McDonnell Douglas Corp. v. United States

50 Fed. Cl. 311, 2001 U.S. Claims LEXIS 171, 2001 WL 1053368
CourtUnited States Court of Federal Claims
DecidedAugust 31, 2001
DocketNo. 91-1204C
StatusPublished
Cited by5 cases

This text of 50 Fed. Cl. 311 (McDonnell Douglas Corp. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Federal Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
McDonnell Douglas Corp. v. United States, 50 Fed. Cl. 311, 2001 U.S. Claims LEXIS 171, 2001 WL 1053368 (uscfc 2001).

Opinion

OPINION

HODGES, Judge.

The issue in this case now is whether the Navy’s unilateral modification establishing a new schedule for first flight was reasonable. The schedule was in place at termination, and it was specific. McDonnell Douglas Corp. v. United States, 182 F.3d 1319, 1332 (Fed.Cir.1999). If it was reasonable as well, the Circuit’s finding that the Government’s decision to terminate for default was performance-related will require us to rule for defendant.

The unilateral schedule was reasonable. A Contracting Officer acting with discretion rationally could have determined that the contractors would not have achieved first flight by December 1991. In consideration of these factors, we dismiss plaintiffs’ complaint and enter judgment for the Government.

I. BACKGROUND

The Navy introduced a program in 1984 to develop a carrier-based stealth aircraft known as the A-12. The A-12 was a full-scale engineering and development contract. McDonnell Douglas and General Dynamics contracted with the Navy in 1988 to produce eight A-12 aircraft.1 The Navy could purchase four production lots of aircraft. It exercised this option in May 1990. Each aircraft would test different characteristics of the A-12. The eighth aircraft would possess the stealth characteristics that would serve as the basis for the optional production lots. The contract schedule called for delivery of the first aircraft in June 1990; the remaining aircraft were to be delivered monthly through January 1991.

Plaintiffs experienced difficulties in performance of this contract from the beginning. Delivery schedules and aircraft weight growth were the primary concerns. The contractors also were aware that their costs likely would exceed the ceiling price in the contract. Everyone knew in early 1990 that a June 1990 first flight could not be achieved. The Contracting Officer asked the contractors for an estimate of when the first aircraft would be delivered. Negotiations ensued, but ultimately the Navy and the contractors could not agree on a date. The Navy issued a unilateral schedule modification on August 17, 1990. The unilateral schedule for first flight was December 31,1991.

The contractors asked the Navy for restructure of the contract in November 1990. The Navy issued reports during November that the Navy A-12 Program Manager was unreasonable in his conclusion that the contract could be completed within the specified ceiling price, and he failed to anticipate greater risk in the schedule. Secretary of Defense Cheney briefed the President of the United States in early December. He expressed disappointment with the Navy’s handling of the A-12 program and promised to take corrective action. Thereafter, Secre[314]*314tary Cheney directed the Deputy Secretary of Defense to report on the status of the A-12 program within 10 days.

Secretary of the Navy Lawrence Garrett responded to Secretary Cheney’s request on December 12. Secretary Garrett was concerned about the contractors’ willingness to complete the contract as it was then structured. The Office of the Secretary of Defense sent a memorandum to the Navy on December 14, directing the Navy to “show cause by January 4, 1991 why the Department should not terminate the A-12 program and pursue other alternatives.”

At the direction of OSD, the Navy sent a cure notice to the contractors on December 17. The Navy asserted in the notice that the contractors “failed to fabricate parts sufficient to permit final assembly in time to meet the schedule for delivery of FSED aircraft [and] fail[ed] to meet specification requirements ____”

The contractors responded to the cure notice denying they were in default of the A-12 contract. They asserted that the unilateral schedule was unenforceable and that the specifications were unachievable. The contractors also provided the Navy with a “Proposal for Equitable Restructure of the A-12 Contract.” They requested the contract be restructured pursuant to Pub.L. No. 85-804.2 In return, they would absorb a $1.5 billion fixed loss, the contract would be restructured to a cost-reimbursement contract, and they would waive their claims for equitable adjustment. The record indicates that the Undersecretary of Defense for Acquisition, Mr. Yockey, would have been willing to go forward if the contractors had agreed to accept a $2 billion loss and other concessions.3

Rear Admiral William R. Morris was the Contracting Officer at the time. He met with Undersecretary Yockey and Navy officials on January 4. The Chief Engineer for the Navy reported at the meeting that technical challenges on the A-12 were typical for this type of development contract, and that the contractors could resolve remaining technical challenges. The Navy and the Joint Requirements Oversight Council re-validated the operational requirements.

Secretary Cheney met with Secretary Garrett, Undersecretary Yockey, and the Chairman of the Joint Chiefs of Staff on January 5 and decided not to grant 85-804 relief. Secretary Cheney understood that the A-12 program would be cancelled as a result, but the Navy would decide how and whether to terminate the contract. Admiral Morris met with Mr. Yockey and other Department of Defense officials on Sunday, January 6. He terminated the contract for default the next day.

Before then, Admiral Morris did not believe that 85-804 relief was the only way to proceed with the contract. He wanted the opportunity to work with the contractors. Admiral Morris had not anticipated termination of the A-12 contract.

Admiral Morris testified that under Yockey’s guidelines he was not able to do what he wanted to do, which was to continue the contract. McDonnell Douglas Corp., 35 Fed.Cl. at 368 n. 13. The termination letter stated that plaintiffs were being terminated for “inability to complete the design, development, fabrication, assembly and test of the A-12 aircraft within the contract schedule and the Team’s inability to deliver an aircraft that meets contract requirements.” Id. at 368. The letter stated,

the Team is in default of the contract for having failed to make progress and not meeting contract requirements. The A-12 aircraft will not be delivered within the contract schedule nor will it meet the weight guaranty contained within the contract specification.

The contractors sued for relief on a number of bases, and the parties agreed to litigate a potentially dispositive issue first. That was Count 17, which challenged the [315]*315manner in which the Navy terminated the contract for default. We ruled that the default termination was improper because we found from testimony and other evidence that Admiral Morris was not permitted to exercise reasoned discretion. Id. at 375. We found that the termination for default was not related to performance. Id. at 377. The Navy was the contracting agency, and it did not believe that the contractors’ performance justified termination for default.

The Federal Circuit found that “the government’s default termination was not pre-textual or unrelated to Contractors’ alleged inability to fulfill their obligations under the contract.” McDonnell Douglas Corp., 182 F.3d at 1326.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

General Dynamics Corp. v. United States
131 S. Ct. 1900 (Supreme Court, 2011)
McDonnell Douglas Corp. v. United States
567 F.3d 1340 (Federal Circuit, 2009)
McDonnell Douglas Corp. v. United States
76 Fed. Cl. 385 (Federal Claims, 2007)
White Buffalo Construction, Inc. v. United States
52 Fed. Cl. 1 (Federal Claims, 2002)

Cite This Page — Counsel Stack

Bluebook (online)
50 Fed. Cl. 311, 2001 U.S. Claims LEXIS 171, 2001 WL 1053368, Counsel Stack Legal Research, https://law.counselstack.com/opinion/mcdonnell-douglas-corp-v-united-states-uscfc-2001.