Seaboard Surety Company v. Dale Construction Co., (Two Cases)

230 F.2d 625
CourtCourt of Appeals for the First Circuit
DecidedMarch 22, 1956
Docket19-1470
StatusPublished
Cited by5 cases

This text of 230 F.2d 625 (Seaboard Surety Company v. Dale Construction Co., (Two Cases)) is published on Counsel Stack Legal Research, covering Court of Appeals for the First Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Seaboard Surety Company v. Dale Construction Co., (Two Cases), 230 F.2d 625 (1st Cir. 1956).

Opinion

WOODBURY, Circuit Judge.

The plaintiff-appellant, Seaboard Surety Company, a New York corporation, brought suit in the court below under its diversity jurisdiction against Dale Construction Co., a Massachusetts corporation, and its two principal officers, both citizens of Massachusetts. The suit was for specific performance of two identical contracts of indemnity executed by Dale and its officers individually in consideration of the issuance by Seaboard of two performance and two payment bonds required by the terms of two separate contracts entered into by Dale with the United States for construction work on two government installations in the Boston area. The first contract, entered into on June 27, *626 1950, was for the replacement of a water main at the Boston Army Base. The second contract, entered into about a year later on June 15, 1951, was for the repair of the fire alarm and police signal systems at the South Boston Annex of the Boston Naval Shipyard. The defendants answered and Dale filed counterclaims to recover damages which it alleged it had sustained by reason of Seaboard’s wrongful assumption and completion of the work called for by the two contracts.

The District Court empanelled an advisory jury to hear the case but at the close of the evidence on January 28, 1955, it discharged the jury, denied the plaintiff’s motion for summary judgment, and, concluding for reasons to be stated presently that it lacked jurisdiction, it orally directed that the plaintiff’s complaint be dismissed and by parity of reasoning that both of the defendant Dale’s counterclaims also be dismissed. The court said in addition that Seaboard’s suit so far as the Naval Shipyard contract was concerned was premature. On January 31, 1955, the court filed findings of fact and conclusions of law embodying in more detail its conclusions expressed orally three days before, and the appellant then seasonably filed motions for a new trial and for amendment of the findings of fact and conclusions of law. These motions were denied on April 29, and on May 4 the court entered judgment dismissing the plaintiff’s complaint but making no mention of Dale’s counterclaims. The plaintiff thereupon promptly moved that the judgment be amended 1) to provide for dismissal of Dale’s counterclaim with respect to the Army Base contract, 2) to make similar disposition of the counterclaim with respect to the Naval Shipyard contract and 3) to provide for the entry of a judgment for the plaintiff in the amount of certain lien claims which it had paid as surety in accordance with the payment bond it had given on the Army Base contract. 1 The District Court by memorandum dated June 1, 1955, allowed this motion in part. It said that the counterclaim “relating to the Army Base contract may be dismissed, as the evidence was insufficient to show that Seaboard maliciously and wrongfully caused the contract breach.” It also dismissed Dale’s counterclaim relating to the Naval Shipyard contract, but did so without prejudice, no doubt because of its belief that the suit was premature insofar as that contract was concerned. It then concluded its memorandum with the statement: “I do not feel that the lien amendment should be allowed at this time. It think that it will be necessary to take evidence to show just what the liens pertained to. This can be done in the fall.” Thereupon the plaintiff on June 30, 1955, filed notice of appeal and its appeal came on for hearing in this court at our November session. In the meantime, however, the parties had agreed that Seaboard had paid and was entitled to recover lien claims under its payment bond issued in connection with the Army Base contract in the amount of $1,123.95, and on October 27 the District Court had handed down a memorandum to that effect.

At the argument on appeal counsel for the appellees orally suggested for the first time that this court lacked appellate jurisdiction. His position was that Seaboard’s appeal should be dismissed as untimely for the reason that its appeal was not taken within 30 days of May 4, 1955, when the judgment was entered dismissing its complaint. And he took the alternative position that Seaboard’s appeal should be dismissed as premature in view of the court’s action on June 1, 1955, postponing decision on Seaboard’s lien claims until evidence could be taken in the fall.

Taken by surprise by this line of argument, we directed counsel for the ap-pellees to file a written motion to dismiss the appeal, and a supporting memorandum, and gave counsel for the appellant an opportunity to file a memoran *627 dum in opposition. They complied in due course. But in the meantime on November 7, 1955, counsel for the appellant, in an attempt to clarify the situation, obtained a certificate from the District Court giving a resume of the proceedings and concluding as follows:

“In accordance with the request of the plaintiff under Rule 54(b) I determine that after the disposition of the plaintiff’s motion to amend the Judgment of Dismissal in accordance with my memorandum filed on June 1, 1955, there was no just reason for delay in seeking a review of the issues raised by the complaint relating to the Army Base contract, the supplemental complaint relating to the Navy contract and the two counterclaims of Dale Construction Co. The controversy as to the lien claims arose under a separate payment bond on the Army Base contract and was a wholly separable claim.”

In addition the court on the same day entered a formal judgment dismissing Dale’s counterclaim relating to the Army Base contract with prejudice and its counterclaim relating to the Naval Shipyard contract, again without prejudice, and also another formal judgment for the plaintiff in the stipulated amount of the lien claims ($1,123.95) which it had paid in connection with the Army Base contract, thereby completing final disposition of all claims in issue. Seaboard then as a precautionary measure took a second appeal and that appeal appears on our docket as No. 5064. Then, in this latter appeal, Seaboard moved that the filing of a statement of points, briefs, record appendices, and oral arguments be dispensed with, and that it be considered and disposed of on the papers and arguments of its earlier appeal numbered 5028.

We do not pause to consider the contention of counsel for the appellee that the 30-day period for appeal began to run against Seaboard on May 4, when judgment was entered dismissing its complaint, instead of on June 1 when that judgment was amended on timely motion. The reason for this is that in the absence of compliance with Rule 54 (b) there was no final judgment from which any appeal could be taken until the lien claims on the Army Base contract, decision on which was postponed on June 1 until fall, were finally disposed of by the judgment which was formally entered on November 7, after argument in this court.

The judgment of May 4 as amended on June 1 finally disposed of some of the claims for relief presented in the action, but it did not dispose of all of them. It postponed determination until fall of Seaboard’s claim for reimbursement for lien claims paid by it under the Army Base payment bond. Possibly under original Rule 54(b), Fed.Rules Civ.Proc. 28 U.S.C.A. this claim for reimbursement could be considered a claim arising out of a separate and distinct transaction with the result that the balance of the judgment was presently ap-pealable under the doctrine of Reeves v.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Payne v. American Contractors Indemnity Co. CA3
California Court of Appeal, 2016
Arntz Contracting Co. v. St. Paul Fire & Marine Insurance
47 Cal. App. 4th 464 (California Court of Appeal, 1996)
Olsen v. French
456 A.2d 869 (Supreme Judicial Court of Maine, 1983)
New Amsterdam Casualty Company v. Lundquist
198 N.W.2d 543 (Supreme Court of Minnesota, 1972)

Cite This Page — Counsel Stack

Bluebook (online)
230 F.2d 625, Counsel Stack Legal Research, https://law.counselstack.com/opinion/seaboard-surety-company-v-dale-construction-co-two-cases-ca1-1956.