H. L. Yoh Co., Inc. v. United States

288 F.2d 493, 153 Ct. Cl. 104, 1961 U.S. Ct. Cl. LEXIS 76
CourtUnited States Court of Claims
DecidedApril 7, 1961
Docket435-55
StatusPublished
Cited by8 cases

This text of 288 F.2d 493 (H. L. Yoh Co., Inc. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
H. L. Yoh Co., Inc. v. United States, 288 F.2d 493, 153 Ct. Cl. 104, 1961 U.S. Ct. Cl. LEXIS 76 (cc 1961).

Opinion

LARAMORE, Judge.

Plaintiff sues to recover the difference in dollars between the overhead rate as fixed in a “time and material” contract and the overhead rate actually encountered during performance thereof.

On June 15, 1952, plaintiff and defendant entered into a time and material contract for the changing and conversion of drawings and parts lists maintained by defendant at its Detroit Arsenal on automotive equipment. A time and material contract was entered into because the number of drawings and parts lists involved were not ascertained, nor could an accurate estimate be made except at a prohibitive cost.

At the time the contract was negotiated and signed, it was contemplated by the defendant that the project would be one of total conversion which would include all drawings and parts lists at the Detroit Arsenal relating to automotive equipment. After the work had been in progress for several months it became evident that many of the drawings were obsolete. It was thereupon determined that such drawings would be eliminated. Accordingly, by letter dated March 17, 1953, the contracting officer issued a directive changing the program from a policy of total conversion to one of selective conversion. This necessarily created a reduction in volume.

The contract provided for a maximum of $5,000,000 to be expended on the project. However, the total amount actually expended was $3,371,980.43. It is as a result of this curtailed expenditure that the plaintiff alleges his overhead expenses were proportionately increased. On March 15, 1954, plaintiff presented a claim for an adjustment in the overhead percentage fixed in the contract. This request was denied by the contracting officer in a letter dated March 31,1954.

On April 27, 1954, plaintiff appealed to the Secretary of the Army from the decision of the contracting officer. This appeal was denied by the Armed Services Board of Contract Appeals by decision dated July 21, 1955.

On November 23, 1955, plaintiff filed its petition in this court and the case was referred to a trial commissioner. By agreement of the parties, and with the approval of the commissioner, the trial was limited to the issues of law and fact relating to the right of the plaintiff to recover.

When a contractor enters into a time and materials contract he agrees to furnish the labor and equipment necessary to fulfill his obligations at a prescribed rate. The rate to be charged for direct labor can be precisely predetermined at an hourly rate or any acceptable measurement. However, the rate for nonproduction personnel such as owners, officers, clerical workers, salesmen, and others must of necessity be estimated. This rate is referred to as overhead or burden rate. It is reasonable to assume that this rate is not merely conjecture but is determined by some intelligent process. Plaintiff alleges, and the commissioner so found, that in this in *495 stance the contractor relied on the volume of work anticipated in the project. The Arsenal personnel orally informed representatives of the plaintiff that it was expected to be a five million dollar program. The plaintiff estimated that up to that time in the year his burden rate was 32 percent. Based on the increased volume of work anticipated under the proposed contract, the plaintiff calculated that he could perform the work at a burden rate of 25.97 percent, and submitted his bid accordingly. It is apparent that in accepting a bid that included a lower burden rate, the defendant was placed in a better position than it would have been in had the contract provided for a burden rate of 32 percent. Defendant admits as much but contends that the plaintiff is bound by the terms of the written contract. Admittedly, defendant may not have accepted plaintiff’s bid had it contained a burden rate of 32 percent, but that is not the issue. The only issue to which this court addresses itself is whether the unilateral reduction in the volume of work under the terms of a partially executed contract creates liability in the party ordering the reduction if it results in increased costs to the other party. We are of the opinion that it does. This Court has previously held that the Government is liable for increased costs resulting from a change in volume from the estimated volume given to the contractor as a basis for computing its bid. In Fehlhaber Corporation v. United States, 1957, 151 F.Supp. 817, 825, 138 Ct.Cl. 571, 584, certiorari denied, 355 U.S. 877, 78 S.Ct. 141, 2 L.Ed.2d 108, we stated:

“ * * * Plaintiff had a right to rely on the Government’s specifications and drawings and the Govern-. ment is bound by any assertions made therein notwithstanding the fact that it was stated that that data would be for information only.”

Perhaps a case more factually similar to the instant case is Peter Kiewit Sons’ Company v. United States, 1947, 74 F.Supp. 165, 109 Ct.Cl. 517. In that case, plaintiffs were three contractors who entered into a contract for the grading of runways at an airfield. Tremendous amounts of fill were required for the grading. This fill was to be obtained from three areas in the following amounts: area one, 700,000 cubic yards; area two, 1,600,000 cubic yards, area three, 2,300,000 cubic yards. The plaintiffs prepared their estimate on that volume with a different price for each area. The prices computed by the plaintiffs were 31.392, 51.23, and 29.77 cents per cubic yard respectively. Plaintiffs were then advised that a composite bid for the three areas would have to be submitted. They then computed a weighted average and arrived at a price of 37.476 cents per cubic yard. It is readily apparent that the contractor stood to profit from areas one and three but would lose money on area two. While the work was in progress the Government notified plaintiffs that the amount of fill from area three would be reduced by 750,000 cubic yards. The plaintiffs complained that this would increase their unit costs and that an equitable adjustment should be made on the contract. * This court agreed. In other cases, Ruff v. United States, 1942, 96 Ct.Cl. 148; Virginia Engineering Co., Inc., v. United States, 1944, 101 Ct.Cl. 516; Loftis v. United States, 1948, 76 F.Supp. 816, 110 Ct.Cl. 551, to cite but a few, the court allowed recovery where there was a mistake either by the Government or by both. In the instant case there was no mistake. Instead, there was a unilateral reduction in volume by the defendant for its own purpose. The defendant clearly had the right to make this reduction under the terms of Section 2 of the standard Government supply contract (finding 28) but they are obliged to pay for increased costs occasioned by the change.

The defendant argues that the plaintiff may not recover because it has failed to prove that it sustained a loss. We find this argument devoid of merit. If a contractor bids on a contract intended to provide a million dollars in profit but because of some unilateral action on the part of the other party he, in fact, makes *496 a profit of 50 cents, can it be denied he was damaged even though clearly he realized a profit? It is in regard to this damage we direct the question of liability. There can be liability even though the contractor has actually realized some profit rather than an actual loss.

Defendant further contends that the plaintiff should be denied recovery for failure to exhaust his administrative remedies for two reasons.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
288 F.2d 493, 153 Ct. Cl. 104, 1961 U.S. Ct. Cl. LEXIS 76, Counsel Stack Legal Research, https://law.counselstack.com/opinion/h-l-yoh-co-inc-v-united-states-cc-1961.