Aerospace Facilities Group, Inc.

CourtArmed Services Board of Contract Appeals
DecidedAugust 10, 2020
DocketASBCA No. 61026
StatusPublished

This text of Aerospace Facilities Group, Inc. (Aerospace Facilities Group, Inc.) is published on Counsel Stack Legal Research, covering Armed Services Board of Contract Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Aerospace Facilities Group, Inc., (asbca 2020).

Opinion

ARMED SERVICES BOARD OF CONTRACT APPEALS

Appeal of -- ) ) Aerospace Facilities Group, Inc. ) ASBCA No. 61026 ) Under Contract No. W912NW-12-C-0035 )

APPEARANCES FOR THE APPELLANT: Theodore P. Watson, Esq. Watson and Associates LLC Washington, DC

Wojciech Z. Kornacki, Esq. Watson & Associates LLC Denver, CO

APPEARANCES FOR THE GOVERNMENT: Scott N. Flesch, Esq. Army Chief Trial Attorney Robert B. Neill, Esq. MAJ Mark T. Robinson, JA Trial Attorneys

OPINION BY ADMINISTRATIVE JUDGE MCILMAIL

Appellant, Aerospace Facilities Group, Inc. (AFG), appeals from the termination of its contract to deliver “paint booth equipment” (for the painting of helicopters) to the Corpus Christi Army Depot; AFG also seeks breach damages (app. br. at 1, 32). Only entitlement is before us (tr. 1/7).

STATEMENT OF FACTS

In Aerospace Facilities Grp., Inc., ASBCA No. 61026, 18-1 BCA ¶ 37,105 at 180,602-03, we recited facts that we incorporate here by reference. Familiarity with that opinion is presumed. In addition, the contract incorporates by reference Federal Acquisition Regulation (FAR) 52.249-1, TERMINATION FOR CONVENIENCE OF THE GOVERNMENT (FIXED PRICE) (SHORT FORM) (APR 1984), and FAR 52.249-8, DEFAULT (FIXED-PRICE SUPPLY & SERVICE) (APR 1984) (R4, tab 1 at 68). AFG contracted with Global Finishing Solutions (GFS) to obtain the paint booth equipment required by the contract (see app. br. 1, 6 ¶ 14). On November 9, 2015, Contracting Officer June Gowen issued the following unilateral modification, withholding payment of $342,600 under the contract at issue here until AFG provided four pieces of equipment called “ergo test stands” due under a different contract between AFG and the government (Contract No. W912NW-12-C-0031), which were also meant for the Corpus Christi Army Depot:

1. BACKGROUND: Aerospace Facilities Group has failed to deliver and install four ergo test stands called for in the specifications of Contract No. W912NW-12-C-0031.

2. ACTIONS TAKEN: Because of this, funding will be withheld from another Aerospace Facilities Group contract, W912NW-12-C-0035 until such time as Aerospace Facilities Group delivers and installs the four ergo test stands at the Corpus Christi Army Depot. The amount of $342,600.00 has been moved out of CLIN 0001AA into new CLIN 0002. This amount will be withheld from payments in contract W912NW-12-C-0035 until such time as Aerospace Facilities Group delivers and installs the four ergo test stands at the Corpus Christi Amount Depot [under Contract No. W912NW-12-C-0031].

R4, tab 35 at 1 (alteration added)

On January 28, 2016, Ms. Gowen issued a unilateral modification that purports to incorporate into the contract FAR 52.212-4, CONTRACT TERMS AND CONDITIONS – COMMERCIAL ITEMS (MAY 2015) (R4, tab 49 at 1). On March 30, 2016, the parties modified the contract to extend the period of performance through June 28, 2016 (see R4, tab 92 at 1-3). That modification also provides:

Installation payments were erroneously paid to contractor prior to installation efforts being performed. All funding prematurely and erroneously paid on CLINS 0001AF in the amount of $772,550.48 and 0001AS in the amount of $837,298.93, totaling $1,609,849.41, shall be returned to the Government by AFG via credits to all future invoices until paid in full.

(Id. at 3)

AFG did not deliver the paint booth equipment to the government by the contract’s June 28, 2016 deadline; indeed, AFG never delivered any of the paint booth equipment required by the contract (see app. br. at 1; tr. 1/31, 193). On July 8, 2016, Contracting Officer Peggy Echols issued to AFG an Order to Show Cause, informing AFG that the government was considering terminating the contract for default (R4,

2 tab 133). On July 27, 2016, AFG responded, admitting that it did not deliver the paint booth equipment on time--even though, according to AFG, the paint booth equipment had been manufactured and was in AFG’s storage--because, AFG said, the government had not made a $342,600 payment to AFG:

All of the equipment for contract (W912NW-12-C-0035) has been manufactured and in our storage since June 2015 awaiting the government to complete the ACCF building where the equipment is going to be installed. . . . The equipment delivery date (June 2016) given to AFG by the government could not be met by [sic] due to the fact that the government held up the contractual agreed payments of $304,406.32, so in turn AFG could not fulfill our contractual agreements with our suppliers.

(R4, tab 157 at 4) AFG admitted to its “failure to perform on this contact [sic],” and explained that, in its view, that failure was “due to the government issui[ng a h]old on our contractual payment schedule set up for this contract” (id. at 3-4 (referencing “AFG failure to perform on this contract”)). Through counsel, AFG reaffirms that admission, stating that “the cause of the non-delivery” was AFG’s “subcontractor not getting paid” (app. br. at 14), and that AFG “did not pay their subcontractors” (tr. 1/79). Indeed, in its post-hearing brief, AFG states:

[AFG] also explained [to the government] that it could not meet the delivery date imposed by [the government] because [the government] did not make contractual payments to [AFG] which prevented [AFG] from making payments to the sub-contractor.

(App. br. at 11 ¶ 53) (alterations added)

However, AFG could have paid GSF for the paint booth equipment, from corporate funds. During the hearing of this appeal, AFG’s owner, Dennis Robinson, read the following from his deposition:

Question: “But you could have paid Global Finishing Solutions with the money you had in the corporate account. Correct?” Answer: “Yes.”

(Tr. 2/135, 171) AFG simply decided not to pay GFS because, in AFG’s view, the government owed AFG money:

3 Question: Is the reason why you didn’t pay Global Finishing Solutions because you believed that the Government owed you money on those additional invoices you submitted?

[Mr. Robinson] Yes.

...

Question: So [the Order to Show Cause is] dated July 8, 2016. And so by that date, the final delivery date established in modification 6 had passed. Did you still not intend to deliver the paint booths until you received the payments that you believed were owed under the contract to you in order to pay Global Finishing Solutions?

[Mr. Robinson] That is correct.

(Id. at 171, 193) Additionally, Mr. Robinson testified that AFG could have paid its supplier from corporate funds, but chose not to do so because “[AFG] wasn’t going to be the bank for the government” (id. at 172, 216).

Finally, the government was ready to receive the paint booth equipment when it was due: on this point, on May 31, 2016, Ms. Echols wrote to AFG that “the government has identified storage space for the remaining paint booth equipment” (R4, tab 114). In addition, the judge who presided over the hearing elicited the following answer to the following question:

JUDGE YOUNG: So does this mean that, even though there was a concern about storage costs, the Government was ready to receive equipment?

[Ms. Gowen]: Yes.

(Tr. 1/212)

On August 4, 2016, Ms. Echols issued a modification terminating the contract for default (using the term “Termination for Cause”), citing FAR 52.212-4(m) and stating that AFG had “failed to deliver in accordance with the terms of the contract” (R4, tab 158 at 1-2; see also tab 159 (cover letter to AFG)).

4 DECISION

Termination for default

The government says that FAR 52.212-4 is incorporated into the contract by the Christian doctrine (gov’t br. at 29). We need not address that issue, nor whether Ms. Gowen’s unilateral modification, purporting to incorporate that clause into the contract, is a nullity.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
Aerospace Facilities Group, Inc., Counsel Stack Legal Research, https://law.counselstack.com/opinion/aerospace-facilities-group-inc-asbca-2020.