J. B. Williams Co. v. United States

450 F.2d 1379, 196 Ct. Cl. 491, 1971 U.S. Ct. Cl. LEXIS 18
CourtUnited States Court of Claims
DecidedNovember 12, 1971
DocketNo. 212-69
StatusPublished
Cited by18 cases

This text of 450 F.2d 1379 (J. B. Williams Co. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
J. B. Williams Co. v. United States, 450 F.2d 1379, 196 Ct. Cl. 491, 1971 U.S. Ct. Cl. LEXIS 18 (cc 1971).

Opinion

Per Curiam:

This case was referred to Trial Commissioner William E. Day with, directions to prepare and file his opinion on the issues of the cross-motions for summary judgment filed by the parties under the order of reference and Rule 166 (c). The commissioner has done so in an opinion and report filed on August 12, 1971, wherein such facts as are necessary to the opinion are set forth. On October 6,1971, defendant filed a motion requesting that the commissioner’s recommended conclusion of law be adopted 'by the court as the basis for its judgment pursuant to Rule 54(b) (3) (iii), no request for review of the commissioner’s opinion and recommended conclusion of law being before the court.

Since the court agrees with the opinion and recommended conclusion of the trial commissioner, it hereby grants defendant’s motion and adopts the same, as hereinafter set forth, as the basis for its judgment in this case. Therefore, plaintiff’s motion for summary judgment is granted and defendant’s cross-motion is denied. Judgment is entered for plaintiff with further proceedings stayed pursuant to Buie 167 for 90 days to afford the parties an opportunity to obtain an administrative resolution by the agency of the adjustment in the contract price commensurate to any additional amounts expended by plaintiff in adhering to the change order.

OPINION OP COMMISSIONER

Dat, Commissioner:

This case involves a Wunderlich Act (68 Stat. 81, 41 U.S.C. §§ 321-22 (1964 ed.)) review of a decision that was rendered by the General Services Administration Board of Contract Appeals under the disputes provision of contract No. GS-00S-37509. Cross-motions for summary judgment have been filed by the parties.

On April 16, 1962, the General Services Administration (GSA) contracted with Landers, Frary & Clark (hereinafter Landers)1 for the production of certain radiological survey meters, Model CD-V-715, designed for use by civil defense personnel to detect and measure high range fallout radia[495]*495tion in the event of nuclear disaster. In accordance with, the contract, and in order to begin full scale production, plaintiff submitted for the contracting officer’s approval 300 initial production units for performance testing and evaluation under the specification requirements. The contracting officer found these meters unable to meet the requirements in three vital areas — namely, spectral dependence and directionality, shock resistance, and voltage saturation of the ionization chamber — and thus withheld approval to proceed. Plaintiff subsequently redesigned its meters to conform to the specifications, thereafter claiming entitlement under the standard changes clause to an equitable adjustment in the contract price reflecting the additional costs incurred in meeting these requirements. The contracting officer denied this claim and plaintiff took timely appeal to the GSA Board of Contract Appeals (hereinafter Board). In a detailed opinion filed on September 25, 1988,2 the Board upheld the decision of the contracting officer, one member dissenting.

Stated briefly, plaintiff now argues that while there is no dispute as to the facts as found by the Board, proper weight was not accorded certain facts while other relevant facts were overlooked, which, taken together, would have led to a contrary decision. Furthermore, plaintiff attacks the Board’s interpretation of Landers’ contractual obligation with defendant. Thus plaintiff claims the Board committed reversible errors in its findings of fact and conclusions of law and that its decision is therefore not entitled to finality by authority of sections 1 and 2 of the Wunderlich Act.3 The pertinent facts of the case are as set forth below.

In 1960 the Federal Supply Service (a branch of GSA) issued an invitation for bids to furnish it with certain radiological survey meters “* * * in accordance with Office of [496]*496Civil Defense Mobilization Standard Item Specification CD-V-715 dated July 1, 1960 * * Included among tbe bidders were Anton Electronic Laboratories, Inc. (soon after bought out by Lionel Electronics Laboratories, and hereinafter Lionel), and plaintiff. As part of the bid requirements, preaward samples were submitted for testing for such things as accuracy, stability, temperature, atmospheric pressure, immersion and light sensitivity, and spectral dependence. While it is not clear to whom the contract was formally awarded (Anton or Lionel), the latter, whose samples were found to be in compliance with the above-mentioned performance characteristics, actually manufactured the original Government contracted CD-V-715 survey meters referred to as Lionel Model No. 1.

The aforesaid specification called for (among other things) testing of three of the initial 300 production units taken at random against certain performance requirements set forth in 21 separate specification paragraphs. In addition, another paragraph required the contractor to certify and, if requested, furnish test data indicating that certain components of the CD-V-715 had been tested for and found to be in conformance with designated specification paragraphs, most notably the one relating to the 95 percent voltage saturation requirement for the heart of the instrument, the ionization chamber. While the record does not indicate whether Lionel tested these units with respect to voltage saturation or whether the mandatory certificate was in fact issued, it appears as though the resulting test data confirmed Lionel’s adherence to the specification requirements because Lionel subsequently produced and the Government thereafter accepted 11,729 Model No. 1 units, deliveries being completed on March 28,1962.

Prior to the award of the Landers contract, but subsequent to the issuance of the invitation for bids for that contract, the Government entered into a second agreement with Lionel to produce approximately 14,000 additional CD-V-715 survey meters. These units were known as Lionel Model No. 1A and were to be “* * * equivalent to OCDM Model 1 as manufactured by Lionel Electronic Laboratories and in ac[497]*497cordance with. Office of Civil Defense Mobilization Standard Item Specification CD-V-715 dated July 1, 1960 * * 4

On March 2,1962, invitations for bids were dispatched by the Federal Supply Service for the production of another 63,185 CD-V-715 survey meters, as before, to be “equivalent to OCDM Model 1 as manufactured by Lionel Electronic Laboratories and in accordance with Office of Civil Defense Mobilization Standard Item Specification CD-V-715 dated July 1, 1960 * * Attached to said invitation was a notice to prospective bidders pointing out 15 significant changes from the initial CD-V-715 invitations, included among which were the availability of sample instruments for bidders in the present invitation, deletion of the preproduction model requirement, and the availability of model instruments for initial testing and inspection. Paragraph 25 of the Terms and Conditions of the said invitation, making sample instruments available to contract bidders, also contained the following language:

Samples of instruments specified in this Invitation for Bids, will be made available to prospective bidders upon request * * *
if* # i|i % #

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Amatea/Grimberg JV
Armed Services Board of Contract Appeals, 2023
Metric Construction Co. v. United States
80 Fed. Cl. 178 (Federal Claims, 2008)
Navcom Defense Electronics, Inc. v. England
53 F. App'x 897 (Federal Circuit, 2002)
North Star Alaska Housing Corp. v. United States
39 Cont. Cas. Fed. 76,607 (Federal Claims, 1993)
C. Sanchez and Son, Incorporated v. United States
6 F.3d 1539 (Federal Circuit, 1993)
Aleman Food Services, Inc. v. The United States
994 F.2d 819 (Federal Circuit, 1993)
Blake Construction Company, Inc. v. The United States
987 F.2d 743 (Federal Circuit, 1993)
Troise v. United States
36 Cont. Cas. Fed. 75,904 (Court of Claims, 1990)
Al Johnson Construction Co. v. United States
36 Cont. Cas. Fed. 75,850 (Court of Claims, 1990)
Zinger Construction Co., Inc. v. The United States
807 F.2d 979 (Federal Circuit, 1986)
Utility Contractors, Inc. v. United States
32 Cont. Cas. Fed. 73,446 (Court of Claims, 1985)
Teledyne Lewisburg v. The United States
699 F.2d 1336 (Federal Circuit, 1983)
Astro-Space Laboratories, Inc. v. United States
470 F.2d 1003 (Court of Claims, 1972)

Cite This Page — Counsel Stack

Bluebook (online)
450 F.2d 1379, 196 Ct. Cl. 491, 1971 U.S. Ct. Cl. LEXIS 18, Counsel Stack Legal Research, https://law.counselstack.com/opinion/j-b-williams-co-v-united-states-cc-1971.