Milmark Services, Inc. v. The United States

731 F.2d 855, 32 Cont. Cas. Fed. 72,350, 1984 U.S. App. LEXIS 14886
CourtCourt of Appeals for the Federal Circuit
DecidedApril 5, 1984
DocketAppeal 83-1259
StatusPublished
Cited by62 cases

This text of 731 F.2d 855 (Milmark Services, Inc. v. The United States) is published on Counsel Stack Legal Research, covering Court of Appeals for the Federal Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Milmark Services, Inc. v. The United States, 731 F.2d 855, 32 Cont. Cas. Fed. 72,350, 1984 U.S. App. LEXIS 14886 (Fed. Cir. 1984).

Opinion

*857 NIES, Circuit Judge.

This ease is an appeal from the judgment of the United States Claims Court (White, Senior Judge) 1 holding that the Immigration and Naturalization Service (INS) is not liable for termination of a contract with Milmark Services, Inc., following Milmark’s non-performance.

The suit was brought directly to the United States Court of Claims from the contracting officer’s decision in accordance with 41 U.S.C. § 609(a)(1) (Supp. II 1978). Under § 403(d) of the Federal Courts Improvement Act of 1982, Pub.L. No. 97-164, 96 Stat. 25, 58 (1982), the case was subsequently transferred from the U.S. Court of Claims Trial Division to the U.S. Claims Court. Pursuant to Claims Court Rule 54(b), the Claims Court, having rendered a decision that Milmark was not entitled to recover and having determined that there was no just reason for delay in the entry of judgment on Milmark’s claims, entered judgment for the Government. Since a final judgment has been entered on Mil-mark’s claims, we have jurisdiction over this appeal under 28 U.S.C. § 1295(a)(3).

Milmark’s position is that its default under the contract was caused by factors beyond its control and without its fault or negligence. The Claims Court held that Milmark’s failure to perform according to the terms of the contract was not excusable. Milmark challenges certain findings of fact made by the trial court, the absence of findings allegedly necessary to the decision, the exclusion of proffered testimony, and the asserted failure by the court to recognize the Government’s duty of cooperation.

Having considered Milmark’s arguments, the record, and the decision of the Claims Court, we affirm.

The Standard of Review

The standard of review by this court of factual determinations by the U.S. Claims Court is not specifically delineated by statute. No decision of this court has directly addressed this issue. However, in CACI, Inc.-Federal v. United States, 719 F.2d 1567, 1582 (Fed.Cir.1983), the court concluded with the statement, “the kind of inquiry and analysis the Claims Court made in this case ... was clearly erroneous ____” (Emphasis added.)

The Government in its brief makes no argument directed to this issue but assumes by repeated references to findings being supported by “substantial evidence” that the more stringent “substantial evidence” standard rather than the “clearly erroneous” standard applies. See SSIH Equipment, S.A. v. USITC, 718 F.2d 365, 379, 218 USPQ 678, 690 (Fed.Cir.1983). Milmark merely asserts that certain findings are clearly erroneous, being contrary to the weight of the evidence.

While this court has not adopted the rule of some circuits that a party must specifically set out the applicable standard of review as an initial paragraph in its brief, an appellate court must always consider its standard of review and it is helpful to the court for the matter to be set out specifically in the briefs so that it can be determined whether the parties are or are not in agreement on the function of this court.

With respect to findings of fact by the U.S. Claims Court in a de novo proceeding on a contract claim, we believe that the appropriate standard of review is “clearly erroneous” as in appeals from trials in district courts. Heisig v. United States, 719 F.2d 1153, 1157-58 (Fed.Cir.1983). As defined by the Supreme Court in United States v. United States Gypsum Co., 333 U.S. 364, 395, 68 S.Ct. 525, 542, 92 L.Ed. 746 (1948):

A finding is “clearly erroneous” when although there is evidence to support it, the reviewing court on the entire evidence is left with the definite and firm conviction that a mistake has been committed.

Accordingly, the clearly erroneous standard will be applied with respect to review of factual disputes in this case.

*858 Background

The INS maintains information on aliens entering and leaving the United States by requiring aliens to complete an 1-94 form upon passage through immigration. After being completed, the form is sent to INS headquarters for processing. Information on the form is entered onto magnetic tape and fed into the INS data base.

In August of 1979, the INS solicited bids for the performance of data entry services in connection with the 1-94 program. The solicitation indicated that the successful bidder would be required to enter 400,000 documents per week, that each batch of 400.000 processed documents would be due at the INS within two weeks after pick-up, that some documents would be “difficult to read,” and that the error rate on every 100.000 documents could not exceed 2.5%. 2 Milmark submitted the lowest bid and was awarded the contract. The bid solicitation was protested, delaying the contract award and upsetting Milmark’s preparation. A protest submitted by the incumbent contractor raised the question of whether Mil-mark could perform within the error rate, given the poor quality of the 1-94 forms. Milmark gave assurances during the protest that, as a subcontractor for the incumbent contractor, it was “fully aware of the perplexity and peculiarities, i.e., handwriting, language difficulties, etc.” Milmark perceived no problem in performance and twice extended its bid. The contract was executed on April 22, 1980.

Milmark picked up the first batch of 400,-000 documents on April 24, but failed to deliver the entered data by the May 9 due date. On May 30, Milmark delivered 200,-000 of the processed documents, and on June 6, delivery was made of the remaining 200,000. The second batch of 400,000 documents was also delivered well after the due date specified in the contract. Milmark subsequently picked up 10 batches of 400,-000 documents on schedule, but had succeeded in processing only 100,000 of these documents by July 18, 1980. During the period of April to July 1980, Milmark submitted only two of 12 progress reports required under the contract.

On May 27, 1980, the INS issued a show cause notice advising Milmark that a default termination of the contract was being considered. As a result of the subsequent delinquencies in Milmark’s performance, the INS decided to terminate the contract on July 14. At Milmark’s request, termination was postponed and Milmark was given a final opportunity to demonstrate its ability to handle the contract by delivering a full batch of 400,000 documents on Friday, July 18. Upon Milmark’s failure to deliver any of the processed documents until Monday, July 21, the INS contracting officer terminated the contract by letter dated July 22, 1980.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Contreras v. Secretary of Health and Human Services
116 Fed. Cl. 472 (Federal Claims, 2014)
Dotcom Associates I, LLC v. United States
112 Fed. Cl. 594 (Federal Claims, 2013)
Veridyne Corp. v. United States
101 Fed. Cl. 651 (Federal Claims, 2011)
Fireman's Fund Insurance v. United States
92 Fed. Cl. 598 (Federal Claims, 2010)
Land Grantors in Henderson, Union v. United States
86 Fed. Cl. 35 (Federal Claims, 2009)
Tamerlane, Ltd. v. United States
550 F.3d 1135 (Federal Circuit, 2008)
Axion Corp. v. United States
75 Fed. Cl. 99 (Federal Claims, 2007)
Orlosky Inc. v. United States
68 Fed. Cl. 296 (Federal Claims, 2005)
Renda Marine, Inc. v. United States
66 Fed. Cl. 639 (Federal Claims, 2005)
Short Bros. PLC v. United States
65 Fed. Cl. 695 (Federal Claims, 2005)
Piscopo v. Secretary of Health & Human Services
66 Fed. Cl. 49 (Federal Claims, 2005)
Powell v. Department of Defense
87 F. App'x 183 (Federal Circuit, 2004)
Land v. United States
37 Fed. Cl. 231 (Federal Claims, 1997)

Cite This Page — Counsel Stack

Bluebook (online)
731 F.2d 855, 32 Cont. Cas. Fed. 72,350, 1984 U.S. App. LEXIS 14886, Counsel Stack Legal Research, https://law.counselstack.com/opinion/milmark-services-inc-v-the-united-states-cafc-1984.