Mundy v. United States

35 Ct. Cl. 265, 1900 U.S. Ct. Cl. LEXIS 174, 1900 WL 1451
CourtUnited States Court of Claims
DecidedMarch 12, 1900
DocketNo. 19397
StatusPublished
Cited by3 cases

This text of 35 Ct. Cl. 265 (Mundy v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Mundy v. United States, 35 Ct. Cl. 265, 1900 U.S. Ct. Cl. LEXIS 174, 1900 WL 1451 (cc 1900).

Opinion

WeldoN, J.,

delivered the opinion of the court:

On an amended petition, filed February 9, 1899, the claimants, James A. Mundy and Joseph Busch, prosecute this suit as surviving partners of William B. Johns, on a contract dated on the 23d day of April, 1891, made between the claimants, their deceased partner, and the defendants, for certain improvements of the harbor between Philadelphia, Pa., and Camden, N. J., as described in certain specifications attached thereto. The contract and specifications are annexed to and made a part of the petition as Exhibit A.

The general project of the work contemplated in the improvement is shown by the following extracts from the specifications:

“The work under these specifications contemplates the formation of a channel about 2,000 feet in width, with a cross section not far from 55,000 square feet at mean tide, along the Philadelphia shore from Kaighns Point to Fishers Point at a distance far enough from the present wharf line to permit the extension of the wharves and the widening of Delaware avenue at their shore ends.

“For this purpose it is proposed to remove Windmill and Smiths islands and the adjacent shoals, so as to form a 26-foot channel, about 1,000 feet wide, or wider if found practicable during the progress of the work, along the front of the revised Philadelphia wharf line from Kaighns Point to the foot of Pettys Island. It is further proposed to widen the Pennsylvania channel at Pettys Island, so as to give the Pennsylvania channel in this locality a width of about 2,000 feet, a depth of 26 feet over a width of about 1,000 feet, more or less, the channel sloping to a depth of 12 feet in the remaining width, and a resulting cross section of about 55,000 square feet.

“The material removed is in part to be deposited and spread on League Island and the balance is to be placed where it will not be an injury to the river.”

The contract, among other matters, provides that the claimants shall receive for said work, in accordance with the conditions of the agreement, the following prices, to wit:

“ (1) Ten and seven-eighths (10&) cents per cubic yard, measured in scows, for all material excavated, removed, and de[284]*284posited at places provided by the said James A. Mundy & Company and approved by the engineer officer in charge, for the entire improvement of Philadelphia Harbor as per plan approved by Congress.

“ (2) One dollar and ninety cents ($1.90) per linear foot for all pile and timber wharfing or revetment removed.

“ (8) Nine and one-half (9i) cents per cubic yard, measured in scows, for all dredged material deposited and spread upon League Island, this price to be in addition to the price per cubic yard paid under item (1).”

The amended petition is the pleading on which plaintiffs rely as a statement of their claim in the following sums, to wit:

Due for materials deposited at sea. $4,411.44

And for materials deposited on League Island. 17, 782.07

Retained percentages.-. 14,584.52

Withheld on revetment work. 1,031. 70

Withheld as inspection expenses. 5,191.16

43,000. 89

The contract is substantially a contract for dredging, and the principal contentions are as to how the work is to be measured, the extent of the agreement as to the amount of labor to be performed, and the right of the defendants to annul the contract.

The plaintiffs, by the allegations of the petition and by their contention upon the facts, claim that they diligently and faithfully performed the agreement, and that there is now due them the said sum; while the defendants insist that the plaintiffs did not faithfully perform their contract within the extensions of the same, that they failed and neglected to commence the work on time; failed and neglected to put on the work the necessaiy plant and machinery; that extensions were made from time to time in order to accommodate the plaintiffs and to insure the completion of the work; and that in consequence of such neglect and failure on the part of plaintiffs the defendants were compelled to annul the contract on the 23d day of December, 1892, and that by reason of such failure and annulment a large part of the work which the contract called for was left unperformed by plaintiffs; that in consequence of such failure the defendants were compelled to contract with other parties at a higher rate; that the contract required the plaintiffs to excavate and remove 18,000,000 cubic yards, and [285]*285they only excavated and deposited 775,161, leaving a difference of 17,724,839, which the defendants had to remove by and through other contractors at a higher rate of compensation, and that in consequence thereof the defendants were damaged in the sum of $572,725.90, being the difference between the contract price of plaintiffs and the price paid the new contractors.

One of the important contentions'in this proceeding is as to the scope of the agreement in the amount of work to be done. Is it a contract for the entire work contemplated by the general plan, or is it limited in its extent to what was substantially performed by the claimants?

In the view which the court has taken of the legal questions involved in this proceeding, it is not necessary to determine whether the obligation of the claimants as to the amount of work to be done is to the extent of the 18,000,000 cubic yards as provided in the general plan, or limited by the provisions of the specifications under the head of “commencement of the work,” in which the approximate amount of excavation in Windmill Island is stated, and which by the contention of the claimants limits the extent of the work to be performed.

If the claimants substantially failed to perform the amount . of labor of Windmill within the extended time, it is immaterial whether the contract contemplated the 18,000,000 cubic yards or only the approximate amount contained in Windmill Island. Having determined that the issues of the cause are not affected by the questions of the extent of the work contemplated by the agreement, we proceed to consider the rights of the parties on the other points of dispute.

As will be seen by the findings of fact, there was an extension of time from December 26, 1891, to June 30, 1892, and from June 30, 1892, to July 31, 1892, and then from July 31, 1892, to January 1, 1893. The engineer in charge of the wprk being dissatisfied with its progress, on the 23d day of December, 1892, by the authority of the Chief of Engineers, notified the claimants that the contract was annulled, and thereafter all work ceased.' A contention has arisen as to the right and propriety of the anulment of the contract under the circumstances.

Whatever may be said of the alleged default of the claim[286]*286ants in December, 1892, it is shown bj^ the findings that for some reason or other not appearing they were not able to perform the specified work within the limits of the original contract, nor within the three extensions, and about the 1st of December, 1892, the claimants having made application for a further extension, the proper authorities of the Department not only refused to extend the time, but, upon the contrary, annulled the contract, and thereby prevented the claimants from doing any further work.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Tecom, Inc. v. United States
66 Fed. Cl. 736 (Federal Claims, 2005)
Spearin v. United States
51 Ct. Cl. 155 (Court of Claims, 1916)
United States v. Weisberger
206 F. 641 (Ninth Circuit, 1913)

Cite This Page — Counsel Stack

Bluebook (online)
35 Ct. Cl. 265, 1900 U.S. Ct. Cl. LEXIS 174, 1900 WL 1451, Counsel Stack Legal Research, https://law.counselstack.com/opinion/mundy-v-united-states-cc-1900.