Swain County v. United States

CourtUnited States Court of Federal Claims
DecidedApril 26, 2017
Docket16-531
StatusUnpublished

This text of Swain County v. United States (Swain County v. United States) is published on Counsel Stack Legal Research, covering United States Court of Federal Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Swain County v. United States, (uscfc 2017).

Opinion

In the United States Court of Federal Claims No. 16-531C Filed: April 26, 2017 NOT FOR PUBLICATION ) SWAIN COUNTY, NORTH ) CAROLINA, ) ) Breach of Contract; Rule 12(b)(1); Plaintiff, ) Subject-Matter Jurisdiction; Rule v. ) 12(b)(6); Failure to State a Claim. ) THE UNITED STATES, ) ) Defendant. )

C. Peter Dungan, Counsel of Record, Nicole D. Picard, Of Counsel, Katherine L. Morga, Of Counsel, Thomas L. McGovern, Of Counsel, Douglas P. Wheeler, Of Counsel, Hogan Lovells US LLP, Washington, DC, for plaintiff.

Tara K. Hogan, Senior Trial Counsel, Claudia Burke, Assistant Director, Robert E. Kirschman, Jr., Director, Chad A. Readler, Acting Assistant Attorney General, Commercial Litigation Branch, Civil Division, United States Department of Justice, Washington, DC, for defendant.

MEMORANDUM OPINION AND ORDER

GRIGGSBY, Judge

I. INTRODUCTION

In this breach of contract action, plaintiff, Swain County, North Carolina (“Swain County”), alleges that the United States has breached a settlement agreement by and between the Tennessee Valley Authority (the “TVA”), the United States Department of the Interior (the “DOI”) and Swain County, by failing to make certain payments required under that agreement. Compl. ¶¶ 1, 18-22. As a result of the alleged breach, Swain County seeks to recover $39,200,000.00 in monetary damages and certain declaratory relief. See generally id. The government has moved to dismiss this action for lack of subject-matter jurisdiction and for

1 failure to state a claim upon which relief can be granted, pursuant to Rules 12(b)(1) and (6) of the Rules of the United States Court of Federal Claims (“RCFC”). For the reasons discussed below, the Court GRANTS the government’s motion to dismiss.

II. FACTUAL AND PROCEDURAL BACKGROUND 1

A. Factual Background

This contract dispute arises out of the ill-fated construction of the North Shore Road in Swain County, North Carolina. Plaintiff, Swain County, is an administrative division of the State of North Carolina. Id. ¶ 1.

Swain County alleges in this action that the United States has breached a settlement agreement that it entered into with the TVA and the DOI in 2010 (the “2010 Agreement”), by failing to make certain payments required under that agreement. Id. ¶¶ 1, 18-22. Specifically, Swain County asserts breach of contract, failure to cooperate and breach of implied duty of good faith and fair dealing, and anticipatory repudiation claims against the government. Id. ¶¶ 60- 79. In addition, Swain County asserts a claim for declaratory relief regarding the availability of certain National Park Service (the "NPS") appropriations to satisfy the government's payment obligations under the 2010 Agreement. As relief, Swain County seeks to recover $39,200,000.00 in monetary damages and this declaratory relief. See generally id.

1. The Construction Of The North Shore Road

In 1929, the local government in the area now known as Swain County, NC constructed North Carolina Highway 288 (“NC 288”)—a state highway to run alongside the Little Tennessee River. Id. ¶¶ 7-8. During World War II, the TVA constructed the Fontana Dam on the Little Tennessee River. Id. ¶ 9. The Fontana Dam created Lake Fontana, which flooded NC 288 and isolated the areas located to the north of the reservoir created by the dam. Id. ¶¶ 9-10.

As a result of the flooding caused by the construction of the Fontana Dam, the State of North Carolina, Swain County, the NPS and the TVA entered into an agreement in 1943, that

1 The facts recited in this Memorandum Opinion and Order are taken from the complaint (“Compl.”), the exhibits to the complaint (“Ex.”) and the government’s motion to dismiss (“Def. Mot.”). Unless otherwise noted, the facts recited herein are undisputed.

2 required, among other things, that the DOI construct the North Shore Road, which would run through the Great Smokey Mountains National Park and provide better access to areas isolated by Lake Fontana (the “1943 Agreement”). Id. ¶ 19. The construction of the North Shore Road began in 1947 and continued through the mid-1960s. Id. ¶ 21. But, construction was hampered by piecemeal funding and challenging terrain. Id.

In 1976, the NPS suspended construction of the North Shore Road. Id. ¶ 23. Thereafter, in 1980, then-Secretary of the Interior, Cecil Andrus, agreed to support legislative efforts to require the federal government to provide a cash settlement to Swain County in exchange for retiring the 1943 Agreement and the government’s obligation to construct the North Shore Road. Id. ¶¶ 25-26. During the 1980s and 1990s, there were several unsuccessful efforts to secure the funds for this settlement. Id. ¶¶ 26-30.

In 2007, the NPS issued a Final Environmental Impact Statement Record of Decision (“ROD”) regarding the delayed construction of the North Shore Road, which determined that a monetary settlement was the preferred way to settle the federal government’s obligations to Swain County. Id. ¶ 36. The NPS did not commit to a particular settlement amount in the ROD. Id. ¶ 42; Compl. Ex. 1, at 9.

2. The 2010 Settlement Agreement

In 2010, the State of North Carolina, Swain County, the TVA, and the DOI entered into the 2010 Agreement to “settle any and all claims under the 1943 Agreement, and to extinguish and supersede the 1943 Agreement in its entirety.” Compl. Ex. 2, at 3. The 2010 Agreement provides, among other things, that Swain County would receive $4,000,000.00 from the federal government upon the enactment of the Department of Defense Appropriations Act of 2010, in lieu of the completion of the construction of the North Shore Road. Id. The 2010 Agreement further provides that an additional payment of $8,800,000.00 would be made to Swain County at a future date. Id.; Compl. ¶ 47. And so, in 2010, the DOI paid $12,800,000.00 to Swain County, pursuant to the terms of the 2010 Agreement. Compl. ¶ 50.

Specifically relevant to this dispute, the 2010 Agreement contains a provision that calls for the government to make future payments to Swain County as compensation for the

3 government’s failure to construct the North Shore Road. Specifically, Section III (2)(b) of the 2010 Agreement provides, in relevant part, that:

The United States Department of the Interior shall pay or cause to be paid to or on behalf of Swain County (as hereinafter provided) as follows: . . . Such additional sums, not to exceed thirty-nine million, two hundred thousand dollars ($39,200,000.00), as are hereafter appropriated by Act of Congress for the express purpose of effectuating the 2010 Agreement relating to the non-construction of the North Shore Road on or before December 31, 2020.

Compl. Ex. 2, at 3.

In 2010 and 2011, the DOI requested that Congress appropriate funds to make the future payments to Swain County contemplated by Section III (2)(b). Compl. ¶¶ 47, 52. But, Congress did not authorize appropriations for these future payments. Def. Mot. at 6 (citing Compl. ¶ 52). 2 Since 2012, the DOI has not requested appropriations for the future payments to Swain County. Compl. ¶ 57.

3. The GAO Opinion

On December 5, 2012, former United States Representative Heath Shuler requested that the United States Government Accountability Office (the “GAO”) issue an opinion regarding whether the NPS could use certain funds appropriated in the 2012 Appropriations Act to make the payments required under the 2010 Agreement. Compl. Ex. 3, at 1. The GAO concluded in an opinion dated December 5, 2012, that the “DOI has no obligation to use fiscal year 2012 appropriated funds to make a payment to Swain County”. Id. at 1, 4.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Merritt v. United States
267 U.S. 338 (Supreme Court, 1925)
United States v. King
395 U.S. 1 (Supreme Court, 1969)
United States v. Testan
424 U.S. 392 (Supreme Court, 1976)
United States v. Mitchell
463 U.S. 206 (Supreme Court, 1983)
Kokkonen v. Guardian Life Insurance Co. of America
511 U.S. 375 (Supreme Court, 1994)
Franconia Associates v. United States
536 U.S. 129 (Supreme Court, 2002)
Bell Atlantic Corp. v. Twombly
550 U.S. 544 (Supreme Court, 2007)
Ashcroft v. Iqbal
556 U.S. 662 (Supreme Court, 2009)
Jumah v. United States
385 F. App'x 987 (Federal Circuit, 2010)
Aboo v. United States
347 F. App'x 581 (Federal Circuit, 2009)
Fortec Constructors v. The United States
760 F.2d 1288 (Federal Circuit, 1985)
City of El Centro v. The United States
922 F.2d 816 (Federal Circuit, 1990)
McAbee Construction, Inc. v. United States
97 F.3d 1431 (Federal Circuit, 1996)
Wayne B. Harris v. Department of Veterans Affairs
142 F.3d 1463 (Federal Circuit, 1998)
Jowett, Incorporated v. United States
234 F.3d 1365 (Federal Circuit, 2000)

Cite This Page — Counsel Stack

Bluebook (online)
Swain County v. United States, Counsel Stack Legal Research, https://law.counselstack.com/opinion/swain-county-v-united-states-uscfc-2017.