Santa Fe, Inc. v. United States

34 Cont. Cas. Fed. 75,385, 13 Cl. Ct. 464, 1987 U.S. Claims LEXIS 196
CourtUnited States Court of Claims
DecidedOctober 30, 1987
DocketNo. 686-86C
StatusPublished
Cited by4 cases

This text of 34 Cont. Cas. Fed. 75,385 (Santa Fe, Inc. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Santa Fe, Inc. v. United States, 34 Cont. Cas. Fed. 75,385, 13 Cl. Ct. 464, 1987 U.S. Claims LEXIS 196 (cc 1987).

Opinion

OPINION

YOCK, Judge.

This contract dispute is before the Court on defendant’s motion to dismiss for lack of jurisdiction. For the reasons discussed herein, the defendant’s motion is granted with the plaintiff’s complaint to be transferred to the Veterans’ Administration Board of Contract Appeals.

Facts

On March 2, 1978, the plaintiff, Santa Fe Engineers (SFE), entered into a contract, No. V101C672, with the Veterans’ Administration to construct and remodel an addition to the Veterans’ Administration Medical Center in Huntington, West Virginia. After concluding that the Government initiated a change to the original contract, SFE submitted a certified equitable adjustment claim, totaling some $82,814, to the contracting officer on February 5, 1982. This claim was denied by the contracting officer in a final decision dated April 15, 1982. SFE elected to proceed in accordance with the provisions of the Contract Disputes Act of 1978, 41 U.S.C. §§ 601 et seq. (1982), and thereafter, elected to appeal the contracting officer’s final, adverse decision to the Veterans’ Administration Board of Contract Appeals (Board).

The plaintiff prevailed at the Board on the issue of entitlement (liability) and the Board remanded the case to the contracting officer to determine the quantum due SFE. Appeal of Santa Fe, Inc., VABCA-1746, VABCA-1747, April 17, 1985. SFE submitted its quantum claim to the contracting officer on November 1, 1985. This claim was later withdrawn and a revised certified claim was submitted to the contracting officer on January 28, 1986. The parties agreed to a settlement totaling some $142,-866 on May 21, 1986.

Several days later, the plaintiff requested that payment of the claim also include interest from the date the claim was initially submitted to the contracting officer, i.e., February 5,1982. This request was denied in part by the contracting officer. In his decision, dated September 3, 1986, the contracting officer determined that the plaintiff was entitled to payment of interest from January 28,1986, the date the revised certified claim was submitted, until June 30, 1986.

The plaintiff contends that 41 U.S.C. § 611 (1982) mandates an interest award of some $77,909. The contracting officer awarded payment of some $5,804 in interest, thereby leaving approximately $72,105 in interest still in dispute. Plaintiff filed suit in the United States Claims Court on October 28, 1986, seeking recovery of this amount. SFE asserts jurisdiction pursüant to the direct access provision of the Contract Disputes Act of 1978, 41 U.S.C. § 609(a)(1) (1982).

Discussion

The defendant, in its motion to dismiss, contends that this Court lacks jurisdiction to decide the plaintiff’s interest dispute with the Government. The Government argues that the plaintiff had previously made a binding election under the Contract Disputes Act of 1978 to appeal its underlying equitable adjustment claim to the Veterans’ Administration Board of Contract Appeals, and cannot now shift gears and appeal a part of that claim (i.e., the interest dispute) to the Claims Court. The defendant asserts that a direct access appeal to the Claims Court is precluded under the factual circumstances presented here. As a result, the defendant maintains that the plaintiff’s complaint should be dismissed for lack of jurisdiction.

The plaintiff counters the Government’s contention by asserting that its present interest claim is “separate and distinct” from its original equitable adjustment claim which was appealed to the Board. In addition, the plaintiff points to the contracting officer’s September 3, 1986 final decision letter, which stated that the plaintiff may appeal the interest dispute to the Claims Court in lieu of appealing to the Board, as granting jurisdiction to this Court. As a [466]*466result, the plaintiff maintains that the plaintiff was entitled to its choice of forum to hear this dispute.

The provisions of the Contract Disputes Act of 1978, 41 U.S.C. §§ 601 et seq. (1982) (CDA) apply to all contracts entered into on or after March 1, 1979. Additionally, for contracts entered into prior to the effective date of the Act, the contractor may elect to proceed under the Act with respect to any claim pending before a contracting officer as of March 1, 1979, or initiated thereafter. 41 U.S.C. § 601 note, Pub.L. No. 95-563, § 16. Here, the plaintiff entered into its contract with the Veterans’ Administration on March 2, 1978, and initiated its original equitable adjustment claim with the contracting officer on February 5, 1982. Thus, the plaintiff had the right to proceed with its claim under the CDA at its election.

Having received an adverse decision from the contracting officer, the plaintiff was faced with making two elections. First, plaintiff had to elect whether to proceed in accordance with the provisions of the CDA or to be governed only by the terms of the contract. Plaintiff chose the former. Appeal of Santa Fe, Inc., VAB-CA-1746, VABCA-1747, April 17, 1985. Having so chosen, plaintiff then had to decide in which forum to pursue its claim. The contractor may elect to proceed under either 41 U.S.C. § 606 (1982) or 41 U.S.C. § 609(a)(1) (1982). The first provision provides: “Within ninety days from the date of receipt of a contracting officer’s decision * * * the contractor may appeal such decision to an agency board of contract appeals * * 41 U.S.C. § 606 (1982). Alternatively, and “in lieu of appealing the decision of the contracting officer * * * to an agency board, a contractor may bring an action directly on the claim in the United States Claims Court * * 41 U.S.C. § 609(a)(1) (1982) (emphasis supplied).

A contractor, however, cannot do both. These avenues for relief from a contracting officer’s adverse decision are mutually exclusive. Once a contractor elects to bring an appeal before an appropriate board of contract appeals, he is bound by that decision and cannot later elect to bring a direct access suit in the Claims Court. Santa Fe Engineers, Inc. v. United States, 230 Ct.Cl. 512, 515-16, 677 F.2d 876, 878 (1982); Tuttle/White Constructors, Inc. v. United States, 228 Ct.Cl. 354, 357-58, 656 F.2d 644, 646-47 (1981); Diamond Mfg. Co. v. United States, 3 Cl.Ct. 424, 427 (1983).

That the plaintiff elected to appeal the contracting officer’s original adverse decision pertaining to its equitable adjustment claim to the Board is undisputed.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Spanish Solutions Language Services
Armed Services Board of Contract Appeals, 2020
Palafox Street Associates, L.P. v. United States
122 Fed. Cl. 18 (Federal Claims, 2015)
Skillo v. United States
68 Fed. Cl. 734 (Federal Claims, 2005)
Marshall Associated Contractors, Inc. v. United States
39 Cont. Cas. Fed. 76,702 (Federal Claims, 1994)

Cite This Page — Counsel Stack

Bluebook (online)
34 Cont. Cas. Fed. 75,385, 13 Cl. Ct. 464, 1987 U.S. Claims LEXIS 196, Counsel Stack Legal Research, https://law.counselstack.com/opinion/santa-fe-inc-v-united-states-cc-1987.