Hre, Incorporated v. United States

142 F.3d 1274, 42 Cont. Cas. Fed. 77,287, 1998 U.S. App. LEXIS 8280, 1998 WL 205340
CourtCourt of Appeals for the Federal Circuit
DecidedApril 29, 1998
Docket97-1197
StatusPublished
Cited by14 cases

This text of 142 F.3d 1274 (Hre, Incorporated v. United States) is published on Counsel Stack Legal Research, covering Court of Appeals for the Federal Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Hre, Incorporated v. United States, 142 F.3d 1274, 42 Cont. Cas. Fed. 77,287, 1998 U.S. App. LEXIS 8280, 1998 WL 205340 (Fed. Cir. 1998).

Opinion

FRIEDMAN, Senior Circuit Judge.

The question is whether the Armed Services Board of Contract Appeals (“Board”) correctly interpreted a government contract for renovation of a building as requiring the contractor to insulate certain piping. We agree with the Board’s interpretation of the contract and we affirm its decision.

I.

The Department of Health and Human Services (“government”) awarded a contract to HRE, Inc., for renovation of a federal *1275 office building. The contract’s instructions for insulating piping and air handling and distribution equipment provide in relevant part:

8.3 INSULATION FOR LOW-TEMPERATURE PIPING
A. General: Unless otherwise specified, insulate low-temperature piping.
B. Locations Insulated: Install insulation in the following locations and as indicated:
1. Chilled water piping.
2. Dual-temperature piping (with alternate heating and cooling).
3.4 INSULATION FOR AIR HANDLING AND AIR DISTRIBUTION EQUIPMENT AND DUCTS
A. General: Unless otherwise specified insulate air handling and air distribution equipment.
B. Ventilation System Locations Insulated [if leaving temperatures less than 32 0 C]:
1. Heating coil enclosures.
C. Air Heating System Locations Insulated [if leaving temperature more than 320 C]:
1. Heating coil enclosures and external headers.

During performance of the contract, the government directed HRE to insulate condenser water piping, vortex dampers, and the new ductwork that HRE had installed pursuant to other provisions of the contract. HRE objected to these directives, contending that they called for work the contract did not require. HRE complied with the directives, and subsequently filed with the contracting officer claims seeking an equitable adjustment for this work. The contracting officer denied HRE’s claims and the Board affirmed. The Board held that the language of the contract required HRE to do the work.

II.

The parties dispute the meaning of the above-quoted sections 3.3 (Insulation for Low-Temperature Piping) and 3.4 (Insulation for Air Handling and Air Distribution Equipment and Ducts). Because the factual background and legal issues relevant to interpreting each section are for our purposes identical, we simplify our discussion by focusing on the provisions for insulating low-temperature piping.

A. Section 3.3A unambiguously states: “Unless otherwise specified, insulate low-temperature piping.” HRE concedes that condenser piping is “low-temperature piping.” Nothing in section 3.3 “specified]” that the low-temperature condenser piping is not to be insulated, and the clear language of section 3.3A requires such insulation.

That section 3.3A means what it says is confirmed by another provision of the contract that contains specific exceptions to an indistinguishable general insulation requirement. Section 3.2A provides that piping and equipment for steam and hot water systems should be insulated “[ujnless otherwise specified.” Section 3.2C, entitled “Locations Not Insulated,” lists specific items of equipment that, although within 3.2A’s general category of “equipment for steam and hot water heating systems,” need not be insulated.

Interpreting the contract in its entirety, see Zinger Constr. Co. v. United States, 807 F.2d 979, 981 (Fed.Cir.1986), we conclude that if the parties intended to exempt condenser piping from the requirement in section 3.3A that low-temperature piping was to be insulated, the contract would have explicitly said so — as it did in section 3.2C for certain steam and hot water systems. In the absence of such an exemption, we agree with the Board that section 3.3A should be applied as written to cover all “low-temperature piping” “[ujnless otherwise specified,” and that the contract did not “otherwise specif[yj” that condenser piping need not be insulated.

B. HRE contends, however, that the history of the drafting of the contract shows that such piping was not to be insulated. The technical provisions of the contract consisted of portions of a government document that supplemented a document known as “Masterspec,” an American Institute of Architects set of work standards widely used in the construction industry. In preparing the *1276 contract, the government’s draftsman made various changes in the Masterspec Supplement.

Section 3.4 of the Masterspec Supplement, which governs “insulation for low-temperature piping” and parallels section 3.3 of the contract, lists six types of equipment under the heading “Locations Insulated.” This is the counterpart of section 3.3B of the contract. Item 2 of that listing is condenser piping. That item was not included in section 3.3B of the contract, which contains only-two other items.

HRE contends that because condenser piping was not included in section 3.3B, the contract’s general insulation requirement was not intended to cover such piping. It is section 3.3A, however, and not section 3.3B, that defines the work to be done. Section 3.3B identifies the locations.

The only exception to the general insulation requirement in section 3.3A is if non-insulation is “otherwise specified.” The use of the word “specified,” instead of a more general word like “indicated,” strongly suggests that any such exception must be explicitly stated — as it is in section 3.2C. The negative implication upon which HRE relies— that the absence of any reference to condenser piping in the “locations insulated” provision in section 3.3B shows that section 3.3A does not cover such piping — does not satisfy the “otherwise specified” requirement of the latter section.

HRE’s construction of the contract violates the well-settled rule that when the provisions of a contract are clear, “the court may not resort to extrinsic evidence to interpret them.” McAbee Constr., Inc. v. United States, 97 F.3d 1431, 1435 (Fed.Cir.1996). “Outside evidence may not be brought in to create an ambiguity where the language is clear.” City of Tacoma v. United States, 31 F.3d 1130, 1134 (Fed.Cir.1994). Here, as we have shown, the general insulation requirement in section 3.3A is clear and unambiguous. Its coverage cannot be restricted by resort to evidence — primarily the testimony of the government official who drafted the contract — regarding the circumstances under which the Masterspec Supplement provision listing condenser piping as one of the six locations to be insulated was not included in section 3.3B of the contract.

Invoking the principle that a contract should be interpreted to give meaning to all of its provisions, see Kimbrell v.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Alnylam Pharmaceuticals, Inc. v. Moderna, Inc.
138 F.4th 1326 (Federal Circuit, 2025)
Zhou v. United States
Federal Circuit, 2018
Zhou v. United States
133 Fed. Cl. 322 (Federal Claims, 2017)
Young v. United States
133 Fed. Cl. 471 (Federal Claims, 2017)
Vermont Yankee Nuclear Power Corp. v. United States
84 Fed. Cl. 339 (Federal Claims, 2008)
Alliant Techsystems Inc. v. United States
74 Fed. Cl. 566 (Federal Claims, 2007)
La Gloria Oil & Gas Co. v. United States
72 Fed. Cl. 544 (Federal Claims, 2006)
General Electric Co. v. United States
60 Fed. Cl. 782 (Federal Claims, 2004)
Sterling Savings v. United States
57 Fed. Cl. 445 (Federal Claims, 2003)
Ryco Construction, Inc. v. United States
55 Fed. Cl. 184 (Federal Claims, 2002)
Precision Pine & Timber, Inc. v. United States
50 Fed. Cl. 35 (Federal Claims, 2001)
LaSalle Partners v. United States
48 Fed. Cl. 797 (Federal Claims, 2001)

Cite This Page — Counsel Stack

Bluebook (online)
142 F.3d 1274, 42 Cont. Cas. Fed. 77,287, 1998 U.S. App. LEXIS 8280, 1998 WL 205340, Counsel Stack Legal Research, https://law.counselstack.com/opinion/hre-incorporated-v-united-states-cafc-1998.