South Carolina Public Service Authority

CourtArmed Services Board of Contract Appeals
DecidedJuly 22, 2020
DocketASBCA No. 60460, 60616
StatusPublished

This text of South Carolina Public Service Authority (South Carolina Public Service Authority) is published on Counsel Stack Legal Research, covering Armed Services Board of Contract Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
South Carolina Public Service Authority, (asbca 2020).

Opinion

ARMED SERVICES BOARD OF CONTRACT APPEALS

Appeals of -- ) ) South Carolina Public Service Authority ) ASBCA Nos. 60460, 60616 ) Under Contract No. DACW60-77-C-0005 )

APPEARANCE FOR THE APPELLANT: Megan E. Driggers, Esq. Counsel

APPEARANCES FOR THE GOVERNMENT: Michael P. Goodman, Esq. Engineer Chief Trial Attorney John P. Kassebaum, Esq. Engineer Trial Attorney U.S. Army Engineer District, Charleston

OPINION BY ADMINISTRATIVE JUDGE MCNULTY

Appellant, South Carolina Public Service Authority (the Authority or appellant) appeals from a denial of its claim that the government acting through the U.S. Army Corps of Engineers, is improperly demanding payment for additional electrical generation capacity provided to the Authority from the government’s St. Stephen hydroelectric power plant pursuant to an agreement the parties entered into in 1976. We deny these appeals, though, in accordance with the Board’s internal operating procedures, this decision has no precedential value because Judges Shackleford and Prouty concur only in result.

FINDINGS OF FACT 1

The Basis for the Contract

1. The contract at issue in these appeals reflects the settlement of a potential claim the Authority had against the government arising from the government’s

1 Findings of fact without citation to the record are borrowed, with deletions, paraphrasing and summarizing as appropriate for these appeals, from previous decisions relating to the contract, primarily South Carolina Public Service Authority, ENG BCA No. 5564, 89-3 BCA ¶ 21,921, and South Carolina Public Service Authority, ENG BCA No. 5564, 91-2 BCA ¶ 23,760. See also South Carolina Public Service Authority, ASBCA No. 53701, 04-2 BCA ¶ 32,651; and South Carolina Public Service Authority, ASBCA No. 57826, decision to reduce the shoaling occurring in the Charleston, South Carolina harbor caused by the increased discharges of water into the Cooper River resulting from the Authority’s construction and operation of the Santee Cooper Project, by reducing the discharge of water into the Cooper River from the Santee River. The reduction of water discharges into the Cooper River adversely affected the Authority’s ability to generate power.

2. The Santee Cooper Project was constructed by the Authority pursuant to a license granted to it in 1926 by the Federal Power Commission (now FERC), beginning in the late 1930’s. The project was designed to harness the hydroelectric power capability of the Cooper River as enhanced by the discharges from the Santee River.

3. After a lengthy period of study in the 1960’s, the government proposed rediverting the water into the Santee River and through a new hydroelectric plant to be built by the United States Army Corps of Engineers, with the generating capacity and energy from this new facility being provided to the Authority as compensation for the loss of water and energy resulting therefrom at the Authority’s Santee Cooper Project’s Jeffries plant. This plan is referred to by the parties as the “St. Stephen Plan.”

4. The Authority preferred an alternate plan, the “Price Inlet Plan” because it would not have affected the generating capacity of its Jeffries plant (R4, tab 10 at 346 ¶ 10b).

5. The Authority did not favor the St. Stephen plan because it would “create unsalable peaking capacity,” as well as result in a loss of energy from the Jeffries plant. Nevertheless, the Authority agreed to work with the government to develop the St. Stephen plan under the principle that the Authority would be “kept whole,” made

13 BCA ¶ 35,239. However, familiarity with these prior decisions, which include lengthy findings of fact setting forth in great detail most of the details relating to the purpose of the Santee Cooper Project and the contract’s negotiation and performance is presumed. In Blue Cross Association & Blue Shield Association, ASBCA No. 25944, 83-1 BCA ¶ 16,524, we stated that we can take official notice of findings of fact made in prior appeals involving the same parties, contract, counsel and tribunal. Although these appeals involve a different tribunal and counsel with respect to some of the decisions above, we are satisfied, based on our review of the record here, that the previous findings we have borrowed, paraphrased and summarized are accurate and that it is appropriate to take official notice thereof for these appeals.

2 neither better nor worse off as a result of the project. 2 The contract between the parties subsequently negotiated was based on the “keep whole” principle.

6. As part of this principle the Corps, in a 1966 study, recommended that the government be reimbursed by the Authority for the “betterments,” i.e., the additional power generated by the St. Stephen plan made available to the Authority. In this regard the study stated:

It is recommended as an equitable solution that the hydro plant be constructed, maintained and operated by the Corps of Engineers; that the power and energy produced be delivered to and as directed by the South Carolina Public Service Authority; that the Corps will be liable for damages resulting from project construction and operation; and that project betterments be reimbursable to the United States.

(R4, tab 9 at 160, tab 10 at 278)

7. The study analyzed several alternative plans, including the hydroelectric plant and related facilities ultimately built. The initial cost estimate from the 1966 study for this plan estimated a total federal investment of $37,592,000 based on an estimated cost of $35,381,000 plus $2,211,000 in interest and annual charges of $1,687,000. (R4, tab 9 at 197, 214) The initial estimate of the value of the betterment of the added dependable capacity was $773,000 per year based on $9.20 per kw year (id. at 203 ¶ 85). The study also indicated the “Net Power Benefits” would total $417,0003 per year, which would have the effect of reducing the annual charges from $1,687,000 to $1,270,000 (id. at 204).

8. All of the project cost analyses performed in the government’s study were based upon a 50 year economic life for the hydro plant (R4, tab 9 at 226). The basis for the 50 year period for economic analysis of hydroelectric plants is set forth in the Federal Power Commission’s “Hydroelectric Power Evaluation” (R4, tab 11 at 517). In contrast, thermal plants, which the FPC/FERC methodology uses to compare to as the alternate power source when evaluating hydro plants, are considered to have 30-35 year service lives (finding 32).

9. The annual value of hydroelectric power consists of two measurable components which are defined as follows: (1) a capacity value, which corresponds to

2 The Authority expressed its understanding that the “kept whole” concept had been agreed to in principle by the government as early as 1966 (R4, tab 10 at 449). 3 How this figure was derived is not set out in the study.

3 the fixed elements of the cost of power supply from an alternative electric generating plant; and (2) an energy value, which corresponds to the variable elements of the cost of power supply from the alternative plant (R4, tab 11 at 596).

10. The 1966 study included a letter from the Authority dated May 5, 1966, setting forth terms that subsequently, essentially became the agreement between the government and the Authority (R4, tab 9 at 218-22). The letter set out the principle that the Authority was to be made “whole” by the government, which would compensate the Authority annually for the reduced flow of water through the Jefferies plant and its detrimental effect on the Authority’s power generating. The letter also set forth the concept that the Authority would credit the government for the added power generating capacity that the new St.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Homestead Golf Club, Inc. v. Pride Stables
224 F.3d 1195 (Tenth Circuit, 2000)
Suess v. United States
535 F.3d 1348 (Federal Circuit, 2008)
Teg-Paradigm Environmental, Inc. v. United States
465 F.3d 1329 (Federal Circuit, 2006)
Flexfab, L.L.C. v. United States
424 F.3d 1254 (Federal Circuit, 2005)
Hercules Incorporated v. United States
292 F.3d 1378 (Federal Circuit, 2002)
Coast Federal Bank, Fsb v. United States
323 F.3d 1035 (Federal Circuit, 2003)
Kam-Almez v. United States
682 F.3d 1364 (Federal Circuit, 2012)
City of Kenai v. Ferguson
732 P.2d 184 (Alaska Supreme Court, 1987)
Cobble Hill Nursing Home, Inc. v. Henry & Warren Corp.
548 N.E.2d 203 (New York Court of Appeals, 1989)
In re Foster
3 Mills Surr. 1 (New York Surrogate's Court, 1902)
Premier Exhibitions, Inc. v. Marmargar, Inc.
908 F. Supp. 2d 741 (E.D. Virginia, 2012)

Cite This Page — Counsel Stack

Bluebook (online)
South Carolina Public Service Authority, Counsel Stack Legal Research, https://law.counselstack.com/opinion/south-carolina-public-service-authority-asbca-2020.