Thomas Creek Lumber and Log Co. v. United States

CourtUnited States Court of Federal Claims
DecidedFebruary 17, 2023
Docket19-1742
StatusUnpublished

This text of Thomas Creek Lumber and Log Co. v. United States (Thomas Creek Lumber and Log Co. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Federal Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Thomas Creek Lumber and Log Co. v. United States, (uscfc 2023).

Opinion

In the United States Court of Federal Claims No. 19-1742C Filed: February 17, 2023 NOT FOR PUBLICATION*

THOMAS CREEK LUMBER AND LOG CO.,

Plaintiff,

v.

UNITED STATES,

Defendant.

Darren Brent Carpenter, Jordan Ramis PC, Lake Oswego, OR, for the plaintiff, with Joseph A. Yazbeck, Jr., of counsel.

Ebonie I. Branch, Commercial Litigation Branch, Civil Division, U.S. Department of Justice, Washington, DC, for the defendant, with Benjamin R. Hartman, U.S. Department of Agriculture, of counsel.

MEMORANDUM OPINION

HERTLING, Judge

In this dispute arising out of a timber contract between the plaintiff, Thomas Creek Lumber and Log Co. (“Thomas Creek”), and the U.S. Forest Service, the parties have filed cross- motions for summary judgment on issues relating to the plaintiff’s breach -of-contract and breach-of-warranty claims.

Although the Court makes no findings of fact at this stage of the litigation, it appears that the Forest Service estimated in the prospectus for the timber sale that reconstruction of the roads necessary to access the timber subject to the contract would cost $98,776.50. The plaintiff argues that it paid the Forest Service $18,900 to calculate the road-reconstruction cost. Thomas Creek paid its sub-contractor more than $210,000 to build the roads. The plaintiff now claims

* A version of this opinion was delivered on the record at the conclusion of oral argument held on February 16, 2023, and an appropriate order in accordance with this memorandum opinion was thereafter entered. (ECF 66.) that the Forest Service owes it the difference between the Forest Service’s erroneous estimate and the actual cost of reconstructing the roads—or $114,148.82.

The plaintiff moves for partial summary judgment on the grounds that Thomas Creek was entitled to rely on the Forest Service’s road-reconstruction estimate in the prospectus and that Thomas Creek is entitled to recover the difference between the estimated cost and actual cost of road reconstruction. (ECF 54.) The defendant moves for summary judgment asserting it did not guarantee its estimate for the costs of reconstructing the roads and, in any event, its estimate was reasonable and did not breach any duty to the plaintiff. (ECF 56.)

The defendant’s motion for summary judgment is granted as to the plaintiff’s breach-of- warranty claim but denied as to the plaintiff’s breach-of-contract claim. The plaintiff’s motion for summary judgment is denied.

I. DISCUSSION

Under Rule 56(a) of the Rules of the Court of Federal Claims (“RCFC”), a “court shall grant summary judgment if the movant shows that there is no genuine dispute as to any material fact and the movant is entitled to judgment as a matter of law.”

The plaintiff’s complaint alleges two claims for relief: breach of warranty and breach of contract.

A. Breach of Warranty

In Oman-Fischbach Int’l (JV) v. Pirie, the Federal Circuit defined a warranty as “‘an assurance by one party to an agreement of the existence of a fact upon which the other p arty may rely; it is intended precisely to relieve the promisee of any duty to ascertain the facts for himself.’” 276 F.3d 1380, 1383-84 (Fed. Cir. 2002) (quoting Dale Constr. Co. v. United States, 168 Ct. Cl. 692, 699 (1964)).

The Federal Circuit articulated in Oman-Fischbach a three-part test to determine whether a breach of warranty has occurred. First, the defendant must have assured the plaintiff of the existence of a fact. Second, the defendant must have intended that the plaintiff be relieved of the duty to ascertain the existence of that fact for itself. Third, the fact must have proved untrue. Contractual language disclaiming responsibility for the veracity of a fact may defeat a breach-of- warranty claim. See id.

In this case, the plaintiff argues that the road-reconstruction estimate in the prospectus contained an implied warranty of reasonable accuracy. The defendant argues that any such warranty was disclaimed in the prospectus and the bid form.

There is no genuine dispute of material fact concerning the plain language of the prospectus and bid form. Two provisions of the prospectus and bid form are relevant: paragraph 8 of the prospectus, (ECF 55-5; ECF 56-4), and paragraph 23 of the bid form, (ECF 55-6; ECF 56-5).

2 Paragraph 8 of the prospectus provides, in all capital letters: “CONSTRUCTION ESTIMATES AND INFORMATION CONTAINED HEREIN, TOGETHER WITH RELATED SPECIFICATIONS, ARE NOT GUARANTEED.” (ECF 55-5 at 3.)

Paragraph 23 of the bid form provides that “[b]efore submitting this bid , the Bidder is advised and cautioned to inspect the sale area, . . . and take other steps as may be reasonably necessary to ascertain . . . the construction estimates . . . . Failure to do so will not relieve the Bidder from responsibility for completing the contract.” (ECF 55-6 at 4.)

The bid form also required Thomas Creek to warrant that the bid was “submitted solely on the basis of its examination and inspection” of the timber and “its costs of recovery, without any reliance on Forest Service estimates of . . . costs of recovery.” Thomas Creek agreed to hold “the Forest Service harmless for any error, mistake, or negligence regarding estimates except as expressly warranted against in the sample contract.” (Id.)

The Court assumes, for the sake of argument, that the Forest Service assured the plaintiff of the fact that the road could be constructed for $98,776.50, and that the first prong of the test in Oman-Fischbach is met.

Even assuming the first prong is met, the plaintiff cannot prevail on the second prong of the test in Oman-Fischbach. That prong requires the plaintiff to show that the Forest Service intended Thomas Creek to rely on its road-reconstruction estimate. The language of the prospectus and bid form evinces the opposite: the Forest Service emphasized that Thomas Creek should not rely on the road-reconstruction estimate and should instead perform its own site inspection.

The plaintiff thus cannot prevail on its breach-of-warranty claim, and that claim must be dismissed.

B. Breach of Contract

The Federal Circuit has set forth a four-part test for a party to recover for a breach of contract. Oliva v. United States, 961 F.3d 1359, 1362 (Fed. Cir. 2020). First, there must be a valid contract between the parties. Second, there must be an obligation or duty arising out of that contract. Third, there must be a breach of that duty. Fourth, the breach must have caused damages to the non-breaching party.

As to the first element of the test, the parties have not put the full contract in evidence on their motions for summary judgment. Accordingly, the existence of a valid contract cannot be determined at this stage of the litigation. Nonetheless, neither party has disputed the existence of some sort of agreement between the parties. It appears that both parties behaved as if some contract, quasi-contract, or contract implied-in-fact existed. For the purposes of these cross- motions, the first element of the test articulated in Oliva is assumed to have been met. 961 F.3d at 1362.

The second element of the test, however, is at the heart of the dispute between the parties. The parties disagree on whether the Forest Service had a duty to estimate the costs of road 3 reconstruction with reasonable accuracy. If such an obligation existed, the parties’ positions also diverge as to whether the Forest Service breached that obligation by providing a grossly erroneous estimate and whether that breach caused the plaintiff damages.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
Thomas Creek Lumber and Log Co. v. United States, Counsel Stack Legal Research, https://law.counselstack.com/opinion/thomas-creek-lumber-and-log-co-v-united-states-uscfc-2023.