Ultimate Concrete, LLC v. United States

CourtUnited States Court of Federal Claims
DecidedJanuary 10, 2019
Docket14-549
StatusPublished

This text of Ultimate Concrete, LLC v. United States (Ultimate Concrete, LLC v. United States) is published on Counsel Stack Legal Research, covering United States Court of Federal Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Ultimate Concrete, LLC v. United States, (uscfc 2019).

Opinion

In the United States Court of Federal Claims No. 14-549C (Filed: January 10, 2019)

) ULTIMATE CONCRETE, LLC, ) Keywords: Contract Disputes Act ) (“CDA”), 41 U.S.C. § 7104; Motion for Plaintiff, ) Summary Judgment, RCFC 56; Contract ) Interpretation; Critical Path; Defective v. ) Specifications. ) THE UNITED STATES OF AMERICA, ) ) Defendant. ) ) ) )

Thomas M. Keranen, Clark Hill PLC, Detroit, Michigan, for Plaintiff, with whom was Jeffrey M. Gallant, Clark Hill PLC.

James W. Poirier, Trial Attorney, Commercial Litigation Branch, Civil Division, U.S. Department of Justice, Washington, D.C., for Defendant, with whom were Claudia Burke, Assistant Director, Robert E. Kirschman, Jr., Director, and Chad A. Readler, Acting Assistant Attorney General.

OPINION AND ORDER

KAPLAN, J.

This case, which is before the Court on cross-motions for partial summary judgment, was brought under the Contract Disputes Act (“CDA”), 41 U.S.C. § 7104(b)(1), by Plaintiff Ultimate Concrete, LLC (“UC”). It arises out of disagreements between UC and the United States Section of the International Boundary and Water Commission (“IBWC”) concerning the interpretation and performance of a contract to rehabilitate, renovate, and perform new construction on an existing levee on the Rio Grande River.

UC’s motion for partial summary judgment seeks a favorable finding as to liability for two of its claims. First, it seeks summary judgment in its favor on its claim for an equitable adjustment of the contract price based on the imposition of what it contends was a new requirement that it excavate and replace materials on a part of the existing embankment, rather than leave them in place (the “REA 7-8-9” claim).1 Second, UC requests that the Court find, as a matter of law, that the survey data the government provided in the contract specifications was defective and that the government failed to take reasonable steps to cure the defects (the “Defective Specifications” claim).

Meanwhile, the government has cross-moved for partial summary judgment on two of UC’s claims: 1) the REA 7-8-9 claim; and 2) the “Early Delays” claim, which is a subpart of the Defective Specifications claim. “Early Delays” refers to alleged delays during the beginning of contract performance which—according to UC—were caused by the defective survey data provided by the government, particularly when combined with the government’s failure to correct the defects in a timely manner.

For the reasons set forth below, the government’s cross-motion is GRANTED as to the REA 7-8-9 claim, and UC’s motion is DENIED as to that claim. UC’s motion is GRANTED as to its Defective Specifications claim, and the government’s cross-motion for summary judgment as to that claim is DENIED.

BACKGROUND2

I. The Rio Grande Canalization Project and Need for Levee Rehabilitation

The contract at issue in this case involved improvements to a levee system. The subject levee is part of the Rio Grande Canalization Project, which was completed in 1943 and extends 105.6 miles along the United States–Mexico border between El Paso, Texas and Caballo Dam, New Mexico. Pl.’s Mot. for Summ. J. (“Pl.’s Mot.”) Ex. 3, ECF No. 107-2. The “Canalization System” is maintained and administered by IBWC, which also administered the contract at issue in this case. See id.

In 2008, IBWC engaged contractors who, among other things, evaluated a 31-mile portion of the Canalization System known as the Canutillo Levee Segment. See, e.g., Pl.’s Mot. Ex. 1, ECF No. 107-1. Based on their findings and conclusions, IBWC in 2010 “determined that certain reaches of the levees require[d] rehabilitation improvements in order to meet FEMA requirements for the safe containment of 100-year flood flows.” Pl.’s Mot. Ex. 3 at 1.

Accordingly, at IBWC’s request, its contractor (S&B Infrastructure, Ltd. (“S&B”)) prepared drawings and plans for a series of construction projects to rehabilitate the Canalization System. One of these projects—the “Upper Rio Grande Flood Control Project (URGFCP), Sunland Park Canutillo Levee Segment, Dona Ana County, NM and El Paso County, TX” (“the Project”)—is the subject of the contract at issue in this case. App. to Def.’s Resp. to Pl.’s Mot.

1 As discussed in greater detail below, “REA” refers to UC’s request for equitable adjustment, and “7-8-9” refers to Typical Sections 7, 8, and 9—sections of the levee as depicted in the Solicitation drawings and plans. 2 Unless otherwise indicated, the facts set forth in this section are not in dispute.

2 for Partial Summ. J., & Def.’s Cross-Mot. for Partial Summ. J. (“Def.’s App.”) at A1, ECF No. 119-1.

II. Factual Background of the REA 7-8-9 Claim

A. The Solicitation, Amended Solicitation, and UC’s Winning Bid

IBWC issued Solicitation IBM10B0004 (“the Solicitation”) in connection with the Project on August 2, 2010. Id. The estimated contract price listed was between $10 million and $20 million. Id. The scope of work, generally speaking, “consist[ed] of the rehabilitation of a portion of the Canutillo Levee System designated at Sunland Park . . . for approximately 11.82 miles.” Specification 01.19.00, Scope of Work, Def.’s App. at A129, ECF No. 119-1. “Major construction efforts” under the contract would include raising the existing levee; building new levee segments; installing a clay cap to the existing levee; building retaining walls where shown on the plans; rehabilitating “various appurtenances to the levee” (such as sluice gates, pipe crossings, connecting roadways, etc.); installing toe drains where shown on the plans; and installing new vehicular gates, road signs, and fences. Id. at A129–30.

The Solicitation referred prospective bidders to a website where they could download drawings depicting the design of the Project. Def.’s App. at A12. Included in the drawings were ten “typical” sections representing certain portions of the levee. See id. at A660–67, ECF No. 119-1; Pl.’s Mot. Ex. 35, ECF No. 107-3. Typical Sections 7, 8, and 9 (denoted with roman numerals on the drawings) are the portions of the levee that are relevant to this case.

Also relevant to the issues raised in this case is § 2.1 of specification 35.41.00, which governs the fill, drainage, and other materials the contractor would be required to furnish in connection with the construction of the levee. Subsection F of § 2.1 gave contractors the option of “re-us[ing] the salvaged material excavated from the existing levees” either “blended with other material or not.” Def.’s App. at A1273, ECF No. 119-4. In either case, § 2.1F provided, “the final product must meet or exceed all material requirements from this specification and in the general notes section of the plans.” Id.

Finally, two contract line item numbers (“CLINs”) set out in the Solicitation are also relevant to the instant dispute. CLINs 9 and 10 both relate to specification 35.41.01 (entitled “raise the levee”). CLIN 9 contained an estimate of the quantity of materials expected to be removed (“bench excavation”) and CLIN 10 supplied an estimate of the quantity of materials to be placed (“embankment”). Def.’s App. at A7–8. Payment for CLINs 9 and 10 was to be calculated by multiplying the total number of cubic yards excavated or placed, respectively, by a unit price to reach a total price. Id. at A7–8; A302, ECF No. 119-1.

B. Pre-Bid Meeting and Amended Solicitation

A pre-bid meeting and a site visit were held on August 12, 2010. Pl.’s Mot. Ex. 36, ECF No. 107-3.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

United States v. Spearin
248 U.S. 132 (Supreme Court, 1918)
Anderson v. Liberty Lobby, Inc.
477 U.S. 242 (Supreme Court, 1986)
M. Maropakis Carpentry, Inc. v. United States
609 F.3d 1323 (Federal Circuit, 2010)
Ace Constructors, Inc. v. United States
499 F.3d 1357 (Federal Circuit, 2007)
International Data Products Corp. v. United States
492 F.3d 1317 (Federal Circuit, 2007)
Medlin Construction Group, Ltd. v. Harvey
449 F.3d 1195 (Federal Circuit, 2006)
The Len Company and Associates v. The United States
385 F.2d 438 (Court of Claims, 1967)
S. S. Silberblatt, Inc. v. The United States
433 F.2d 1314 (Court of Claims, 1970)
Mingus Constructors, Inc. v. The United States
812 F.2d 1387 (Federal Circuit, 1987)
Blake Construction Company, Inc. v. The United States
987 F.2d 743 (Federal Circuit, 1993)
McAbee Construction, Inc. v. United States
97 F.3d 1431 (Federal Circuit, 1996)
Air-Sea Forwarders, Inc. v. United States
166 F.3d 1170 (Federal Circuit, 1999)
Jowett, Incorporated v. United States
234 F.3d 1365 (Federal Circuit, 2000)
The Hunt Construction Group, Inc. v. United States
281 F.3d 1369 (Federal Circuit, 2002)

Cite This Page — Counsel Stack

Bluebook (online)
Ultimate Concrete, LLC v. United States, Counsel Stack Legal Research, https://law.counselstack.com/opinion/ultimate-concrete-llc-v-united-states-uscfc-2019.