Gaston & Associates, Inc. v. United States

38 Cont. Cas. Fed. 76,429, 27 Fed. Cl. 243, 1992 U.S. Claims LEXIS 156, 1992 WL 360172
CourtUnited States Court of Federal Claims
DecidedDecember 3, 1992
DocketNo. 91-910C
StatusPublished
Cited by6 cases

This text of 38 Cont. Cas. Fed. 76,429 (Gaston & Associates, Inc. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Federal Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Gaston & Associates, Inc. v. United States, 38 Cont. Cas. Fed. 76,429, 27 Fed. Cl. 243, 1992 U.S. Claims LEXIS 156, 1992 WL 360172 (uscfc 1992).

Opinion

MODIFIED ORDER

MOODY R. TIDWELL, III, Judge.

This case is before the court on defendant’s motion for summary judgment and plaintiff’s cross-motion for partial summary judgment. For the reasons set forth below, the court grants plaintiff’s motion and denies defendant’s motion.

FACTS

On February 15, 1989, the United States Army Corps of Engineers (“the Corps”) issued an. invitation for bids for the construction of three Battalion Headquarters Buildings at Fort Wainwright, Alaska. Work included the construction of two new one-story 14,840 square foot concrete ma[245]*245sonry buildings and the alteration of an existing 2,577 square foot building with construction of a 5,140 square foot concrete masonry addition to the building. The three buildings were at different locations on Fort Wainwright. The Invitation for Bids (“IFB”) permitted the Corps to award the individual building projects to different bidders, or to award all three projects to a single bidder.

On March 28, 1989, the Corps held its bid opening for this contract, and on April 17, 1989, awarded the entire fixed-price construction contract to Gaston & Associates, Inc. (“Gaston”) for a total price of $5,793,-000. 00. The Corps gave its notice to proceed on April 28, 1989, acknowledged May 1, 1989. Also on May 1, 1989, Gaston submitted a network analysis system and bar chart which displayed concurrent construction of all three buildings.

The parties’ dispute centers on the interpretation of two contract clauses addressing the Contractor Quality Control (“CQC”) System. Gaston based its bid on the project on its plans to designate the project superintendent as the CQC System Manager. Gaston also planned to have one CQC inspector monitor the entire project, i.e. construction of all three buildings. Gaston submitted its Quality Control Plan (“the Plan”) to the Corps on May 10, 1989. The Plan named John Ballard as CQC System Manager and project superintendent, and named Russell Lowney as the sole CQC staff person, i.e. the sole quality control inspector.

The Corps orally rejected the Plan on May 15, 1989, stating that the project superintendent could not act as the CQC System Manager, and that a full-time CQC inspector would be required for each of the three buildings. After revisions and discussions about the staffing of the CQC System, Gaston submitted a revised Quality Control Plan assigning the project superintendent and CQC System Manager positions to two individuals, and designating three CQC inspectors. On August 7, 1989, the Corps accepted this Plan, submitted on July 6, 1989.

On August 21, 1989, Gaston filed a Request for Contracting Officer’s decision on its claim for an equitable adjustment of $147,958.00, the cost incurred in hiring the three additional CQC personnel not contemplated at the time of the project bid.1 The Contracting Officer issued a decision denying the claim on April 11, 1990. Subsequently, Gaston filed suit in the United States Claims Court2 on February 12,1991, seeking review of the Contracting Officer’s final decision.

DISCUSSION

This case is before the court on defendant’s motion for summary judgment and plaintiff’s cross-motion for partial summary judgment. Summary judgment is properly granted when there are no genuine issues of material fact and the movant is entitled to judgment as a matter of law. Anderson v. Liberty Lobby, Inc., 477 U.S. 242, 248-49, 106 S.Ct. 2505, 2510, 91 L.Ed.2d 202 (1986); Mingus Constructors, Inc. v. United States, 812 F.2d 1387, 1390 (Fed.Cir.1987) (citing Armco, Inc. v. Cyclops Corp., 791 F.2d 147, 149 (Fed.Cir.1986)). In considering a motion for summary judgment, the evidence must be viewed, and inferences drawn, in a light most favorable to the non-moving party. Litton Indus. Prod., Inc. v. Solid State Sys. Corp., 755 F.2d 158, 163 (Fed.Cir.1985); D.L. Auld Co. v. Chroma Graphics Corp., 714 F.2d 1144, 1146 (Fed.Cir.1983).

1. CQC System Manager Claim

The dispute in this case involves issues of contract interpretation arising [246]*246from two contractor quality control organization requirements contained in the contract. Interpretation of a contract is a question of law. American Satellite Co. v. United States, 20 Cl.Ct. 710, 713 (1990) (citing Tilley Constructors & Engineers, Inc. v. United States, 15 Cl.Ct. 559, [563] (1988)). The first issue pertains to Clause SC-30(4)(a), entitled “CQC System Manager,” which sets forth the requirements for the contractor’s quality control manager, as follows:

The Contractor shall identify an individual, within his organization at the site of the work, who shall be responsible for overall management of CQC and have the authority to act in all CQC matters for the Contractor. This CQC System Manager shall be acceptable to the CO [the Contracting Officer] or COR.

At the time it bid on the Battalion Headquarters project, Gaston interpreted this clause to mean that the individual so named as the CQC System Manager could perform other duties on the project as well. Gaston intended to have its project superintendent simultaneously fulfill the function of CQC System Manager. Only after the Corps rejected this plan did Gaston hire another individual to act solely as the CQC System Manager.3

Clause 58 of the contract, FAR 52.236-6, sets forth the requirements of contractor superintendence as follows:

At all times during performance of this contract and until the work is completed and accepted, the Contractor shall directly superintend the work or assign and have on the work [site] a competent superintendent who is satisfactory to the Contracting Officer and has authority to act for the Contractor.

This clause makes clear that Gaston was to have someone supervising the entire Battalion Headquarters project. Read along with SC-30(4)(a), it suggests that the two sets of duties are to be held by two separate individuals, as defendant contends. However, nothing in these clauses, nor in any other clause presented to the court, prohibits the CQC System Manager from simultaneously functioning as the project superintendent.4 Moreover, neither party has submitted credible evidence establishing prevailing industry practice as to the CQC System Manager’s simultaneous performance of additional duties.

Plaintiff has submitted excerpts from the Corps’ Guide Specifications which show that the Corps is capable of writing a clear and unambiguous contractor quality control organization clause. Specifically, the Guide states:

3.4.2.2 CQC System Manager
Note: Insert desired requirements. Select appropriate options. The specifier must evaluate the project to determine the level of CQC required and select options accordingly.
* SjS ¡}t i}! Sj! *

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Keeter Trading Co. v. United States
79 Fed. Cl. 243 (Federal Claims, 2007)
Information Systems & Networks Corp. v. United States
68 Fed. Cl. 336 (Federal Claims, 2005)
P.R. Burke Corp. v. United States
47 Fed. Cl. 340 (Federal Claims, 2000)
Fort Myer Construction Corp. v. United States
43 Cont. Cas. Fed. 77,425 (Federal Claims, 1999)
Conoco Inc. v. United States
35 Fed. Cl. 309 (Federal Claims, 1996)
H.B. Zachry Co. v. United States
38 Cont. Cas. Fed. 76,502 (Federal Claims, 1993)

Cite This Page — Counsel Stack

Bluebook (online)
38 Cont. Cas. Fed. 76,429, 27 Fed. Cl. 243, 1992 U.S. Claims LEXIS 156, 1992 WL 360172, Counsel Stack Legal Research, https://law.counselstack.com/opinion/gaston-associates-inc-v-united-states-uscfc-1992.