Goodloe Marine, Inc.

CourtArmed Services Board of Contract Appeals
DecidedJanuary 27, 2022
DocketASBCA No. 62106, 62446
StatusPublished

This text of Goodloe Marine, Inc. (Goodloe Marine, Inc.) is published on Counsel Stack Legal Research, covering Armed Services Board of Contract Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Goodloe Marine, Inc., (asbca 2022).

Opinion

ARMED SERVICES BOARD OF CONTRACT APPEALS

Appeals of - ) ) Goodloe Marine, Inc. ) ASBCA Nos. 62106, 62446 ) Under Contract No. W9126G-18-C-0071 )

APPEARANCES FOR THE APPELLANT: Michael H. Payne, Esq. Cohen Seglias Pallas Greenhall & Furman PC Philadelphia, PA

Casey J. McKinnon, Esq. Cohen Seglias Pallas Greenhall & Furman PC Washington, DC

APPEARANCES FOR THE GOVERNMENT: Michael P. Goodman, Esq. Engineer Chief Trial Attorney Clark Bartee, Esq. Engineer Trial Attorney U.S. Army Engineer District, Galveston

OPINION BY ADMINISTRATIVE JUDGE MELNICK GRANTING THE GOVERNMENT’S MOTION FOR SUMMARY JUDGMENT

Appellant, Goodloe Marine, Inc., of Wimauma, Florida (Goodloe), was awarded a contract to perform pipeline dredging by the United States Army Corps of Engineers (Corps or government). The government eventually terminated Goodloe for default for failing to dredge at the required production rate. Goodloe appeals from the default, as well as from a denial by the government of its claim for additional time it alleges should be recognized due to weather delays. The government has moved for summary judgment, which we grant.

STATEMENT OF FACTS (SOF) FOR PURPOSES OF THE MOTION

I. Undisputed Facts

The following facts have not been shown to be in genuine dispute.

1. On September 29, 2018, the government awarded the firm fixed-price contract identified above to Goodloe. The contract was for pipeline dredging of the Gulf Intracoastal Waterway around Galveston, Texas. The contract estimated that 630,000 cubic yards of material would be removed. (R4, tab 1 at 4-10, tab 2) Among the standard Federal Acquisition Regulation (FAR) clauses incorporated by reference was FAR 52.249-10, DEFAULT (FIXED-PRICE CONSTRUCTION) (APR 1984) (R4, tab 1 at 16). In addition to that provision, the contract contained section 3.1.3, entitled “Default Terms.” It provided that:

Failure of the Contractor to comply with the requirements of the Contract will be grounds for a determination, by the Contracting Officer, that the Contractor is not prosecuting the work with sufficient diligence to ensure completion within the time specified in this Contract. Upon making this determination, the Contracting Officer may terminate the Contractor’s right to proceed with the work, or separable parts of it, in accordance with the default terms of the Contract.

(R4, tab 1 at 173)

2. The contract required Goodloe to begin performing 10 calendar days after receiving a notice to proceed and complete performance 130 calendar days later. The government issued the notice to proceed on October 17, 2018, establishing February 24, 2019, as the contract completion date. (R4, tab 1 at 8, tab 3)

3. The contract imposed strict capacity requirements upon Goodloe. Section 1.15.2 mandated that “[t]he effective production rate of the dredge plant shall not be less than 360,000 cubic yards per month” and “[n]o reduction in the capacity of the dredge equipment and attendant plant employed to execute the work is to be made except by written direction of the Contracting Officer.” The capacity would be measured from actual performance. (R4, tab 1 at 133) Dredging 360,000 cubic yards per month (30 days) requires an average of 12,000 cubic yards per day.

4. To achieve the contract’s requirements, Goodloe informed the government during a pre-award survey that it intended to use two dredges. One was Bettie G and the other was Perseverance. (Gov’t statement of undisputed material facts ¶ 2; app. resp. ¶ 2) Goodloe said that Bettie G’s average production rate ranged between 6,000 and 8,000 cubic yards per day. Goodloe stated that Perseverance could achieve between 8,000 and 10,000 cubic yards per day. Goodloe also noted that it had a third dredge, Reliable, available to assist if necessary to complete performance on time. Goodloe represented that all three dredges were sitting idle at its yard and could be moved within days to the project site once it received a notice to proceed. Goodloe confirmed that it understood that the minimum amount of material that had to be dredged in a month was 360,000 cubic yards. It represented that Bettie G would start dredging about 21 days after the notice to proceed and Perseverance would arrive about

2 two to three weeks later and dredge concurrently with Bettie G at a rate that would achieve the minimum production. (R4, tab 349 at 1409, 1411, tab 350 at 1420)

5. The record contains a series of forms purporting to be Goodloe’s Contractor Quality Control (QCR) Reports. However, no author is identified and their certification lines are blank. Beginning with the form dated November 6, 2018, a series of them indicate that Goodloe encountered weather delays on a total of 30 different days between October 18 and December 29, 2018. Many of the forms attached calendars for October, November, and December 2018 that also supposedly show the reported adverse weather. The calendars appear to be from an internet weather application (“app”), but Goodloe does not identify the source. There is also no indication of the geographical location they purport to describe, except the December calendar is marked Bay City, Texas. We judicially notice that location is over 70 miles on a straight line from Galveston. 1 (R4, tabs 196, 198, 200, 202, 204, 212, 214, 227, 237, 239, 241, 243, 257, 275, 277, 281, 283, 293, 295, 297, 301, 303, 305, 307)

6. Goodloe began dredging on December 17, 2018, with Bettie G. (R4, tab 220; gov’t statement of undisputed material facts ¶ 15; app. resp. ¶ 15; app. supp. R4, tab 30 (Native) at 1391 (production rate tab)).

7. On January 10, 2019, the government sent a letter of concern to Goodloe’s president in Florida regarding its ability to timely complete the contract. The government indicated that Goodloe’s average dredging rate of 2,011 cubic yards per day had placed it three weeks behind schedule and was unacceptable. The government directed Goodloe to submit an updated schedule by January 15, 2019. (R4, tab 170)

8. Goodloe’s president, Ms. Bettie Goodloe, responded to the government on January 15, 2019. She indicated that Goodloe had experienced “weather days” and “vendor delays” that delayed the arrival of Bettie G and Perseverance to the site. She stated that Goodloe had provided documentation of the weather, and expressed the belief that the conditions Goodloe encountered justified a later completion date. She also represented that Perseverance would arrive on or about January 22, 2019. (R4, tab 161)

9. On February 11, 2019, the contracting officer issued a show cause notice to Goodloe notifying it that the government was considering terminating the contract for default. The government observed that Bettie G did not start dredging until December 17, 2018, 65 days after the notice to proceed. Perseverance did not arrive until January 23 and experienced operational problems. Goodloe’s invoice for December 15, 2018 through January 23, 2019, showed less than 35,000 cubic yards removed, well below the contractual requirement. (R4, tab 101)

1 See FED. R. EVID. 201. 3 10. Goodloe responded to the show cause letter on February 15, 2019. Goodloe stated that it had been delayed by weather since the notice to proceed. It characterized the amount of rainfall during the previous several months as unusual, saying anyone who lives or works in the area knows that. It explained that the conditions had hampered its assembly and placement of pipelines, emphasizing its delays commenced before dredging began. Goodloe also represented that other Corps projects in the area had been delayed by weather and that the government’s survey party had declined to work on Goodloe’s project due to weather on two occasions. It also stated that it had recently been delayed for two days by fog.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

First Nat. Bank of Ariz. v. Cities Service Co.
391 U.S. 253 (Supreme Court, 1968)
Anderson v. Liberty Lobby, Inc.
477 U.S. 242 (Supreme Court, 1986)
Darwin Construction Co., Inc. v. United States
811 F.2d 593 (Federal Circuit, 1987)
Dairyland Power Cooperative v. United States
16 F.3d 1197 (Federal Circuit, 1994)
Dcx, Inc. v. William J. Perry, Secretary of Defense
79 F.3d 132 (Federal Circuit, 1996)
Dj Manufacturing Corporation v. United States
86 F.3d 1130 (Federal Circuit, 1996)
Labatte v. United States
899 F.3d 1373 (Federal Circuit, 2018)
Dobyns v. United States
915 F.3d 733 (Federal Circuit, 2019)
Cape Ann Granite Co. v. United States
100 Ct. Cl. 53 (Court of Claims, 1943)
Broome Construction, Inc. v. United States
492 F.2d 829 (Court of Claims, 1974)
Daydanyon Corp. v. United States Defense Logistics Agency
673 F. App'x 997 (Federal Circuit, 2017)

Cite This Page — Counsel Stack

Bluebook (online)
Goodloe Marine, Inc., Counsel Stack Legal Research, https://law.counselstack.com/opinion/goodloe-marine-inc-asbca-2022.