Kellogg Brown & Root Services, Inc.

CourtArmed Services Board of Contract Appeals
DecidedDecember 13, 2023
Docket62681, 62843, 62844
StatusPublished

This text of Kellogg Brown & Root Services, Inc. (Kellogg Brown & Root Services, Inc.) is published on Counsel Stack Legal Research, covering Armed Services Board of Contract Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Kellogg Brown & Root Services, Inc., (asbca 2023).

Opinion

DOCUMENT FOR PUBLIC RELEASE The decision issued on the date below is subject to an ASBCA Protective Order. This version has been approved for public release.

ARMED SERVICES BOARD OF CONTRACT APPEALS Appeals of - ) ) Kellogg Brown & Root Services, Inc. ) ASBCA Nos. 62681, 62843, 62844 ) Under Contract No. W912GB-13-C-0011 )

APPEARANCES FOR THE APPELLANT: Daniel J. Kraftson, Esq. Sean M. Howley, Esq. Jonathan J. Straw, Esq. Kraftson Caudle PLC McLean, VA

APPEARANCES FOR THE GOVERNMENT: Michael P. Goodman, Esq. Engineer Chief Trial Attorney Paul L. Huhtanen, Esq. Herbert J. Aldridge, Esq. Paul Cheverie, Esq. LuzDanielle O. Bolong, Esq. Engineer Trial Attorneys U.S. Army Engineer District, Europe OPINION BY ADMINISTRATIVE JUDGE HERZFELD ON THE GOVERNMENT’S MOTION TO AMEND ITS ANSWER

The United States Army Corps of Engineers (Corps of Engineers) moves to amend its answer to add an affirmative defense that Kellogg Brown & Root Services, Inc. (KBR) made material misrepresentations in its proposal, rendering the fully-performed contract void ab initio. For the reasons discussed below, we grant the Corps of Engineers’ motion to amend its answer to add the material misrepresentation affirmative defense. The Board will consider this legal defense on the merits.

BACKGROUND

On July 9, 2013, the Corps of Engineers and KBR executed Contract No. W912GB-13-C-0011 for a firm, fixed-price amount of $134,211,592 to construct an Aegis Ashore Missile Defense System site on Deveselu Air Base in Deveselu, Romania (R4, tab 3 at 1-2); Kellogg Brown & Root Servs., Inc., ASBCA No. 62681 et al., 22-1 BCA ¶ 37,974 at 184,424. Later in July, two unsuccessful offerors protested the award to the U.S. Government Accountability Office (GAO), asserting that the Corps of Engineers conducted an improper price realism analysis, which should have found KBR’s price unrealistically low, and that the agency should have DOCUMENT FOR PUBLIC RELEASE The decision issued on the date below is subject to an ASBCA Protective Order. This version has been approved for public release.

given the protesters higher technical ratings and KBR lower technical ratings. AMEC Programs, Inc., B-408708 et seq., Dec. 4, 2013, 2014 CPD ¶ 50 at 7-9. On December 4, 2013, GAO denied the protests, concluding that (1) the Corps of Engineers’ price realism analysis was reasonable and (2) because neither protester argued that “their own proposal should have been found technically superior to KBR’s” and the price disparity in the proposals, neither protester could show a “reasonable possibility of prejudice” even if GAO accepted the “protesters’ technical evaluation challenges.” Id. at 9-10.

KBR substantially completed the project on December 19, 2015, on an expedited schedule to meet a presidential mandate to have the system operational “in the 2015 timeframe” (R4, tab 38; consolidated & amended compl. ¶ 73; gov’t answer to appellant’s consolidated & amended compl. ¶ 73); Kellogg Brown, 22-1 BCA ¶ 37,974 at 184,424.

Thereafter, KBR submitted a certified claim, which the Corps of Engineers denied, and KBR filed its first timely notice of appeal to this Board on September 24, 2020. Kellogg Brown, 21-1 BCA ¶ 37,974 at 184,425-27. Subsequently, the Corps of Engineers issued two demand letters seeking liquidated damages, which KBR timely appealed to this Board on March 8, 2021. Id. at 184,427-29. The Corps of Engineers moved to dismiss the appeals as untimely, which we denied on November 22, 2021. Id. A month later, the Corps of Engineers filed another motion to dismiss, asserting that the appeals should be dismissed because KBR’s certified claim did not include a sum certain in its claim. We have not ruled on that motion yet.1

On July 14, 2023, the Corps of Engineers moved to amend its answer to allege an affirmative defense that KBR’s material misrepresentations in its proposal induced the Corps of Engineers to enter the contract with KBR, which should result in voiding the contract. Fact discovery had ended on June 23, 2023. Notwithstanding the Corps of Engineers’ delay in formally amending its answer, KBR was aware of the potential affirmative defense before the conclusion of fact discovery (as reflected in its deposition of the contracting officer on these issues).

The Corps of Engineers’ proposed affirmative defense alleges KBR made eight material misrepresentations in its proposal, which the agency relied on in awarding the contract and defending the GAO protest. The Corps of Engineers asserts that those material misrepresentations render the contract void ab initio (gov’t mot. at 1-3).

1 We intend to seek supplemental briefing from the parties in light of the U.S. Court of Appeals for the Federal Circuit’s decision in ECC Int’l Constructors, LLC v. Sec’y of Army, 79 F.4th 1364 (Fed. Cir. 2023). 2 DOCUMENT FOR PUBLIC RELEASE The decision issued on the date below is subject to an ASBCA Protective Order. This version has been approved for public release.

First, the Corps of Engineers alleges KBR misrepresented that it had “obtained ‘firm subcontract and vendor quotes for over 97 percent of the tasks and materials’ in the project and only $3,637,386 or 2.93 percent of KBR’s proposal was estimated” (gov’t mot. at 1). In February 2014, after performance began, the Corps of Engineers realized that KBR did not have all their subcontractors “bought out” and that the “97 percent firm quotes and 2.93 percent” figure in KBR’s proposal had not been accurate (app. resp., ex. 1 – Deposition Transcript of Contracting Officer Rachael Raposa (CO tr.) at 15)). The Corps of Engineers did not attempt to void the contract at that point, “[b]ecause we wanted KBR to just get back on track” with an interest in “KBR performing the work” (CO tr. at 17-18).

Second, the Corps of Engineers alleges KBR misrepresented that “it had ‘firm fixed prices’ and ‘acceptance of subcontract terms and conditions from all major subcontractors’” (gov’t mot. at 1). Like the first alleged misrepresentation, the contracting officer stated she knew in February 2014 that “KBR had not bought out all its subs” (CO tr. at 21).

Third, the Corps of Engineers alleges KBR misrepresented the “scope and value of the work subcontracted to its ‘key subcontractor’ US International Development Consortium, Inc” (USIDC) (gov’t mot. at 1). The contracting officer acknowledged she knew in late 2013 that KBR intended to use a different subcontractor, Schneider Electric Buildings Critical Systems, Inc., instead of USIDC to do this security systems work (CO tr. at 109). For example, in the second partnering conference between the Corps of Engineers and KBR in 2014, the contracting officer noted that KBR’s performance seemed like a “bait and switch” (CO tr. at 115-16). Nevertheless, at that time, the Corps of Engineers wanted KBR to perform and did not consider defaulting KBR or seek to void the contract (CO tr. at 109, 117).

Fourth, the Corps of Engineers alleges KBR misrepresented that it “would self- perform 25 percent of the total amount of work by value under the Contract, as required by the Solicitation clause 52.236-1 ‘Performance of Work by the Contractor’” (gov’t mot. at 1-2). “[S]hortly after award when we couldn’t get anybody to the site” (and no later than September 2014), the contracting officer suspected that KBR might not comply with the requirement to perform 25% of the work (CO tr. at 137-38, 153, 159). However, the contracting officer hoped that KBR “would come forward” with more staff during the project because the Corps of Engineers was “driving towards performance” and “looking at the finish line” of the project (CO tr. at 155-56).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

United States v. Mississippi Valley Generating Co.
364 U.S. 520 (Supreme Court, 1961)
Foman v. Davis
371 U.S. 178 (Supreme Court, 1962)
Bell Atlantic Corp. v. Twombly
550 U.S. 544 (Supreme Court, 2007)
Ashcroft v. Iqbal
556 U.S. 662 (Supreme Court, 2009)
Long Island Savings Bank, FSB v. United States
503 F.3d 1234 (Federal Circuit, 2007)
J.E.T.S., Inc. v. The United States
838 F.2d 1196 (Federal Circuit, 1988)
Am-Pro Protective Agency, Inc. v. United States
281 F.3d 1234 (Federal Circuit, 2002)
Cencast Services, L.P. v. United States
729 F.3d 1352 (Federal Circuit, 2013)
Laguna Construction Company v. Defense
828 F.3d 1364 (Federal Circuit, 2016)
Canpro Investments, Ltd v. United States
130 Fed. Cl. 320 (Federal Claims, 2017)
Securiforce International America, LLC v. United States
879 F.3d 1354 (Federal Circuit, 2018)
Shell Oil Company v. United States
896 F.3d 1299 (Federal Circuit, 2018)
Pacific Architects & Engineers Inc. v. United States
491 F.2d 734 (Court of Claims, 1974)

Cite This Page — Counsel Stack

Bluebook (online)
Kellogg Brown & Root Services, Inc., Counsel Stack Legal Research, https://law.counselstack.com/opinion/kellogg-brown-root-services-inc-asbca-2023.