Esprit Corp. v. United States

32 Cont. Cas. Fed. 73,069, 6 Cl. Ct. 546, 1984 U.S. Claims LEXIS 1259
CourtUnited States Court of Claims
DecidedNovember 15, 1984
DocketNo. 95-83C
StatusPublished
Cited by12 cases

This text of 32 Cont. Cas. Fed. 73,069 (Esprit Corp. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Esprit Corp. v. United States, 32 Cont. Cas. Fed. 73,069, 6 Cl. Ct. 546, 1984 U.S. Claims LEXIS 1259 (cc 1984).

Opinion

OPINION

MARGOLIS, Judge.

The plaintiff, Esprit Corporation, Inc., brings this action against the defendant, the United States, for interest on price adjustment payments made by the defendant to the plaintiff for work done pursuant to change orders issued by the Contracting Officer. This case is before the Court on cross motions for summary judgment, submitted with oral argument.

[547]*547FACTS

On April 7, 1980 the parties entered into a construction contract for miscellaneous and handicapped alterations of the Federal Building, United States Courthouse and Post Office in Concord, New Hampshire. The plaintiff was to be paid $87,461 and was to complete performance within 180 days after receiving notice to proceed. The plaintiff received notice on May 1, 1980.

From July 14, 1980 to November 15, 1981 the plaintiff sent letters to the Contracting Officer informing him of problems and requesting 18 contract modifications. The Contracting Officer accepted all the suggested modifications, but left open the question of contract price adjustments while the plaintiff proceeded with the work in accordance with the change orders. The plaintiff has completed all the work.

The Contracting Officer then sent the plaintiff 18 invoices on which the plaintiff listed a price adjustment proposal for each change order. The Contracting Officer accepted all the proposals, and the defendant has paid all the invoices. The defendant has also paid the plaintiff for two other changes. Complaint, Claims # 16, # 20.

On January 18, 19, and 20, 1982 the plaintiff requested interest under section 12 of the Contract Disputes Act of 1978, 41 U.S.C. § 611 (1982) [CDA], which provides: “Interest on amounts found due contractors on claims shall be paid to the contractor from the date the contracting officer receives the claim pursuant to section 605(a) of this title from the contractor until payment thereof.” The plaintiff asserted in the alternative that it was entitled to interest on the price adjustment payments: 1) from the date it submitted the requests for modifications until the date of payment (type I claim); or 2) from the date upon which those payments became unreasonably delayed until the date of payment (type II claim). The Contracting Officer denied these claims on February 26, 1982. The plaintiff reasserts these claims in its motion for summary judgment.

In its cross motion, the defendant contends that the doctrine of accord and satisfaction bars the plaintiffs type I claim. The defendant also contends that neither claim is a claim on which relief can be granted because requests for contract modifications are not “claims” on which interest will accrue under section 12 of the CDA. A “claim” under the CDA must be disputed, the defendant argues. The requests for modifications were never disputed. Therefore, the plaintiff is not entitled to interest under the CDA.

This Court agrees that the plaintiff cannot claim interest under the statute. The Court need not address the defendant’s arguments as to accord and satisfaction because the plaintiff cannot demand interest from the government absent contractual or statutory entitlement. 28 U.S.C. § 2516(a) (1982). Therefore, the Court grants the defendant’s motion for summary judgment and denies the plaintiff’s motion for summary judgment.

DISCUSSION

Background

In 1969 Congress established the Commission on Government Procurement to examine the existing procurement system. In 1972 the Commission sent Congress twelve recommendations concerning the resolution of contract disputes arising in connection with the performance of a contract. One recommendation was that Congress waive sovereign immunity to permit interest to run against the government in certain circumstances.

Because interest cannot run against the government absent contractual or statutory authorization, the Commission noted that contractors had “been unable to recover interest on amounts recovered at the close of a dispute,” and concluded that “the goals of the administrative process are frustrated if final payment of a judgment ignores long delays and losses resulting from a mandatory review procedure.” 4 Commission on Government Procurement, Report of the Commission on Government Procurement 29 (1972) [Commission Report]. The Senate noted this flaw of the [548]*548procurement system when it passed the CDA:

Since the contractor has been compelled to perform the work with its own money ... there can be no equitable adjustment to the contractor until the contractor recovers the entire cost of the additional work. The cost of money to finance this additional work while pursuing the administrative remedy, normally called interest, is a legitimate cost of performing the additional work.

S.Rep. No. 1118, 95th Cong., 2d Sess. 32, reprinted in 1978 U.S.Code Cong. & Ad. News 5235, 5266.

The CDA awards the contractor interest “on amounts found due ... on claims....” 41 U.S.C. §611. The Act does not define the word “claim,” but courts have already determined that a demand for interest alone is not a claim under the CDA. See, e.g., Nab-Lord Associates v. United States, 230 Ct.Cl. 694, 699, 682 F.2d 940, 944 (1982) (Since the contractor’s underlying claim was not subject to the CDA, interest did not accrue on the claim.). See also Recon Paving, Inc. v. United States, 745 F.2d 34 at 40 (Fed.Cir.1984) (Interest cannot run on an uncertified demand for more than $50,000 because such a demand is not a “claim” under the CDA.). Therefore, the plaintiff cannot recover interest under section 12 of the CDA unless the requests for contract modifications were “claims.”

The Office of Federal Procurement Policy (OFPP) has issued two definitions of the word “claim” as used in the CDA. The first, promulgated on February 26, 1979, defined “claim” as a matter in dispute. 44 Fed.Reg. 12,524 (1979). This definition was included in the Disputes Clause of the contract at issue in this case. The final OFPP regulations, effective on June 1, 1980, define “claim” as follows:

1(b) (i) As used herein “claim” means a written demand ... seeking, as a legal right, the payment of money, adjustment or interpretation of contract terms, or other relief, arising under or relating to the contract.
(ii) A voucher, invoice, or request for payment that is not in dispute when submitted is not a claim for the purposes of the Act. However, where such submission is subsequently not acted upon in a reasonable time, or disputed either as to liability or amount, it may be converted to a claim under Section 6(a) of the Act as provided in Section 3, below.

45 Fed.Reg. 31,035 (1980), codified at 32 C.F.R. § 7-103.12(c) (1983). The plaintiff seeks type I interest under § l(b)(i) of this regulation, contending that such a claim requires no dispute. The plaintiff seeks type II interest under § l(b)(ii).

Type I Claims

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Tiger Natural Gas, Inc. v. United States
61 Fed. Cl. 287 (Federal Claims, 2004)
Hardwick Bros. v. United States
41 Cont. Cas. Fed. 76,972 (Federal Claims, 1996)
Detroit International Bridge Co. v. United States
39 Cont. Cas. Fed. 76,711 (Federal Claims, 1994)
HNV Central River Front Corp. v. United States
37 Cont. Cas. Fed. 76,289 (Court of Claims, 1992)
CPT Corp. v. United States
37 Cont. Cas. Fed. 76,282 (Court of Claims, 1992)
Essex Electro Engineers, Inc. v. United States
37 Cont. Cas. Fed. 76,042 (Court of Claims, 1991)
Arkansas Best Freight System, Inc. v. United States
36 Cont. Cas. Fed. 75,905 (Court of Claims, 1990)
City of El Centro v. United States
35 Cont. Cas. Fed. 75,724 (Court of Claims, 1989)
Santa Fe, Inc. v. United States
34 Cont. Cas. Fed. 75,385 (Court of Claims, 1987)
Straga v. United States
32 Cont. Cas. Fed. 73,470 (Court of Claims, 1985)
Hoffman Construction Co. v. United States
32 Cont. Cas. Fed. 73,279 (Court of Claims, 1985)

Cite This Page — Counsel Stack

Bluebook (online)
32 Cont. Cas. Fed. 73,069, 6 Cl. Ct. 546, 1984 U.S. Claims LEXIS 1259, Counsel Stack Legal Research, https://law.counselstack.com/opinion/esprit-corp-v-united-states-cc-1984.