Troise v. United States

36 Cont. Cas. Fed. 75,904, 21 Cl. Ct. 48, 1990 U.S. Claims LEXIS 270, 1990 WL 98767
CourtUnited States Court of Claims
DecidedJuly 17, 1990
DocketNo. 245-88C
StatusPublished
Cited by9 cases

This text of 36 Cont. Cas. Fed. 75,904 (Troise v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Troise v. United States, 36 Cont. Cas. Fed. 75,904, 21 Cl. Ct. 48, 1990 U.S. Claims LEXIS 270, 1990 WL 98767 (cc 1990).

Opinion

OPINION

NETTESHEIM, Judge.

This case is before the court after argument on defendant’s motion for summary judgment and plaintiff’s cross-motion for partial summary judgment. Of the many issues raised by the cross-motions, the principal issue that can be resolved is whether the Government’s assessment of liquidated damages against plaintiff after plaintiff failed to complete contract performance on schedule is void as a penalty despite the Government’s correcting the method of calculation before assessment.

FACTS

The following material facts are undisputed, unless otherwise noted. On September 20, 1982, the United States Department of the Air Force (the “Air Force”), Dover, Delaware, awarded Contract No. F0760382-C0046 (“contract 0046”) in the amount of $2,359,000.00 to Edward J. Troise, Sr., and E.J.T. Construction Management Corporation, a Joint Venture (“plaintiff”). The contract pertained to Phase III of a four-phase renovation project at Dover Air Force Base (“Dover”). As described in the Invitation for Bids, Phase III work constituted renovating ten blocks of housing units, each block containing 19 to 26 individual housing units. Plaintiff previously performed Phase II contract work for the same renovation project at Dover. Plain[52]*52tiff was low bidder on the contract by $259,000.00 and offered a bid that was $1,515,049.00 lower than the Air Force’s estimate.

Contract 0046 required plaintiff to perform major renovation work in the housing units, encompassing, but not limited to, installation of kitchen cabinets, heating, ventilation, and air conditioning equipment, and bathroom vanities; wall and ceiling repairs; and installation of exterior privacy wood fencing. The period for contract performance was 450 days, which commenced within ten calendar days after issuance of the Notice to Proceed on November 4, 1982, and ended on or about January 29, 1984. Plaintiff provided the Air Force with a contract performance schedule estimating a 417-day calendar performance period ending on approximately December 29, 1983. The contract provided for a 90-cal-endar day period to complete each of Blocks One and Two and 60 calendar days to complete each successive block.

On August 4,1982, prior to the receipt of bids, the Air Force amended certain specifications contained in the Invitation for Bids. The amendments later were incorporated by reference into contract 0046. One amended specification altered the contract’s liquidated damages clause. Under the amendment the charge for each day of delay was increased from $64.74 to $223.94, with the notation that “[liquidated damages shall be assessed by unit.” Also amended was the specification concerning Phase III kitchen cabinets. The preamendment language read, in pertinent part: “At the contractor’s option, cabinets shall be constructed as specified hereinafter and shall conform to ANSI A161.1____” 1 On August 4, 1982, the language was altered by deleting “At the contractor’s option” from the wording.

1. Kitchen cabinet claim

In bidding the contract, plaintiff assumed that it would be able to use the same cabinets that it supplied under the Phase II contract. At the Phase III pre-performance conference, plaintiff’s representative did not question the revised specifications. On December 23, 1982, plaintiff submitted to the Air Force a cabinet manufactured by Boro Woods Products Co., Inc. (“Boro”). The Air Force disapproved that cabinet on January 18, 1983, on the grounds that the “Classic” cabinet was not constructed from materials outlined in the Phase III specifications. As the notes to the contractor on the submittal form state with respect to submittal number 9:

Item # 1:

a. Drawer sides and backs shall be lh" hardboard as specified.
b. Drawer fronts and doors shall be hardwood as specified.
c. Hardwood blocks shall be used in lieu of plastic corner blocks.
d. Door hardware shall be magnetic type catches as specified.

Item #8:

a. Bottom of cabinet shall be braced with hardwood blocks.
b. Sample of wall cabinets not submitted as required.
c. Request drawer fronts be nailed to sides of drawers.

Plaintiff’s expert in woodworking and furniture design, Paul E. Rumbaugh, finds the notations on the Material Submittals “inept and confusing.” In his affidavit, he states:

Item 1(a) states “Drawer sides and backs shall be lk inch hardboard as specified”. The specs actually require “lh inch hardwood ”! Item 1(b) states “Drawer fronts and doors shall be hardwood as specified”. The specs actually require doors to be “hardwood plywood”! Item 1(c) Plastic corner blocks are a totally satisfactory substitute for wood comer blocks and are used extensively. Item 1(d) Spring loaded, self-closing hinges as used on the sample improve quality compared to regular hinges and troublesome magnetic catches.
[53]*53(2) Item 8(a) “Bottom of the cabinet shall be braced with hardwood blocks”. Hardwood blocks do brace the bottom of the cabinet. Item 8(c) “Request drawer fronts to be nailed to sides of drawers”. “Nailing” in cabinet construction is a very poor method of joinery, it is not recommended and is rarely if ever used.

Affidavit of Paul E. Rumbaugh, Mar. 5, 1990, 118 (emphasis in original). Mr. Rumbaugh does concede, however, that there were two valid bases for rejecting submittal number 9. First, the sides of the drawer should have been constructed of either V2-inch hardwood or 5-ply hardwood plywood. Rumbaugh Aff. 118b. Second, while the specifications did not require that the painted backs of the cabinet doors, drawers, and edges be covered in plastic, had these items been so covered, the Classic cabinet would have been equal to submittal number 63. Submittal number 63 was listed on the “Material Approval Submittal” as satisfactory. Id.

Defendant asserts that on March 23, 1983, a Boro representative discussed the cabinet submissions with Contracting Officer Thelma 0. Gabrielson. According to Air Force phone logs, “Lou from Boro Wood” claimed that he had told “Eddie Troise,” prior to bid submission, that Boro did not make a cabinet that would comply with Phase III specifications. The phone logs appear to be inadmissible hearsay and are not considered in ruling on defendant’s motion. Defendant can attempt to introduce them at trial under the business records exception to the hearsay rule. Fed.R.Evid. 803(6).

Contracting Officer Gabrielson, by letter dated April 7, 1983, informed plaintiff that Haas Cabinet Company (“Haas”) was able to produce a cabinet line that met Phase III requirements. Through submission No. 63, plaintiff submitted a cabinet manufactured by Haas. Master Sergeant Leland M. Webb rejected the submittal on the grounds that “[pjarticle board sides and shelves are not an approved equal to the material specified____” Plaintiff, through its expert Mr. Rumbaugh, challenges the propriety of the Air Force’s disapproval of the Haas cabinet. Mr. Rumbaugh concludes that the Haas cabinet, for normal use, is equivalent to the cabinet specifications. Mrs. Gabrielson appears to share the same view.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

PHT Supply Corp. v. United States
71 Fed. Cl. 1 (Federal Claims, 2006)
Abcon Associates, Inc. v. United States
49 Fed. Cl. 678 (Federal Claims, 2001)
Miller Elevator Co. v. United States
39 Cont. Cas. Fed. 76,635 (Federal Claims, 1994)
Gresham, Smith & Partners v. United States
37 Cont. Cas. Fed. 76,247 (Court of Claims, 1991)
Reed v. United States
23 Cl. Ct. 517 (Court of Claims, 1991)
Dufau v. United States
22 Cl. Ct. 156 (Court of Claims, 1990)
Riggs v. United States
21 Cl. Ct. 664 (Court of Claims, 1990)
Essen Mall Properties v. United States
36 Cont. Cas. Fed. 75,942 (Court of Claims, 1990)

Cite This Page — Counsel Stack

Bluebook (online)
36 Cont. Cas. Fed. 75,904, 21 Cl. Ct. 48, 1990 U.S. Claims LEXIS 270, 1990 WL 98767, Counsel Stack Legal Research, https://law.counselstack.com/opinion/troise-v-united-states-cc-1990.