Zinger Construction Co., Inc. v. The United States

807 F.2d 979, 33 Cont. Cas. Fed. 74,886, 1986 U.S. App. LEXIS 20733
CourtCourt of Appeals for the Federal Circuit
DecidedDecember 18, 1986
DocketAppeal 86-1180
StatusPublished
Cited by16 cases

This text of 807 F.2d 979 (Zinger Construction Co., Inc. v. The United States) is published on Counsel Stack Legal Research, covering Court of Appeals for the Federal Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Zinger Construction Co., Inc. v. The United States, 807 F.2d 979, 33 Cont. Cas. Fed. 74,886, 1986 U.S. App. LEXIS 20733 (Fed. Cir. 1986).

Opinion

JACK R. MILLER, Senior Circuit Judge.

This appeal is from a decision of the Armed Services Board of Contract Appeals (“board”), Docket No. 26331, affirming the denial of appellant’s request for an equitable adjustment. We affirm.

BACKGROUND

In 1980, Zinger Construction Company (“Zinger”) was awarded Contract No. DACA 31-80-C-0110 for the installation of electric duct heaters in a dehumidifier system at the Tobyhanna Army Depot in Pennsylvania. Under the contract, Zinger was required to move existing fan units and steam coils in the dehumidifier ducts approximately three feet forward and to install new electric heaters downstream from the relocated steam coils and fans. The purpose of the contract was to provide the option of electric heat during the summer months while retaining the option of steam heat (provided by the steam coils) during the winter.

After installing the electric heaters and relocating the existing fan units and steam coils, Zinger was directed by the contracting officer to reconnect the steam coils and fans to the electric control box. Zinger performed the work under protest, asserting that it was not required to reconnect the control wires. Because the existing wires would not reach the relocated equipment, a new junction box and connecting wires had to be installed. Zinger filed a claim for an equitable adjustment of $14,-891, but the contracting officer denied the claim.

On appeal to the board, Zinger argued that the contract was a “design contract,” not a “performance contract,” and that Zinger was entitled to rely exclusively on the drawings and detailed specifications. Because the disputed wiring was not depicted in the drawings or described in detail in the specifications, it was argued that reconnection of the control wires was not a part of the contract.

*981 The board concluded that the contract required that the completed system be fully reconnected and operational. Alternatively, the board found that to the extent the disputed wiring was not depicted or described in detail, a reasonable contractor would have recognized its absence in the plans and would have been obligated to inquire about the extent of work to be performed. Because Zinger had not inquired and had failed to examine existing wiring during pre-bid inspection, the board concluded that Zinger had assumed the risk that its interpretation of the contract was incorrect.

Zinger argues that the board erred in concluding that the disputed work was required and also asserts that there was no patent ambiguity or omission in the drawings such that Zinger was obligated to inquire about the scope of work to be performed. It reasserts that the contract in question was a design contract and that the omission of detail in the drawings and specifications clearly indicated that reconnection of the control wiring was not required.

OPINION

Our review of board decisions is governed by section 10(b) of the Contract Disputes Act of 1978, 41 U.S.C. § 609(b) (1982). Questions of law resolved by the board are neither final nor binding on the court, but findings of fact made by the board are final and conclusive unless arbitrary, capricious or unsupported by substantial evidence. American Electronic Laboratories, Inc. v. United States, 774 F.2d 1110, 1112 (Fed.Cir.1985).

The board found that a reasonable contractor would have expected to reconnect the control wiring and concluded that the contract, read as a whole, required that the completed system be operational. We are satisfied that the board’s finding was neither arbitrary nor capricious and was based on substantial evidence; further, that its conclusion was reasonable. The record includes the testimony of the project engineer, who stated that the equipment had to be reconnected for the system to be fully operational. Moreover, paragraph 11.3.6 of the contract requires the contractor to install and electrically connect the duct heaters “in such a manner that ... existing automatic control is functionally and operationally assured____”

Zinger’s argument, that the subject contract is a “design contract,” entitling it to rely solely on the drawings and detailed specifications, is misguided. On occasion the labels “design specification” and “performance specification” have been used to connote the degree to which the government has prescribed certain details of performance on which the contractor could rely. See, J.L. Simmons Company v. United States, 188 Ct.Cl. 684, 689, 412 F.2d 1360, 1362 (1969); see also, Ordnance Research, Inc. v. United States, 221 Ct.Cl. 641, 670, 609 F.2d 462, 479 (1979) (performance is established where contractor followed the methods and utilized the materials prescribed in specifications). However, those labels do not independently create, limit, or remove a contractor’s obligations. Contracts are viewed in their entirety and given the meaning imputed to a “reasonably intelligent contractor” acquainted with the involved circumstances, J.B. Williams Company v. United States, 196 Ct.Cl. 491, 507, 450 F.2d 1379, 1388 (1971); Holgar Mfg. Corp. v. United States, 169 Ct.Cl. 384, 388, 351 F.2d 972, 975 (1965), regardless of whether labelled “design,” “performance,” or both.

Accordingly, the decision of the board is affirmed.

AFFIRMED.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Meltech Corporation, Inc.
Armed Services Board of Contract Appeals, 2025
Meridian Engineering Company v. United States
122 Fed. Cl. 381 (Federal Claims, 2015)
Fireman's Fund Insurance v. United States
92 Fed. Cl. 598 (Federal Claims, 2010)
C.H. Guernsey & Co. v. United States
65 Fed. Cl. 582 (Federal Claims, 2005)
Turner Construction Co., Inc. v. United States
367 F.3d 1319 (Federal Circuit, 2004)
Fru-Con Construction Corp. v. United States
42 Cont. Cas. Fed. 77,399 (Federal Claims, 1998)
Hre, Incorporated v. United States
142 F.3d 1274 (Federal Circuit, 1998)
Dillingham Construction, N.A. v. United States
40 Cont. Cas. Fed. 76,827 (Federal Claims, 1995)
Mega Construction Co. v. United States
39 Cont. Cas. Fed. 76,564 (Federal Claims, 1993)
Blake Construction Company, Inc. v. The United States
987 F.2d 743 (Federal Circuit, 1993)
Gaston & Associates, Inc. v. United States
38 Cont. Cas. Fed. 76,429 (Federal Claims, 1992)
California Sand & Gravel, Inc. v. United States
36 Cont. Cas. Fed. 75,968 (Court of Claims, 1990)
Haehn Management Co. v. United States
34 Cont. Cas. Fed. 75,469 (Court of Claims, 1988)
Darwin Construction Co., Inc. v. United States
811 F.2d 593 (Federal Circuit, 1987)

Cite This Page — Counsel Stack

Bluebook (online)
807 F.2d 979, 33 Cont. Cas. Fed. 74,886, 1986 U.S. App. LEXIS 20733, Counsel Stack Legal Research, https://law.counselstack.com/opinion/zinger-construction-co-inc-v-the-united-states-cafc-1986.