Jowett, Incorporated v. United States

234 F.3d 1365, 2000 U.S. App. LEXIS 31846, 2000 WL 1827687
CourtCourt of Appeals for the Federal Circuit
DecidedDecember 13, 2000
Docket00-5021
StatusPublished
Cited by93 cases

This text of 234 F.3d 1365 (Jowett, Incorporated v. United States) is published on Counsel Stack Legal Research, covering Court of Appeals for the Federal Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Jowett, Incorporated v. United States, 234 F.3d 1365, 2000 U.S. App. LEXIS 31846, 2000 WL 1827687 (Fed. Cir. 2000).

Opinion

DYK, Circuit Judge.

This case involves a claim for an equitable adjustment to an Army Corps of Engineers construction contract. Appellant Jowett, Incorporated (“Jowett”) seeks review of a decision by the United States Court of Federal Claims granting the government’s motion for summary judgment and denying Jowett’s cross-motion for summary judgment. Jowett, Inc. v. United States, No. 98-590C (Fed.Cl. Oct. 27, 1999). We affirm.

BACKGROUND

On June 24, 1996, the United States Army Corps of Engineers awarded a contract to Jowett to construct a three-story air-conditioned office building at Fort Bel-voir, Virginia. Each floor of the building was twenty-two feet high and contained thirty-six inch raised flooring. The contract called for the construction of occupied space directly above the raised flooring and the construction of a suspended ceiling above the occupied space.

The contract also required Jowett to construct ceiling spaces between the suspended ceiling and the raised floor or roof deck above. The ceiling spaces would house wiring for the building’s electrical systems, as well as all of the cold-air supply ducts for the building’s air conditioning system. The contract also provided that the ceiling spaces would serve as return air plenums, removing air from the air-conditioned rooms and returning it to the air handling units. Jowett constructed and installed the ductwork for the building, but subcontracted the insulation work required by the contract to Southern Insulation, Inc. (“Southern”).

At issue in this case are two sections of the contract specifications relating to the insulation of the building. Section 8.3.1, entitled “Insulation and Vapor Barrier for Cold Air Duct,” required, in pertinent part, that “[t]he following shall be insulated: a. Supply ducts[;] b. Return air duets[;] ... d. Plenums.... ” Section 3.3, entitled “Duct Insulation Installation,” provided, in pertinent part, that:

Duct installation shall be omitted on the following:
f. Return ducts in ceiling spaces. Ceiling spaces shall be defined as those spaces between the ceiling and bottom of floor deck or roof deck inside the airconditioned space insulated envelope.
j. Ceilings which form plenums_

In performing the insulation work, Southern did not insulate ceilings which formed plenums, and also did not insulate the cold-air supply ducts inside the ceiling spaces.

On August 27, 1997, the Army Corps of Engineers met with Jowett to discuss the progress of the construction. At the meeting, Jowett asked whether the contract required the insulation of cold-air supply ducts in the ceiling spaces. On September 3,1997, the Administrative Contracting Officer determined that the contract required such insulation and directed Jowett to proceed accordingly. Jowett, through its subcontractor, Southern, insulated the cold-air supply ducts in the ceiling spaces under protest.

On January 16,1998, Jowett submitted a claim to the Contracting Officer, seeking $83,727 in additional expenses incurred by Jowett and Southern in insulating the cold-air supply ducts. Jowett contended that the instruction by the Army Corps of Engineers to insulate the cold-air supply ducts constituted a change in the contract, entitling Jowett to an equitable adjustment *1367 pursuant to the “Changes” clause of the contract.

On May 28, 1998, the Contracting Officer denied the claim. She stated that “[t]he controlling provision [of the contract] is Paragraph 3.8.1 which specifies that ... insulation and vapor barrier shall be applied to cold-air supply ducts.” The Contracting Officer rejected Jowett’s interpretation of the contract, noting that “[paragraph 3.3j excludes insulation from ceilings which form plenums but, by its terms, not from the cold-air ducts placed within those ceilings.” (Emphasis in original). On July 20, 1998, Jowett commenced a timely action in the Court of Federal Claims for an equitable adjustment to the contract in the amount of $83,727, as well as attorneys’ fees and interest.

On April 27, 1999, the government moved for summary judgment, arguing that the plain language of the contract unambiguously required Jowett to insulate the cold-air supply ducts. The government stated that “paragraph 3.3.1 ... leaves no doubt that the cold-air supply ducts are required to be insulated.” The government also contended that paragraph 3.3 of the specifications did not exempt the cold-air supply ducts inside the ceiling spaces from the insulation requirement. The government argued that the exclusion in paragraph 3.3j for “ceilings which form plenums” applied only to ceilings, and not to supply ducts within the ceilings. The government further noted that the paragraph 3.3f was limited specifically to “return ducts in ceding spaces.” The government contended that had the contract drafters intended to exempt the supply ducts as well as the return ducts from requiring insulation, they would have done so. 1

On June 7, 1999, Jowett filed a cross-motion for summary judgment, arguing that the contract unambiguously exempted the cold-air supply ducts inside the ceiling plenums from the insulation requirement. Jowett further contended that the government’s interpretation of paragraph 3.3j of the specifications — that it applied only to those ceilings which form plenums — was not reasonable.

In support of its motion, Jowett submitted affidavits from executives at four construction firms — Southern, Jowett, The Poole and Kent Corporation, and Mid-Atlantic Insulation, Inc. — disagreeing with the government’s interpretation of paragraph 3.3j. The latter two affidavits also attested that it was not “standard practice in the greater Baltimore/Washington area” to insulate supply ducts in ceilings. All of the affidavits attested that there was a well-established practice of not applying duct insulation to ceilings. Each of the affidavits was executed in May 1999, nearly one year after the commencement of the action and nearly three years after the date of the contract award.

On October 27, 1999, the Court of Federal Claims granted the government’s motion for summary judgment and denied Jowett’s cross-motion, finding that the “plain language of the contract unambiguously requires the insulation pf cold air supply ducts located in the ceiling spaces.” Jowett, Inc. v. United States, No. 98-590C, slip op. at 8 (Fed.Cl. Oct. 27, 1999).

The court also declined to accord any weight to the affidavits provided by Jowett regarding alleged industry practice. The court noted that even assuming the affidavits provided by Jowett correctly stated the industry practice, such practice “cannot be used to vary or contradict the plain language of the contract.” Id. at 8 n. 10. Following the court’s grant of the government’s motion for summary judgment, Jowett timely filed this appeal.

DISCUSSION

I

We have jurisdiction over this appeal pursuant to 28 U.S.C. § 1295(a)(3). We *1368 review de novo

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Sofitc3, LLC v. United States
Federal Claims, 2025
Vigor Works, LLC
Armed Services Board of Contract Appeals, 2023
Flint v. United States
Federal Claims, 2022
State of Ohio v. United States
Federal Claims, 2021
The Boeing Company v. United States
968 F.3d 1371 (Federal Circuit, 2020)
Mw Builders, Inc. v. United States
134 Fed. Cl. 469 (Federal Claims, 2017)
Rebish v. United States
134 Fed. Cl. 308 (Federal Claims, 2017)
Stromness Mpo, LLC v. United States
134 Fed. Cl. 219 (Federal Claims, 2017)
Idaho Stage LLC v. United States
131 Fed. Cl. 727 (Federal Claims, 2017)
Hendrickson v. United States
131 Fed. Cl. 489 (Federal Claims, 2017)
Tidewater Contractors, Inc. v. United States
131 Fed. Cl. 372 (Federal Claims, 2017)

Cite This Page — Counsel Stack

Bluebook (online)
234 F.3d 1365, 2000 U.S. App. LEXIS 31846, 2000 WL 1827687, Counsel Stack Legal Research, https://law.counselstack.com/opinion/jowett-incorporated-v-united-states-cafc-2000.