Alvarado Construction, Inc. v. United States

39 Cont. Cas. Fed. 76,708, 32 Fed. Cl. 184, 1994 U.S. Claims LEXIS 195, 1994 WL 539324
CourtUnited States Court of Federal Claims
DecidedOctober 4, 1994
DocketNo. 92-599C
StatusPublished

This text of 39 Cont. Cas. Fed. 76,708 (Alvarado Construction, Inc. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Federal Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Alvarado Construction, Inc. v. United States, 39 Cont. Cas. Fed. 76,708, 32 Fed. Cl. 184, 1994 U.S. Claims LEXIS 195, 1994 WL 539324 (uscfc 1994).

Opinion

OPINION

ANDEWELT, Judge.

In this government contract action brought pursuant to the Contract Disputes Act (CDA), 41 U.S.C. §§ 601-613, plaintiff, Alvarado Construction, Inc., seeks compensation for costs and expenses incurred by its subcontractor, Burdco Environmental, Inc. (Burdco), for asbestos abatement work performed under a contract plaintiff entered with the General Services Administration (GSA). This action is presently before the court on defendant’s motion to dismiss the complaint pursuant to RCFC 12(b)(1) for lack of subject matter jurisdiction. Defendant contends that this court lacks jurisdiction over the instant action because prior to instituting suit, plaintiff did not submit to the contracting officer a certified claim that satisfies the requirements of Section 605 of the CDA and related regulations and contract 'provisions. For the reasons set forth below, defendant’s motion to dismiss is granted.

[185]*185I.

The contract in issue covered the renovation of the Federal Building/Customs House in Denver, Colorado.1 The contract provided for certain asbestos abatement work which plaintiff subcontracted to Burdco. During performance of the contract, the parties discovered that more asbestos abatement had to be performed than originally anticipated in the contract and, as a result, the GSA issued five unilateral orders directing Burdco, through plaintiff, to perform the additional asbestos abatement work. On or about February 19, 1988, the GSA terminated for the convenience of the government certain portions of the contract, including that portion relating to asbestos abatement.

On December 21, 1988, plaintiff submitted to the contracting officer a termination for convenience settlement proposal, entitled “Interim Proposal No. 1,” seeking a total termination payment of $871,942. This interim proposal did not include costs relating to Burdco’s asbestos abatement work. On February 15, 1989, plaintiff submitted a “second and final proposal” seeking a total termination payment of $1,663,803. This final proposal included settlement proposals for the work of various subcontractors, including $336,914 for the asbestos abatement work performed by Burdco. The last paragraph of the cover letter accompanying the final proposal contained a certification signed by plaintiffs president, Linda G. Alvarado.

After the GSA completed an audit, the parties entered into negotiations concerning plaintiffs final proposal. Because the Inspector General had initiated an investigation into Burdco’s activities with respect to the contract, the initial negotiations did not cover Burdco’s costs. With the exception of Burd-co’s costs and a question concerning CDA interest, the parties ultimately reached an agreement as to all costs claimed in plaintiffs final proposal.

After the Inspector General completed its investigation of Burdco and declined to take any action, the parties commenced negotiations as to Burdeo’s costs. After the parties failed to reach an agreement, the GSA issued a unilateral contract change order pursuant to the contract’s termination for convenience clause, Federal Acquisition Regulation (FAR), 52.249-2, 48 C.F.R. § 52.249-2, which reflected the final amount the GSA believed it owed plaintiff for Burdco’s costs. The cover letter accompanying the change order stated that “[t]his is the final decision of the Contracting Officer and is made in accordance with the disputes clause____ In lieu of appealing to the General Services Board of Contract Appeals, you may bring an action directly in the U.S. [Court of Federal Claims] within 12 months of the date you receive this decision.” On September 1, 1992, plaintiff filed its complaint in this court seeking $200,-000 for Burdco’s asbestos abatement work.

II.

As a jurisdictional prerequisite to a Section 609 CDA suit in this court, a contractor must first submit to the contracting officer a claim that satisfies the requirements of Section 605 of the CDA. W.M. Schlosser Co. v. United States, 705 F.2d 1336, 1338-39 (Fed.Cir.1983). Defendant argues that this court lacks jurisdiction over the instant action because plaintiffs February 15, 1989, final proposal does not constitute a proper CDA claim for the asbestos abatement work performed by Burdco.

While the CDA does not define the term “claim,” the contract’s disputes clause, FAR 52.233-1, provides, in pertinent part:

(c) “Claim,” as used in this clause, means a written demand or written assertion by one of the contracting parties seeking, as a matter of right, the payment of money in a sum certain ... arising under or relating to this contract____ A voucher, invoice, or other routine request for payment that is not in dispute when submitted is not a claim under the [CDA],

In Dawco Constr., Inc. v. United States, 930 F.2d 872, 878 (Fed.Cir.1991), the Court of Appeals for the Federal Circuit interpreted this same language as generally requiring that a dispute exist between the parties prior to the filing of a claim. The court explained, as follows:

[186]*186Clearly, the FAR mandates that, inter alia, a [CDA] claim must seek payment of a sum certain as to which a dispute exists at the time of submission.

Similarly, the contract’s disputes clause ... states that a “request for payment that is not in dispute when submitted is not a claim for purposes of the [CDA].” The language is not ambiguous, and means what it says: A contractor and the government contracting agency must already be in dispute over the amount requested. Unilateral cost proposals or correspondence suggesting disagreement during negotiations, while they may ultimately lead to a dispute, do not for purposes of the [CDA], satisfy the clear requirement that the request be in dispute. Mayfair Construction Co. v. United States, 841 F.2d 1576,1577 (Fed.Cir.), cert, denied, 488 U.S. 980, 109 S.Ct. 528, 102 L.Ed.2d 560 (1988) (“It is beyond cavil that under this clause, no claim exists unless it involves a dispute.”).

(Emphasis in original.)

Defendant argues that under Dawco, plaintiffs final proposal cannot constitute a claim because it entails a unilateral cost proposal which was not in dispute at the time the proposal was submitted. Defendant is correct in so far as it contends that the final proposal was not in dispute at the time it was submitted. Plaintiff submitted its final proposal pursuant to the contract’s termination for convenience clause, FAR 52.249-2, which provides, in pertinent part:

(d) After termination, the Contractor shall submit a final termination settlement proposal to the Contracting Officer in the form and with the certification prescribed by the Contracting Officer____

(e) Subject to paragraph (d) above, the Contractor and the Contracting Officer may agree upon the whole or any part of the amount to be paid because of the ter-mination____

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Christianson v. Colt Industries Operating Corp.
486 U.S. 800 (Supreme Court, 1988)
Fidelity Construction Company v. The United States
700 F.2d 1379 (Federal Circuit, 1983)
United States v. Turner Construction Company
827 F.2d 1554 (Federal Circuit, 1987)
Mayfair Construction Company v. The United States
841 F.2d 1576 (Federal Circuit, 1988)
Dawco Construction, Inc. v. The United States
930 F.2d 872 (Federal Circuit, 1991)
Donald M. Drake Co. v. United States
34 Cont. Cas. Fed. 75,330 (Court of Claims, 1987)
Paul E. Lehman, Inc. v. United States
673 F.2d 352 (Court of Claims, 1982)
Skelly v. United States
685 F.2d 414 (Court of Claims, 1982)
W.M. Schlosser Co. v. United States
705 F.2d 1336 (Federal Circuit, 1983)

Cite This Page — Counsel Stack

Bluebook (online)
39 Cont. Cas. Fed. 76,708, 32 Fed. Cl. 184, 1994 U.S. Claims LEXIS 195, 1994 WL 539324, Counsel Stack Legal Research, https://law.counselstack.com/opinion/alvarado-construction-inc-v-united-states-uscfc-1994.