Johnny F. Smith Truck & Dragline Service, Inc. v. United States

49 Fed. Cl. 443, 2001 U.S. Claims LEXIS 87, 2001 WL 543145
CourtUnited States Court of Federal Claims
DecidedMay 21, 2001
DocketNo. 99-997C
StatusPublished
Cited by6 cases

This text of 49 Fed. Cl. 443 (Johnny F. Smith Truck & Dragline Service, Inc. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Federal Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Johnny F. Smith Truck & Dragline Service, Inc. v. United States, 49 Fed. Cl. 443, 2001 U.S. Claims LEXIS 87, 2001 WL 543145 (uscfc 2001).

Opinion

OPINION

FIRESTONE, Judge.

This contract dispute comes before the court on the government’s motion for partial summary judgment. The ease arises over a [445]*445contract entered into in 1997 between the United States Army Corps of Engineers (“Corps” or “COE”) and Johnny F. Smith Truck & Dragline Service, Inc. (“Smith”). Necessitated by the floods in the City of Grand Forks, North Dakota, in the spring of 1997, the contract provided for disaster-related demolition and disposal services. In its complaint, Smith seeks an equitable adjustment for work it completed that it argues went beyond the scope of the contract. In its motion for partial summary judgment, the government counters that, as a matter of law, Smith is not entitled to further payment on the majority of its claims.

For the reasons that follow, the court GRANTS the government’s motion for partial summary judgment.

FACTS

I. Background

A. The Contract

The following facts are not in dispute. The City of Grand Forks, North Dakota, was subject to devastating flooding in the spring of 1997. The Corps was assigned responsibility for cleaning up the area. In keeping with this responsibility, the Corps, on June 27, 1997, awarded Contract No. DACW37-97-C-0019 (“Grand Forks contract”) to Smith, a Mississippi contractor, to perform disaster cleanup work. The bid schedule for the base contract consisted of four line items:

1. Item 0001, “Demolition, Debris Removal, & Backfill of Homes (Less than 1200 SF [square feet]),” with an estimated quantity of five;

2. Item 0002, “Demolition, Debris Removal, & Backfill of Homes (Greater than or equal to 1200 SF),” with an estimated quantity of ten;

3. Item 0003, “Detached Garages — Demolition and Debris Removal,” with an estimated quantity of five; and

4. Item 0004, “Waterline Capping,” with an estimated quantity of four.

The base contract provided a fixed price of $98,000 (demolition of twenty structures for $90,000 and water capping for $8,000).

The contract bid schedule also included twenty-seven optional items:

1. Items 0005 through 0010, “Demolition, Debris Removal, & Backfill of Homes (Less than 1200 SF),” with an estimated quantity of five structures within each option;

2. Items 0011 through 0017, “Demolition, Debris Removal, & Backfill of Homes (Greater than or equal to 1200 SF),” with an estimated quantity of five structures within each option;

3. Items 0018 through 0026, “Detached Garages — Demolition and Debris Removal,” with an estimated quantity of five structures within each option; and

4. The remaining optional items were for “Waterline Capping.”

The price for all these options, if exercised, was $211,000. Together, the price of the base contract plus all options, if exercised by the government, was $309,000.

The contract contained the following pertinent provisions. Paragraph 1 of the Scope of Work, GENERAL, provided:

The work under this contract consists of demolition, debris removal, and structural excavation to demolish and remove public and private buildings and appurtenant structures within the city of Grand Forks, ND that were damaged beyond repair and that represent an immediate threat to public safety. The contractor shall provide all labor, plant equipment, machines and tools necessary to perform demolition and removal of structural debris at sites identified by the Contracting Officer’s Representative (COR). The contractor shall demolish and remove all structures including basements____ The Contractor shall also remove all debris remaining on each work site surrounding the structure to be demolished under this contract. This includes the debris existing on the work site prior to the Contractor mobilizing to the site____The bid price for demolition of homes and garages will include all costs of mobilization, demobilization, labor, tools, material, equipment, and evei’ything necessary to demolish, load, haul and dispose of all debris generated by the demolition.

[446]*446Paragraph 2 of the Scope of Work, SCHEDULE, provided:

The contractor shall mobilize his equipment and crews within thirty-six (36) hours of receipt of the Notice to Proceed.... A production rate of at least 20 work sites demolished, cleared, and backfilled per week (7 days) is required. The contractor is responsible for all necessary permits and utility disconnection’s [sic] to insure this production rate.

Paragraph 3 of the Scope of Work, OPTIONS, stated:

The work sites listed as options will be exercised in groups of five work sites at a time.

Paragraph 4 of the Scope of Work, UTILITIES, established:

The contractor shall comply with the requirements of local officials and codes having jurisdiction over the work, including but not limited to, hours of work, abandonment of utilities, and permits____The contractor shall contact all local officials and utility companies at least 48 hours prior to commencing work on each work site and a record of contacts shall be provided to COR for verification____ The contractor, prior to making any preparations, shall bring to the Contract Officer’s attention any work that the contractor considers to be an additional service not included in this contract.

Paragraph 5 of the Scope of Work, SAFETY, provided:

The Government shall accomplish initial identification and removal of hazardous or toxic waste. However some propane cylinders and hazardous waste material may escape detection and be located in the debris. The contractor shall inform the COR immediately upon finding any hazardous material such as propane tanks or other potentially hazardous material. The contractor shall set aside all hazardous materials____The contractor shall supply workers with personal protective equipment to protect against potential asbestos, chemical and biological hazards.

Paragraph 8.e of the Scope of Work, SCOPE, stated:

All demolition debris shall become the property of the contractor. It shall be the contractor’s responsibility to remove from the site and properly dispose of all material. The contractor is required to submit disposal site permits before work begins. All disposal fees are the responsibility of the contractor.

Paragraph 8.h of the Scope of Work, SCOPE, provided:

The contractor shall coordinate with the COR and city to remove any inoperable automobiles, trucks, boats, and trailers that obstruct or impede demolition and debris removal.

Paragraph H.2 of the Special Contract Requirements, OPTION TO EXTEND SERVICES, provided:

The option provision may be exercised more than once, but the total extension of performance hereunder shall not exceed 6 months.

And paragraph H.3 of the Special Contract Requirements, OPTION TO EXTEND THE TERM OF THE CONTRACT, provided:

The total duration of this contract, including the exercise of any options under this clause, shall not exceed 6 MONTHS.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Helix Electric, Inc. v. United States
13 A.L.R. Fed. 2d 753 (Federal Claims, 2005)
Branch v. Farmers Ins. Co.
311 F.3d 1241 (Tenth Circuit, 2002)
Branch v. Farmers Insurance
311 F.3d 1241 (Tenth Circuit, 2002)
Hi-Shear Technology Corp. v. United States
53 Fed. Cl. 420 (Federal Claims, 2002)
Branch v. Farmers Ins. Co., Inc.
2002 OK 16 (Supreme Court of Oklahoma, 2002)

Cite This Page — Counsel Stack

Bluebook (online)
49 Fed. Cl. 443, 2001 U.S. Claims LEXIS 87, 2001 WL 543145, Counsel Stack Legal Research, https://law.counselstack.com/opinion/johnny-f-smith-truck-dragline-service-inc-v-united-states-uscfc-2001.