Rudolph and Sletten, Inc. v. United States

120 Fed. Cl. 137, 2015 U.S. Claims LEXIS 165, 2015 WL 753319
CourtUnited States Court of Federal Claims
DecidedFebruary 23, 2015
Docket14-647C
StatusPublished
Cited by5 cases

This text of 120 Fed. Cl. 137 (Rudolph and Sletten, Inc. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Federal Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Rudolph and Sletten, Inc. v. United States, 120 Fed. Cl. 137, 2015 U.S. Claims LEXIS 165, 2015 WL 753319 (uscfc 2015).

Opinion

*139 Contract Disputes Act (CDA), 41 U.S.C. §§ 7101-09; Motion to Dismiss, Rule 12(b)(1); Motion for Summary Judgment, Rule 56; Motion Remand to the Contracting Officer, 41 U.S.C. § 7103(f)(5); Deemed Denial of a Claim.

MEMORANDUM OPINION AND ORDER

LYDIA KAY GRIGGSBY, Judge

I. INTRODUCTION

Plaintiff, Rudolph and Sletten, Inc. (“R & S”), brought this action pursuant to the Contract Disputes Act of 1978, 41 U.S.C. §§ 7101-09 (“CDA”). The government moved to dismiss R & S’s complaint, or alternatively for summary judgment, for lack of subject-matter jurisdiction pursuant to Rules 12(b)(1) and 56 of the Rules of the United States Court of Federal Claims (“RCFC”), arguing that there has been neither an actual nor a deemed final decision by the contracting officer. In the alternative, the government moves for remand of the case to the contracting officer for a final decision. For the reasons set forth below, the government’s motion to dismiss, or alternatively for summary judgment, is DENIED. The government’s motion in the alternative for remand of this case to the contracting officer for a final decision is GRANTED.

II. FACTUAL AND PROCEDURAL BACKGROUND 1

The dispute in this case arises out of a government contract awarded to R & S to build the Southwest Fisheries Science Center Replacement Headquarters and Laboratory in La Jolla, California (“La Jolla Laboratory”).

On May 3, 2010, the United States Department of Commerce, National Oceanic and Atmospheric Administration (“NOAA”), awarded R & S Contract No. AB1330-10-CN-0114 to construct the La Jolla Laboratory. Compl. at Ex. A.

On August 20, 2013, R & S submitted a certified claim (“Claim 1”) to NOAA’s con-traeting officer (“the contracting officer”) seeking a compensable contract time extension and $26,809,003 as compensation for costs due to alleged government-caused delay and disruption, additional consultant costs, and extra work undertaken by R & S and its subcontractors. Compl. at Ex. B. NOAA received R & S’s certified claim on August 23, 2013. Compl. at Ex. C.

On October 21, 2013, the contracting officer wrote to R & S advising that:

In accordance with FAR 52.233-l(e), the Contracting Officer’s final decision, or a date by which a decision will be made, must be provided to your firm. Due to the complexity and extensive nature of your claim, we anticipate a final Contracting Officer’s decision to be issued 9 months from the date of this letter.

App. to Def. Mot. at 19.

On October 30, 2013, R & S submitted a second certified claim (“Claim 2”) to the contracting officer. App. to Def. Mot. at 1-18. This claim sought an additional $2,600,861 for delay-related costs and unresolved Requests for Contract Modifications. App. to Def. Mot. at 7.

On November 4, 2013, R & S wrote to the contracting officer acknowledging receipt of the October 21, 2013 letter, but stating that the nine-month extension to review Claim 1 was excessive and unreasonable. App. to Def. Mot. at 20. In addition, R & S requested either a detailed explanation for the delay or a work plan. Id. The contracting officer responded on November 8, 2013, explaining the reason for the nine-month delay and providing R & S with a timeline for reaching a final decision on Claim 1 by July 15, 2014. App. to Def. Mot. at 21-22.

On January 6, 2014, R & S filed its first lawsuit arising under the La Jolla contract. Rudolph & Sletten, Inc. v. United States, No. 14-14C (Fed.Cl. Jan. 6, 2014) (“R & S I”). On May 6, 2014, the government filed a dispositive motion in R & SI. That motion is *140 fully briefed, and is separately pending before the Court.

On July 8, 2014, the contracting officer informed R & S that a final decision on Claim 1 would not be reached by July 15, 2014 as originally estimated by the government, and that, instead, a final decision would be forthcoming on March 15, 2015. App. to Def. Mot. at 40-41. The contracting officer also provided R & S with the following schedule for the resolution of Claim 1:

July 31, 2014: Approximately 35 PCOs Requiring a Technical Merit Letter;
August 31, 2014: Approximately 35 PCOs reassessing previously issued unilateral modifications and directives;
October 15, 2014: Approximately 35 PCOs reassessing previously issued unilateral modifications and directives;
November 15, 2014: Approximately 35 PCOs reassessing previously issued unilateral modifications and directive;
January 15, 2015: Approximately 35 PCOs pending evaluation;
February 27, 2015: Approximately 25 PCOs pending evaluation.

App. to Def. Mot. at 41. R & S filed the present action regarding Claim 1 on July 23, 2014.

The government moves to dismiss this case, or alternatively for summary judgment, for lack of jurisdiction, arguing that R & S failed to obtain a final decision from the contracting officer before filing its complaint. See generally Def. Mot. Alternatively, the government requests that the Court stay and remand this case to the contracting officer for a final decision, pursuant to 41 U.S.C. § 7103(f)(5). Id. at 19.

III. ANALYSIS

A. Legal Standards

Whether this Court possesses jurisdiction to decide the merits of a case is a threshold matter. Copar Pumice Co., Inc. v. United States, 112 Fed.Cl. 515, 527 (2013) (citing PODS, Inc. v. Porta Stor, Inc., 484 F.3d 1359, 1364 (Fed. Cir.2007)); Steel Co. v. Citizens for a Better Env’t, 523 U.S. 83, 94-95, 118 S.Ct. 1003, 140 L.Ed.2d 210 (1998). Deciding a motion to dismiss “starts with the complaint, which must be well-pleaded in that it must state the necessary elements of the plaintiffs claim, independent of any defense that may be interposed.” Holley v. United States, 124 F.3d 1462, 1465 (Fed.Cir.1997). As a ease cannot proceed if a court lacks jurisdiction to hear it, the plaintiff bears the burden of establishing subject-matter jurisdiction and must do so by a preponderance of the evidence. Arbaugh v. Y & H Corp.,

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
120 Fed. Cl. 137, 2015 U.S. Claims LEXIS 165, 2015 WL 753319, Counsel Stack Legal Research, https://law.counselstack.com/opinion/rudolph-and-sletten-inc-v-united-states-uscfc-2015.