Blake Construction Co. v. United States

38 Cont. Cas. Fed. 76,537, 28 Fed. Cl. 672, 1993 U.S. Claims LEXIS 90, 1993 WL 254874
CourtUnited States Court of Federal Claims
DecidedJuly 9, 1993
DocketNo. 471-88C
StatusPublished
Cited by8 cases

This text of 38 Cont. Cas. Fed. 76,537 (Blake Construction Co. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Federal Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Blake Construction Co. v. United States, 38 Cont. Cas. Fed. 76,537, 28 Fed. Cl. 672, 1993 U.S. Claims LEXIS 90, 1993 WL 254874 (uscfc 1993).

Opinion

OPINION

HORN, Judge.

This case is before the court on the defendant’s motion for summary judgment. The plaintiff, Blake Construction Company (Blake), a Delaware Corporation, brought this action pursuant to the Contract Disputes Act of 1978, 41 U.S.C. § 609(a) (1982) (CDA). The plaintiff alleges that the defendant, through employees at the United States Department of the Navy (Navy), directed it to perform work which constitutes a constructive change to the contract. After the plaintiff requested an equitable adjustment to the contract price on August 11, 1987, the contracting officer issued a final decision denying the plaintiff’s claim on the basis that the claim had not been properly certified.

In the complaint filed with this court,1 plaintiff alleges that the Navy caused a change to the scope of the contract when it directed the plaintiff to install rigid steel conduit instead of PVC conduit when installed underground.2 Plaintiff further alleges that, on or about January 23, 1987, plaintiff transmitted a certified cost proposal in the amount of $327,231.00 to the Navy, followed by two additional letters from the plaintiff to the defendant, dated March 27, 1987 and June 12, 1987.3 In [675]*675response to the complaint, the defendant filed an answer requesting dismissal of the complaint, asserting that the plaintiff is not entitled to the relief requested. Rather than file a motion to dismiss, however, defendant filed a motion requesting summary judgment asserting that the Navy had made no changes to the contract requirements and, therefore, plaintiff is not entitled to an equitable adjustment to the contract price.

Oral argument was heard by the court after submission of briefs by both parties. Subsequent to the oral argument, because neither party had addressed the issue of the adequacy of the certification, the court requested additional submissions on the certification issue. Both parties submitted extensive briefings in response to the court’s request. In its second supplemental brief, the defendant requested that the court dismiss the case for lack of jurisdiction, but, again, did not file a motion to this effect.

After careful consideration of the facts, the papers submitted by both parties, the record in the case, the arguments presented at oral argument, and for the reasons discussed below, the defendant’s motion for summary judgment is GRANTED.

FACTS

On or about June 15, 1983, the defendant, acting through the Navy, awarded contract No. N62474-81-C-8799 to the plaintiff, Blake, to perform construction work on the Main Hospital Complex Center at the Naval Regional Medical Center in San Diego, California. The contract was for a fixed price in the amount of $98,411,-000.00. On July 25, 1983, Blake subcontracted with Steiny to perform all electrical work on the project. The Steiny-Blake subcontract encompassed Blake’s contract with the Navy and incorporated specification sections by reference, including sections 16301 and 16402.

According to plaintiff, in April 1984, a dispute arose regarding the type of conduit to be installed underground. The complaint indicates that:

On or about April 25, 1984, and continuing thereafter to May 17, 1984, BLAKE, STEINY, and the NAVY attended meetings and/or exchanged correspondence regarding STEINY’S intention to install PYC conduit for branch circuit directly in the earth underneath slab on grade at the PROJECT.

The relevant portions of the contract are as follows:

SECTION 16301

UNDERGROUND ELECTRICAL WORK PART 1 — GENERAL

1.2 GENERAL REQUIREMENTS: Materials and installation shall conform to Section 16402, “Interior Wiring Systems”, with the additions and modifications specified herein. The work includes furnishing of labor, material, tools, and equipment necessary for and incidental to the installation of underground electrical work in accordance with the applicable requirements of NFPA 70 and of this specification. Materials and equipment to be furnished under this contract shall be the current design products of manufacturers regularly engaged in production of such equipment and shall be listed [676]*676by Underwriters’ Laboratories, Inc. (UL) or approved by Factory Mutual Systems Laboratories (F.M.)

PART 2 — PRODUCTS

2.1 MATERIALS AND EQUIPMENT: Materials and equipment shall conform to the respective specifications and standards and to the specifications herein. Electrical ratings shall be as indicated.
2.1.1 Conduit:
2.1.1.1 Rigid Metal Conduit, P.V.C. Coated: NEMA RN 1, type A20.
2.1.1.2 Fiber Conduit: UL 543, fiber conduit Type I.
SECTION 16402
INTERIOR WIRING SYSTEMS
2.1 MATERIALS AND EQUIPMENT: Materials and equipment shall conform to the respective specifications and standards and to the specifications herein. Electrical ratings shall be as indicated.
2.1.1 Conduit:
2.1.1.1 Rigid Metal Conduit: U.L. 6, galvanized threaded.
2.1.1.2 Rigid Metal Conduit, P.V.C. Coated: NEMA RN 1, galvanized, threaded.

The plaintiff and the defendant disagree as to how these two key sections of the contract should be read in order to determine the applicable contract requirements. Plaintiff maintains that only section 16301 applies to the installation of underground branch circuits and should be read independent of section 16402. According to plaintiff: “Thus, under the express terms of the contract, underground electrical conduit could be either rigid metal conduit, PVC coated or fiber conduit.” Plaintiff further maintains that PVC conduit is recognized in the industry as an acceptable substitute for fiber conduit for underground installations. Therefore, plaintiff argues PVC conduit, not rigid metal conduit, should have been considered acceptable under the contract. The defendant, however, contends that because section 16301 references section 16402, both sections should be read together, to reach a different result. According to defendant: “Thus, under the express terms of the contract, underground electrical conduit could be either galvanized rigid metal conduit, rigid metal conduit with a PVC coating, or fiber conduit.” According to defendant, the contract did not allow PVC conduit to be used.

The disagreement regarding which type of conduit should be used to install branch circuits seems to have originated with the subcontractor (Steiny) early in the contract relationship, but the record documents the first discussion of the issue at a meeting on April 25, 1984.4

Free access — add to your briefcase to read the full text and ask questions with AI

Related

K-Con Building Systems, Inc. v. United States
107 Fed. Cl. 571 (Federal Claims, 2012)
M. Maropakis Carpentry, Inc. v. United States
84 Fed. Cl. 182 (Federal Claims, 2008)
Viromed Laboratories, Inc. v. United States
62 Fed. Cl. 206 (Federal Claims, 2004)
Comtrol, Inc. v. United States
49 Fed. Cl. 294 (Federal Claims, 2001)
Nematollahi v. United States
38 Fed. Cl. 224 (Federal Claims, 1997)
Barseback Kraft AB v. United States
41 Cont. Cas. Fed. 77,040 (Federal Claims, 1996)
United Sales, Inc. v. United States
40 Cont. Cas. Fed. 76,842 (Federal Claims, 1995)

Cite This Page — Counsel Stack

Bluebook (online)
38 Cont. Cas. Fed. 76,537, 28 Fed. Cl. 672, 1993 U.S. Claims LEXIS 90, 1993 WL 254874, Counsel Stack Legal Research, https://law.counselstack.com/opinion/blake-construction-co-v-united-states-uscfc-1993.