Boyd Lumber Corp. v. United States

32 Cont. Cas. Fed. 72,728, 5 Cl. Ct. 803, 1984 U.S. Claims LEXIS 1337
CourtUnited States Court of Claims
DecidedAugust 14, 1984
DocketNo. 526-83C
StatusPublished
Cited by3 cases

This text of 32 Cont. Cas. Fed. 72,728 (Boyd Lumber Corp. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Boyd Lumber Corp. v. United States, 32 Cont. Cas. Fed. 72,728, 5 Cl. Ct. 803, 1984 U.S. Claims LEXIS 1337 (cc 1984).

Opinion

OPINION ON PLAINTIFF’S AND DEFENDANT’S MOTIONS TO DISMISS THE COMPLAINT

PHILIP R. MILLER, Judge:

The complaint in this case, filed August 16,1983, alleges the following: On January 12, 1978, plaintiff contracted to purchase from the United States Forest Service a specified quantity of standing timber by April 16, 1981. On April 15, 1981, plaintiff requested a year’s extension to complete the purchase due to adverse economic conditions, pursuant to the force majeur clause of the contract, but defendant denied the request. On August 17, 1982, the Forest Service contracting officer notified plaintiff that he considered plaintiff’s failure to remove the included timber by the contract termination date to be a breach of contract, that the Service had resold such timber at a lower price than plaintiff had agreed to pay for it, and that plaintiff was liable to the United States for its damages, in the sum of $542,429.09 plus interest. The notice stated that it was a final decision of the contracting officer which plaintiff was entitled to appeal under the “disputes” clause of the contract to the Agriculture Board of Contract Appeals (AGBCA) (within 30 days) pursuant to Department Regulations (7 C.F.R. § 24.5 (1982)), or under the Contract Disputes Act of 1978 (41 U.S.C. §§ 606, 607 and 609) either to the AGBCA within 90 days or directly to the U.S. Court of Claims within 12 months.

The complaint states that in the plaintiff’s view this court (as successor to the Court of Claims) does not have jurisdiction of this dispute, but that the complaint is filed to protect plaintiff’s rights in the event the United States district court, where plaintiff believes jurisdiction lies, does not have jurisdiction. Plaintiff further alleges that it does not owe the United States the $549,429.09 or any other sum, and prays for a judgment to that effect.

In its answer, filed October 17, 1983, defendant denies that plaintiff is entitled to the relief it seeks and counterclaims for a $542,429.09 judgment in its favor.

Plaintiffs Motion to Dismiss

On February 14, 1984, plaintiff moved to dismiss the complaint and counterclaim on the ground that this court is without subject matter jurisdiction. Plaintiff’s argument in support of the motion is that the Claims Court’s jurisdiction is limited generally to claims for money against the government, whereas plaintiff’s claim is for an adjudication that it is not liable to the government. It states that the contracting officer was mistaken in advising plaintiff it could appeal to the Claims Court under the Contract Disputes Act, because Section 16 of that Act provides that it is effective only with respect to contracts entered into after February 28, 1979 (120 days after the date of enactment of the Act (November 1, 1978) Sec. 16 of Contract Disputes Act of 1978, Pub.L. 95-563, 93 Stat. 648 (reprinted in note to 41 U.S.C.A. § 601)), whereas plaintiff’s contract was entered into more than a year earlier. It contends that the government’s claim for [805]*805breach of contract may only be adjudicated in a United States district court, where it is entitled to a jury trial as a matter of constitutional right.

It is plaintiff which is mistaken, since it overlooks the second sentence of Section 16 of the Act, which provides:

Notwithstanding any provision in a contract made before the effective date of this Act, the contractor may elect to proceed under this Act with respect to any claim pending then before the contracting officer or initiated thereafter.

Plaintiff had several options: To the extent the contracting officer’s refusal to allow plaintiff the year’s extension or the contracting officer’s damage claim involved questions of fact, plaintiff could have appealed to the AGBCA under the “disputes” clause of its contract.1 Alternatively plaintiff could have elected to proceed under the Contract Disputes Act both with respect to the plaintiff’s claim and the government’s claim (whether based on disputes of fact or law), with the further alternative of electing to appeal to the AGBCA 2 or to proceed by direct action in the U.S. Claims Court. Still further, plaintiff could have elected to do nothing and waited for the government to sue it in a district court for damages for the claimed breach of contract, at which time plaintiff could have asserted its right to a jury trial.3 Cf. Algernon Blair Industrial Contractors, Inc. v. T.V.A., 552 F.Supp. 972 (M.D.Ala.1982); Damsky v. Zavatt, 289 F.2d 46, 51 (2nd Cir.1961).

Plaintiff was not misled by the contracting officer as to its options, since all but the last are stated in the contracting officer’s notice of decision of August 17, 1972, and the contracting officer was under no duty to inform plaintiff of the last option, which is based on plaintiff’s own conception of its constitutional rights.

Accordingly plaintiff’s motion to dismiss the complaint for lack of subject matter jurisdiction is denied.

Defendant's Motion

Although defendant’s motion is entitled a “Cross-Motion to Dismiss and Response to Plaintiff’s Motion to Dismiss”, it is not in fact a motion to dismiss the claim but a motion for summary judgment, because it relies on matters outside the pleadings; and it does not in fact respond to plaintiff’s motion. All it says in opposition is in the latter half of the following sentence:

Defendant respectfully moves the Court to dismiss plaintiff's claim on the ground that this Court lacks jurisdiction over the claim, and concurrently opposes plaintiff’s motion to dismiss on the ground that the Contract Disputes Act of 1978 controls the present dispute.

In support of its cross-motion, defendant originally argued that the plaintiff’s claim should be dismissed on the ground that the court lacks jurisdiction over the claim because plaintiff previously made a binding and irrevocable election under the Contract Disputes Act to appeal to the AGBCA and thus is now barred from proceeding in the Claims Court. However, in response to the court’s question as to what action constituted such an election, in a supplemental memorandum defendant now concedes that plaintiff’s resort to the AGBCA was timely [806]*806enough to have been under the authority of the “disputes” clause and applicable regulations; but defendant nevertheless contends that such election likewise irrevocably deprived the court of jurisdiction over a direct access suit, and should therefore be dismissed.

The action which defendant contends constituted the binding election by plaintiff was its appeal to the AGBCA from the contracting officer’s letters of May 8 and 14, 1981, filed June 5, 1981. The May 8 letter denied plaintiff’s request for a one-year contract term adjustment due to adverse market conditions on the ground that the force majeur clause upon which plaintiff relied did not include adverse market conditions.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Spodek v. United States
51 Fed. Cl. 221 (Federal Claims, 2001)
Santa Fe, Inc. v. United States
34 Cont. Cas. Fed. 75,385 (Court of Claims, 1987)
Mark Smith Construction Co. v. United States
33 Cont. Cas. Fed. 74,510 (Court of Claims, 1986)

Cite This Page — Counsel Stack

Bluebook (online)
32 Cont. Cas. Fed. 72,728, 5 Cl. Ct. 803, 1984 U.S. Claims LEXIS 1337, Counsel Stack Legal Research, https://law.counselstack.com/opinion/boyd-lumber-corp-v-united-states-cc-1984.