Bowman Construction Company v. United States

CourtUnited States Court of Federal Claims
DecidedJune 14, 2021
Docket18-1822
StatusPublished

This text of Bowman Construction Company v. United States (Bowman Construction Company v. United States) is published on Counsel Stack Legal Research, covering United States Court of Federal Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Bowman Construction Company v. United States, (uscfc 2021).

Opinion

In the United States Court of Federal Claims No. 18-1822C (Filed: June 14, 2021)

************************** * BOWMAN CONSTRUCTION CO., * * Motion to Dismiss; Contract Plaintiff, * Disputes Act; Statute of * Limitations; Termination for v. * Default; Surety; Failure to Present * Claim to Contracting Officer; THE UNITED STATES, * Vague Claims. * Defendant. * * ** * * * * * * * * * * * * * * * * * * * * * * * * Spencer L. Sears, Erin Frazee Masini, Fox Rothschild LLP, 1030 15th Street, N.W., Suite 380 East, Washington, D.C. 20005, for Plaintiff.

Jeffrey Bossert Clark, Robert E. Kirschman, Jr., Patricia M. McCarthy, Michael Duane Austin, United States Department of Justice, Civil Division, P.O. Box 480, Ben Franklin Station, Washington, D.C. 20044, for Defendant. Alexander Fichtel, United States Department of the Interior, Of Counsel. _________________________________________________________

OPINION, ORDER OF PARTIAL DISMISSAL, AND ORDER TO SHOW CAUSE _________________________________________________________

WILLIAMS, Senior Judge. Defendant seeks dismissal of this Contract Disputes Act (“CDA”) case on statute of limitations grounds. In October 2012, the contracting officer issued a final decision terminating for default Plaintiff’s contract for construction of a bicycle trail in Voyageurs National Park, Minnesota. Although Plaintiff was required to appeal that decision within one year under the CDA, Plaintiff did not take any action to challenge that decision until some five years later in October 2017. Then, in what it characterized a “claim,” Plaintiff argued that the Government wrongfully terminated its contract and sought $837,759.21 representing reimbursement of the amounts its Surety paid for excess reprocurement costs, as well as unpaid invoices, costs of services and materials, work done by subcontractors, extended overhead, and “loss of bonding power” and future Government work. The Government denied this 2017 claim, and Plaintiff appeals the denial in this Court. Defendant argues that this action, filed in 2018, is an untimely challenge to the 2012 decision terminating the contract for default. The Court agrees that Plaintiff was required to file an appeal of the termination decision within one year under the CDA and failed to do so, making Plaintiff’s attempted challenge to the termination decision time-barred. Nor can Plaintiff maintain an action to recover the amount that its insurer, Old Republic Surety Company (“Surety”), paid the Government due to Plaintiff’s default. Plaintiff has not established the jurisdictional predicate for this claim as the Government never asserted a CDA claim for excess reprocurement costs and Plaintiff never appealed a contracting officer’s final decision assessing those costs. Rather, the Surety paid those costs standing in Plaintiff’s shoes, and Plaintiff acquiesced in that payment by confessing judgment in favor of the Surety in state court. In this action, Plaintiff also asserts claims for lost profits stemming from the alleged bad-faith termination and for home office overhead, but these claims were never presented to a contracting officer and must be dismissed. Plaintiff’s claim for unpaid invoices survives the motion to dismiss because Plaintiff has alleged that these invoices cover work performed and accepted prior to the termination. The Government contends that the remaining elements of this action and Plaintiff’s 2017 claim -- costs for surveying, subcontractor work, stump removal, erosion and stabilization fabrics, supervisor labor, extended overhead, and additional clearing work -- are also challenges to the termination for default dressed up as separate monetary claims and that an appeal of the denial of those claims is time-barred. The Court cannot resolve this aspect of the Government’s argument because Plaintiff has failed to articulate the bases for these claims. As such, the Court defers resolving Defendant’s motion as to those claims pending further development of the record. Background 1 The Solicitation On July 13, 2011, the National Park Service issued a solicitation seeking bids for construction of a 1.78 mile-long, 10-foot wide paved bicycle trail in Voyageurs National Park near International Falls, Minnesota. The procurement was a “100% Total Small Business set-aside.” ECF No. 73-1 at 2. Bidders were required to submit bids for 30 line items and, if selected, were to provide “all labor, equipment, supervision and materials necessary” for construction of the bike trail. Id. at 7; ECF No. 73-3 at 3. The line items included materials and services, such as geotextile fabrics, rip rap and barrow, aggregate base, bituminous concrete pavement, turf establishment, rock blasting, clearing, stump removal, surveying and staking, and construction of temporary access drives and a parking area. The solicitation stated: B.2 BID SCHEDULE ... Submit bid for all items; failure to do so may render the bid non-responsive. On lump-sum bid items, provide total price only; on unit price bid items, provide the unit price and the extended amount of bid.

1 This background is derived from the Second Amended Complaint, appendices and exhibits to the parties’ filings, and admissions during oral argument. 2 Quantities for unit price items are estimated, but payment will be made only for actual quantities of work completed. ECF No.73-1 at 7. On August 15, 2011, Plaintiff, Bowman Construction Company, Inc. (“Bowman”), submitted its bid in the amount of $1,204,902, and on September 22, 2011, the National Park Service awarded Plaintiff Contract No. P11PC60388 (“the Contract”). Performance The agency issued a notice to proceed on October 24, 2011. As of an October 24, 2011 construction meeting, performance “proceeded in a timely fashion with surveying discrepancies, blasting plans and protocols, approval of class 5 barrow and field adjustments amicably resolved.” ECF No. 64-1 at 2. On December 12, 2011, due to “winter weather conditions, the Government halted work at approximately one-third completeness.” Second Am. Compl. ¶ 30; see Answer ¶ 30; ECF No. 37-7 at 1. During the winter shutdown, the parties met and discussed a potential need for more topsoil, and issues with parking area grades, drainage, and slopes. On March 19, 2012, the parties agreed on Amendments 0001 and 0002 “to increase and adjust unit measurements and volumes.” ECF No. 64-1 at 3. Work on the project resumed on April 30, 2012. In mid-April 2012, the parties discussed “the contract limitation on imported common and granular barrow,” and in May, Plaintiff informed contracting officer (“CO”) S. Dale Allen that it would exceed the barrow limitation. Id. at 3-4. On May 22, 2012, the contract specialist, Karen Thomas, advised Plaintiff that she would issue Amendment 0003 to the Contract, allowing for an additional 3,600 tons of barrow, and granting a price increase based on a cost of $10 per ton. It appears that between June 11 through September 29, 2012, no work was performed on the bike trail, and that on June 14, 2012, Plaintiff removed its machinery and workers from the worksite. On July 18, 2012, the contracting specialist issued Amendment 0003 apparently increasing granular barrow and agreeing to pay an additional $35,000. 2 The parties continued to have disputes into August 2012, regarding additional fill material and grade slopes. On August 4, 2012, the Government issued Amendment 0004, providing an unspecified payment for an additional 1,743 tons of granular barrow. On August 15, 2012, Plaintiff advised the contracting officer that it would “not submit a fixed price to shape the slopes of the bike trail. There are no ‘true grades’ to meet: ….only the whim of your inspector David Draipsa [sic].” ECF No. 64-1 at 6.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

M. Maropakis Carpentry, Inc. v. United States
609 F.3d 1323 (Federal Circuit, 2010)
Adair v. United States
497 F.3d 1244 (Federal Circuit, 2007)
The Sharman Company, Inc. v. United States
2 F.3d 1564 (Federal Circuit, 1993)
Colonel David W. Palmer, II v. United States
168 F.3d 1310 (Federal Circuit, 1999)
Nicon, Inc. v. United States
331 F.3d 878 (Federal Circuit, 2003)
Scott Timber Company v. United States
333 F.3d 1358 (Federal Circuit, 2003)
Miller v. Shugart
316 N.W.2d 729 (Supreme Court of Minnesota, 1982)
Majestic Inc. v. Berry
593 N.W.2d 251 (Court of Appeals of Minnesota, 1999)
Veridyne Corporation v. United States
758 F.3d 1371 (Federal Circuit, 2014)
K-Con Building Systems, Inc. v. United States
778 F.3d 1000 (Federal Circuit, 2015)
Laguna Construction Company v. Defense
828 F.3d 1364 (Federal Circuit, 2016)
National Air Cargo Group, Inc. v. United States
127 Fed. Cl. 707 (Federal Claims, 2016)

Cite This Page — Counsel Stack

Bluebook (online)
Bowman Construction Company v. United States, Counsel Stack Legal Research, https://law.counselstack.com/opinion/bowman-construction-company-v-united-states-uscfc-2021.