Central Company

CourtArmed Services Board of Contract Appeals
DecidedFebruary 2, 2022
DocketASBCA No. 62624
StatusPublished

This text of Central Company (Central Company) is published on Counsel Stack Legal Research, covering Armed Services Board of Contract Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Central Company, (asbca 2022).

Opinion

ARMED SERVICES BOARD OF CONTRACT APPEALS Appeal of - ) ) Central Company ) ASBCA No. 62624 ) Under Contract No. FA4654-19-C-A006 )

APPEARANCE FOR THE APPELLANT: Mr. Chris Yang Representative

APPEARANCES FOR THE GOVERNMENT: Jeffrey P. Hildebrant, Esq. Air Force Deputy Chief Trial Attorney Jason R. Smith, Esq. Lori R. Shapiro, Esq. Lt Col John C. Degnan, USAF Trial Attorneys

OPINION BY ADMINISTRATIVE JUDGE SMITH

In this appeal, we resolve appellant Central Company’s (Central) challenge to respondent Air Force’s (the government) default termination of Central’s $348,688 design/build construction contract. The parties have elected a written disposition under Board Rule 11. 1 Central argues primarily that the government’s termination failed to account for obstacles to Central’s performance caused by the COVID-19 pandemic (COVID). The government responds that Central made almost no progress during the majority of the performance period which was prior to COVID and that Central did not demonstrate any legitimate COVID delays. For the reasons discussed below, we find that the government’s decision to terminate Central’s contract for default was justified and Central’s arguments against the termination are unavailing. As a result, we deny the appeal.

1 During earlier proceedings, the government moved for summary judgment and Central submitted its position in response to the government’s motion. The government then replied to Central’s response. Subsequently, the parties agreed to a Rule 11 disposition, adopted their earlier submissions as their Rule 11 briefs, and supplemented the record before it was closed. We have considered Central’s positions in its Rule 11 briefing and its prior communications with the government. FINDINGS OF FACT

Central’s $348,688.00 contract No. FA4654-19-C-A006 (the contract) was executed on September 30, 2019, by Central’s president Mr. Chris Yang (R4, tab 5 at 2, 8; tab 6). The contract was for the design and construction of a fairly small (2,400 square feet) one-story metal Civil Engineer Squadron storage building and yard at Grissom Air Reserve Base, Indiana (R4, tab 1a at 3, 7). The contract required all work to be completed by May 19, 2020, which was 180 days from the November 21, 2019, notice to proceed (NTP) (R4, tab 1 at 1; tabs 17, 35).

The contract contained typical preconstruction paperwork requirements for a relatively simple 2 government construction project (bonds, plans, permits, schedule, submittals, design reviews, etc.) (R4, tab 1a at 8-9; tab 1f at 5; tab 16 at 2-3). The preconstruction documents were to be sequentially submitted to the government for review, comment and approval and the contract explicitly stated that construction could not begin “prior to Government approval of plans and specifications” (R4, tab 1a at 15). As with any design/build project, a fully reviewed and approved design was critical to beginning any field work, and the contract here required a sequential three- phase submittal/review/approval process at 35%, 95%, and 100% of the design (R4, tab 1a at 7- 8, 10).

Central’s Performance Prior to COVID

From contract award onward, progress was slow or non-existent (see e.g. R4, tab 27 at 5). The NTP was delayed for lack of Central’s bonding (R4, tab 8). Deadlines for basic startup submissions came and went – often until the contracting officer reminded Central of its obligations (see e.g. R4, tabs 27, 35). The government attempted to assist Central, including in-person meetings, examples of necessary forms, and pointers regarding efficient ways to prepare documents (R4, tabs 18-20, 27). Central replied to the contracting officer’s reminders with several promises such as “I will get it done soon,” “the plan will be ready next week,” “[o]ur Architect should get the plan ready this week, and I will try to get all paper work ready too” that were not kept (R4, tabs 18, 27). By February 28, 2020, over halfway through the allotted performance time, and before COVID significantly affected the United States,

2 The building was solely for storage of “clothing, furniture, tents, containers, and miscellaneous construction tools” so the physical features were straightforward and did not have any particularly complicated elements (R4, tab 1a at 5). For example, the building required a fire protection system and basic electric power, but not a plumbing or HVAC system (see e.g. R4, tab 1a at 5-6; tab 27 at 6-10, 15).

2 Central’s first and only submission (made on January 12, 2020, disapproved on January 17, 2020) was not acceptable, and most of the other required documents – including the 35% design, had not been submitted by Central at all (R4, tabs 24, 27). Another month later, on March 26, 2020, Central’s second and third submissions were again deficient and many documents remained missing (R4, tab 28). Central’s project schedule – the fundamental tool by which contract progress is measured – was sketchy and noncompliant. Id. With less than two months remaining, the contracting officer’s March 26, 2020, email summarized Central’s lack of progress and once again provided specific instructions regarding outstanding items. Id. On March 27, 2020, Central wrote “[w]e are really sorry for the delay; we are doing everything we can to catch up” (R4, tab 28 at 1).

In April and May 2020, Central continued to demonstrate a lack of attention to the sequence in which the project was to proceed and indicated vaguely that it was “ready to start the project,” that elements of the design were “finished” and that it was “ready to do the site preparation work” when none of the necessary approvals had been obtained (R4, tabs 27-28). The government’s April 16, 2020, feedback on Central’s third submission identified numerous fundamental problems with Central’s documents (R4, tabs 24, 26). By the contract completion date of May 19, 2020, Central still did not have an approved progress schedule and none of Central’s design documents were approved (R4, tab 33). On May 20, 2020, the contracting officer issued a show cause notice, to which Central responded on May 26, 2020 (R4, tabs 33- 34). On June 4, 2020, approximately two weeks after the completion date and with 0% of the work completed, Central’s contract was terminated for default for failure to meet the contract completion date without a valid excuse (R4, tab 35). The termination notice considered COVID and determined that it did not excuse Central’s lack of progress. Id.

COVID’s Effect on Central’s Performance

The first indication in the record regarding COVID came in an email from Central on March 25, 2020, when four months of the six-month performance period had already passed, and Central had not made any palpable progress on preconstruction requirements (R4, tab 27 at 1-2). By that date, Central had not re- submitted, much less received approval of, its design (R4, tab 33). Consequently, completion of the design review process, the other preconstruction requirements, and construction – all by May 19, 2020, was highly unlikely. Further, Central’s March 25, 2020, email indicated awareness of COVID and some degree of concern, without identifying any specific impediment to the completion of the design, as follows:

I saw the notice of the DOD about the coronavirus crisis; does it means most contracts in the emergence area are 3 given more time to finish. We are still try to finish it as soon as possible on our side, but we do have lots of difficulties dealing with it.

(R4, tab 27 at 1)

Similarly, on March 27, 2020, Central wrote “I will redo the [form AF] 3000 as well; our site preparation contractor is ready and can start anytime; I do worry about this coronavirus thing may get worse and we have to stop in the middle, that may cause some losses” (R4, tab 29 at 1).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Darwin Construction Co., Inc. v. United States
811 F.2d 593 (Federal Circuit, 1987)
Lisbon Contractors, Inc. v. The United States
828 F.2d 759 (Federal Circuit, 1987)

Cite This Page — Counsel Stack

Bluebook (online)
Central Company, Counsel Stack Legal Research, https://law.counselstack.com/opinion/central-company-asbca-2022.