help RCC with ·'the DBA insurance only'' (CLIN 4) and appended a copy of the contract "modification" that terminated the contract. (R4, tab 20)

On October 25, 2016, Walt Pennington, an American attorney retained by RCC, sent a certified claim for $135,720 for CLIN 3 to an unspecified office at ''the Pentagon." In response to his claim submission, he received a telephone call from an Army official advising him that Celeste Hobert was the CO responsible for RCC's contract. (R4, tab 21 at 1) On December 1, 2016, attorney Pennington sent CO Hobert, a copy of RCC 's certified claim indicating RCC completed its work before its contract was terminated for convenience (id.). An affidavit by RCC's business operations manager attached to the claim stated: RCC told the CO that all work was complete, asked the CO to review and approve its completed work in order for it to send its final invoice, and the CO did not perform the requested review. The business manager added that: the CO instead terminated the contract; RCC never agreed to a no-cost settlement with the CO; and RCC never signed the Army's notice of convenience termination. The business manager stated in this affidavit he expressly authorized the CO or COR "and any person assigned to dispute resolution for this claim to discuss RCC's claim with RCC's attorney, Walt Pennington," but did not authorize or request the CO' s final decision be sent or transmitted only to attorney Pennington, rather than RCC. (Id. at 4-5)

On February 1, 201 7, after receiving no response from CO Hobert regarding the claim submitted, attorney Pennington filed a petition with the ASBCA to direct the CO to issue a decision pursuant to ASBCA Rule l(a)(5) (R4, tab 22 at 1-5). Two days later, on February 3, 2017, the Board issued an order stating the government shall, within 21 days of the date of the order, show cause why an order directing the CO to

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Riley & Ephriam Construction Co. v. United States
408 F.3d 1369 (Federal Circuit, 2005)
Cosmic Construction Co. v. The United States
697 F.2d 1389 (Federal Circuit, 1982)
The Borough of Alpine v. The United States
923 F.2d 170 (Federal Circuit, 1991)

Cite This Page — Counsel Stack

Bluebook (online)
Rohulhameed Construction Company, Counsel Stack Legal Research, https://law.counselstack.com/opinion/rohulhameed-construction-company-asbca-2019.